The California ISO has posted new proposed revision requests (PRRs) reflecting edits to Business Practice Manuals (BPM). Revised BPMs that have completed the BPM change management process are posted in the BPM Library.
All PRRs and related activity are publicly available through the BPM change management site at http://bpmcm.caiso.com/Pages/default.aspx.
New Feature: BPM PRR updates will now be part of the ISO Daily Briefing in addition to being listed in the “Announcement” sections of the BPM change management tool. These updates will include PRRs that have become available for review, upcoming BPM meetings, and comment due dates. All registered BPM users should continue to reference the BPM Change Management tool to see current PRR status. To sign up for the Daily Briefing, please go to: http://www.caiso.com/informed/Pages/Notifications/Subscribe.aspx
The PRRs listed below have an open 10-business day comment or appeal period from May 5, 2020 through May 19, 2020.
New PRRs
PRR 1241 Transmission Planning Process BPM, Revision to update electromagnetic transients modeling requirements in Section 10
PRR 1242 Market Instruments BPM, Emergency PRR, Changes to hydro default energy bid formulation
PRR 1243 Reliability Requirements BPM, Emergency PRR, Energy storage and distributed energy resources 3 proxy demand resource
PRR 1244 Settlements and Billing BPM, Updated BPM configuration guide for CC 6045 over and under scheduling EIM settlement to align the documentation with current active settlement configuration
PRR 1245 Market Instruments BPM, Changes to market operations related to energy storage and distributed energy resource initiative
PRR 1246 Market Operations BPM, Changes to market operations related to energy storage and distributed energy resource initiative
PRR 1247 Demand Response BPM, Updates for energy storage and distributed energy resources 3B initiative
PRR 1248 Outage Management BPM, Updates for energy storage and distributed energy resources 3B to sections 3.4 and 4.1
PRR 1249 Generator Interconnection and Deliverability Allocation Procedures BPM, Emergency PRR, Implementation of FERC Order 845
PRR 1250 Generator Interconnection Procedures BPM, Emergency PRR, Implementation of FERC Order 845 for Generator Interconnection Procedure and Agreements
PRR 1251 Generator Management BPM, Emergency PRR, Implementation of FERC Order 845 changes to the Generator Interconnection Procedures
PRR 1252 Outage Management BPM, Language to clarify 24 hour outage rule
PRR 1253 Metering BPM, Energy storage and distributed energy resources 3B updates
ISO Recommendations
PRR 1235 Market Operations BPM, Manual dispatch codes
PRR 1236 Outage Management BPM, Emergency PRR, Removal of section 4.5 as an implementation of 1122 appeals decision
PRR 1237 Reliability Requirements BPM, Emergency PRR, Removal of reference to outage management bpm section 4.5 for 1122 appeals decision
PRR 1239 Reliability Requirements BPM, Stabilization of maximum import capability baseline calculation
PRR 1240 Congestion Revenue Rights BPM, Congestion revenue rights clarifications
ISO Final Decisions
PRR 1228 Managing Full Network Model BPM, Aliso Canyon tariff provisions - FERC order ER20-273
PRR 1229 Direct Telemetry BPM, Removing dispersive technologies
PRR 1230 Market Instruments BPM, Additional clarification and timeline for review of master file modifications
PRR 1231 Candidate CRR Holder Registration BPM, Update to congestion revenue rights holder application and corrected formatting
PRR 1232 Transmission Planning Process BPM, Consolidation of interregional transmission coordination information into a single chapter
PRR 1233 Settlements and Billing BPM, Updated configuration guides for CC 1001, CC 1101 and CC 3101 and created new BPM configuration guides for CC 3102 and CC 1102 with regard to settlement and invoicing impacts from Black start and system restoration phase 2 initiative
PRR 1234 Settlements and Billing BPM, Updated BPM configuration guides for CC 5701 and CC 5705 to allow for correct settlement of the reliability coordinator minimum charge for entities onboarding outside of April 1 timeline
BPM Library updates
The reference document on the ISO website lists the updated BPMs in the library.
The ISO may unilaterally make and implement revisions to the BPMs in emergency circumstances, as set forth in Sections 22.4.3 and 22.11 of the ISO Tariff and in Section 2.6 of the Business Practice Manual for BPM Change Management. An emergency PRR will continue through the BPM change management stakeholder process to obtain stakeholder input on the revisions and make other recommendations, as necessary.
Please note that affected parties must register in order to submit a PRR or written comments.
More information on the BPM change management process is available at http://www.caiso.com/rules/Pages/BusinessPracticeManuals/Default.aspx.