CALIFORNIA ISO MARKET NOTICE
Requested Client Action: Information Only
Date of Distribution: March 5, 2008
Categories: Settlements and Market Clearing
Subject: Adjustment of the Start-Up Cost Charge
___________________________________________________
Summary: The CAISO will adjust the Start-Up Cost charge effective January 1, 2008.
__________________________________________________
Main Text: In accordance with the June 19, 2001 FERC Order in ER04-835, the California ISO (CAISO) pays generators for Start-Up fuel costs incurred when generators are required to run in accordance with CAISO Dispatch Instructions and the must-offer provisions. As directed by FERC, the CAISO began reimbursing generators for such costs beginning on operating day June 21, 2001. In addition, the CAISO has been collecting a Start-Up charge on all metered load within the CAISO Control Area and Real-Time gross exports to other in-state control areas. The Start-Up rates have been based on an estimate of Start-Up fuel costs.
In the December 27, 2006 Order in ER04-835, the Federal Energy Regulatory Commission (FERC) directed the CAISO to allocate Start-Up Costs in the same manner as Minimum Load Cost Compensation (MLCC) costs. In its November 20, 2007 Order on rehearing, FERC clarified that the CAISO may use “Estimated” Start-Up Costs when allocating Start-Up Costs in the same manner as MLCC costs.
According to the CAISO Tariff (Section 40.12.4 Adjustment of the Start-Up Cost Charge), the CAISO may adjust the Start-Up Cost charge as needed. The CAISO needs to adjust the rates for Start-Up effective January 1, 2008 for two reasons: 1) due to the difference between actual Cost Demand and projected Cost Demand; and 2) use of an estimated Monthly Start-Up Cost Charge instead of a per megawatt-hour (MWh) rate.
Detailed calculations for the Start-Up Cost charge amount can be found on the CAISO website at: http://www.caiso.com/docs/2005/09/23/2005092315410212329.html.
The CAISO will continue to monitor the current Start-Up Cost Charge account to maintain sufficient, but not excess balances, to fully pay submitted invoices. If the CAISO Start-Up Trust account has a negative balance due to under-collection of Start-Up charges, Start-Up invoices submitted will be paid pro-rata as funds become available each month until the invoices are paid in full in accordance with Tariff Section 40.12.7.
___________________________________________________
For More Information Contact: Catherine Bodine at 916-351-2395 or cbodine@caiso.com

151 Blue Ravine Road, Folsom, CA 95630
Click here to update your profile or unsubscribe.
EA/ComPR/IPS/ds