| Resource ID | Resource Name | Outage Type | Capacity (MW) | Curtailed (MW) | Zone Name | 
      
      
        | AGUCAL_5_SOLAR1 | Agua Caliente Solar | Planned | 290.00 | 62.00 | SDGE Gen | 
      
        | ALAMIT_7_UNIT 4 | ALAMITOS GEN STA. UNIT 4 | Forced | 335.67 | 95.67 | SCE Gen | 
      
        | ALAMIT_7_UNIT 5 | ALAMITOS GEN STA. UNIT 5 | Forced | 497.97 | 157.97 | SCE Gen | 
      
        | ALAMIT_7_UNIT 6 | ALAMITOS GEN STA. UNIT 6 | Forced | 495.00 | 35.00 | SCE Gen | 
      
        | ALTA3A_2_CPCE8 | CPC East - Alta Wind 8 | Planned | 150.00 | 0.00 | SCE Gen | 
      
        | ALTA4B_2_CPCW6 | CPC West - Alta Wind 6 | Planned | 150.00 | 0.00 | SCE Gen | 
      
        | ALTA6B_2_WIND11 | Alta Wind 11 | Forced | 90.00 | 0.00 | SCE Gen | 
      
        | ALTA6E_2_WIND10 | Alta Wind 10 | Forced | 138.00 | 0.00 | SCE Gen | 
      
        | AVSOLR_2_SOLAR | AV SOLAR RANCH 1 | Planned | 241.50 | 241.50 | SCE Gen | 
      
        | BIGCRK_2_EXESWD | BIG CREEK HYDRO PROJECT PSP | Planned | 820.00 | 163.00 | SCE Gen | 
      
        | BISHOP_1_ALAMO | BISHOP CREEK PLANT 2  AND  6 | Planned/Forced | 13.40 | 2.50 | SCE Gen | 
      
        | BISHOP_1_UNITS | BISHOP CREEK PLANT 3  AND  4 | Planned | 15.80 | 5.75 | SCE Gen | 
      
        | BLAST_1_WIND | Mountain View IV Wind | Planned | 49.00 | 0.00 | SCE Gen | 
      
        | BLKCRK_2_SOLAR1 | McCoy Station | Planned | 250.00 | 190.00 | SCE Gen | 
      
        | BORDER_6_UNITA1 | CalPeak Power Border Unit 1 | Planned | 51.25 | 3.25 | SDGE Gen | 
      
        | BUCKWD_1_QF | Buckwind Re-powering project | Forced | 16.50 | 0.00 | SCE Gen | 
      
        | BUTTVL_7_UNIT 1 | BUTT VALLEY HYDRO | Forced | 40.00 | 1.00 | PGAE North | 
      
        | CARBOU_7_PL4X5 | CARIBOU PH 2 UNIT 4 & 5 AGGREGATE | Forced | 122.00 | 8.00 | PGAE North | 
      
        | CCRITA_7_RPPCHF | Rancho Penasquitos Hydro Facility | Planned | 5.25 | 5.25 | SDGE Gen | 
      
        | CHINO_7_MILIKN | MN Milliken Genco LLC | Planned | 1.90 | 1.90 | SCE Gen | 
      
        | COLCEM_6_UNITS | CALIFORNIA PORTLAND CEMENT COMPANY | Forced | 25.00 | 25.00 | SCE Gen | 
      
        | COLEMN_2_UNIT | Coleman | Forced | 13.00 | 11.00 | PGAE North | 
      
        | COLGAT_7_UNIT 1 | COLGATE HYDRO UNIT 1 | Planned | 176.72 | 38.72 | PGAE North | 
      
        | COLGAT_7_UNIT 2 | COLGATE HYDRO UNIT 2 | Planned/Forced | 175.67 | 37.67 | PGAE North | 
      
        | COLTON_6_AGUAM1 | AGUA MANSA UNIT 1 (CITY OF COLTON) | Forced | 43.00 | 2.00 | SCE Gen | 
      
        | COLUSA_2_PL1X3 | Colusa Generating Station | Forced | 641.00 | 59.10 | PGAE North | 
      
        | CONTRL_1_CASAD1 | Mammoth G1 | Forced | 10.00 | 3.60 | SCE Gen | 
      
        | CONTRL_1_CASAD3 | Mammoth G3 | Forced | 14.00 | 4.10 | SCE Gen | 
      
        | CONTRL_1_LUNDY | LUNDY | Forced | 3.00 | 2.39 | SCE Gen | 
      
        | CRSTWD_6_KUMYAY | Kumeyaay Wind Farm | Forced | 50.00 | 0.00 | SDGE Gen | 
      
        | DSRTSN_2_SOLAR1 | Desert Sunlight 300 | Planned/Forced | 300.00 | 120.96 | SCE Gen | 
      
        | DSRTSN_2_SOLAR2 | Desert Sunlight 250 | Planned | 250.00 | 0.00 | SCE Gen | 
      
        | ELCAJN_6_LM6K | El Cajon Energy Center | Forced | 48.10 | 0.00 | SDGE Gen | 
      
        | ELECTR_7_PL1X3 | ELECTRA PH UNIT 1 & 2 AGGREGATE | Forced | 101.50 | 101.50 | PGAE North | 
      
        | ELSEGN_2_UN1011 | El Segundo Energy Center 5/6 | Forced | 263.00 | 12.00 | SCE Gen | 
      
        | ELSEGN_2_UN2021 | El Segundo Energy Center 7/8 | Forced | 263.68 | 12.68 | SCE Gen | 
      
        | ENCINA_7_EA3 | ENCINA UNIT 3 | Forced | 110.00 | 110.00 | SDGE Gen | 
      
        | ENERSJ_2_WIND | ESJ Wind Energy | Planned | 155.10 | 0.00 | SDGE Gen | 
      
        | ENWIND_2_WIND2 | Ridgetop I | Forced | 65.00 | 36.80 | SCE Gen | 
      
        | ESCNDO_6_PL1X2 | MMC Escondido Aggregate | Forced | 48.71 | 0.00 | SDGE Gen | 
      
        | ESCNDO_6_UNITB1 | CalPeak Power Enterprise Unit 1 | Planned | 48.04 | 0.00 | SDGE Gen | 
      
        | ETIWND_2_FONTNA | FONTANALYTLE CREEK POWERHOUSE P | Planned | 2.56 | 2.06 | SCE Gen | 
      
        | ETIWND_6_MWDETI | ETIWANDA RECOVERY HYDRO | Planned | 24.00 | 24.00 | SCE Gen | 
      
        | ETIWND_7_MIDVLY | MN Mid Valley Genco  LLC | Planned | 2.10 | 0.40 | SCE Gen | 
      
        | ETIWND_7_UNIT 4 | ETIWANDA GEN STA. UNIT 4 | Forced | 320.00 | 70.00 | SCE Gen | 
      
        | FMEADO_7_UNIT | FRENCH MEADOWS HYDRO | Forced | 18.00 | 2.10 | PGAE North | 
      
        | GARNET_1_UNITS | GARNET GREEN POWER PROJECT AGGREGATE | Forced | 16.50 | 1.50 | SCE Gen | 
      
        | GARNET_1_WINDS | Garnet Winds Aggregation | Forced | 22.50 | 1.50 | SCE Gen | 
      
        | GLNARM_7_UNIT 2 | GLEN ARM UNIT 2 | Forced | 22.30 | 22.30 | SCE Gen | 
      
        | GOLETA_6_ELLWOD | ELLWOOD ENERGY SUPPORT FACILITY | Forced | 54.00 | 54.00 | SCE Gen | 
      
        | GRIZLY_1_UNIT 1 | GRIZZLY HYDRO | Planned | 20.00 | 20.00 | PGAE North | 
      
        | GRNLF1_1_UNITS | GREENLEAF #1 COGEN AGGREGATE | Forced | 49.50 | 0.30 | PGAE North | 
      
        | HAASPH_7_PL1X2 | HAAS PH UNIT 1 & 2 AGGREGATE | Forced | 144.00 | 0.00 | PGAE North | 
      
        | HARBGN_7_UNITS | HARBOR COGEN COMBINED CYCLE | Planned/Forced | 109.01 | 14.01 | SCE Gen | 
      
        | HATCR2_7_UNIT | Hat Creek  #2 | Planned | 8.50 | 8.50 | PGAE North | 
      
        | HIDSRT_2_UNITS | HIGH DESERT POWER PROJECT AGGREGATE | Forced | 830.00 | 111.00 | SCE Gen | 
      
        | INDIGO_1_UNIT 1 | INDIGO PEAKER UNIT 1 | Forced | 44.00 | 7.00 | SCE Gen | 
      
        | INDIGO_1_UNIT 2 | INDIGO PEAKER UNIT 2 | Forced | 44.53 | 7.53 | SCE Gen | 
      
        | INDIGO_1_UNIT 3 | INDIGO PEAKER UNIT 3 | Forced | 43.69 | 6.69 | SCE Gen | 
      
        | INLDEM_5_UNIT 1 | Inland Empire Energy Center, Unit 1 | Forced | 376.20 | 36.19 | SCE Gen | 
      
        | INLDEM_5_UNIT 2 | Inland Empire Energy Center, Unit 2 | Forced | 366.32 | 104.31 | SCE Gen | 
      
        | IVWEST_2_SOLAR1 | Imperial Valley West ( Q # 608) | Planned | 150.00 | 0.00 | SDGE Gen | 
      
        | KERKH1_7_UNIT 1 | KERKHOFF PH 1 UNIT #1 | Planned | 13.00 | 13.00 | PGAE North | 
      
        | KERKH1_7_UNIT 3 | KERKHOFF PH 1 UNIT #3 | Planned | 12.80 | 12.80 | PGAE North | 
      
        | KERRGN_1_UNIT 1 | KERN RIVER HYDRO UNITS 1-4 AGGREGATE | Forced | 25.60 | 25.60 | SCE Gen | 
      
        | KILARC_2_UNIT 1 | KILARC HYDRO | Planned | 3.20 | 1.60 | PGAE North | 
      
        | LARKSP_6_UNIT 1 | LARKSPUR PEAKER UNIT 1 | Forced | 46.10 | 4.10 | SDGE Gen | 
      
        | LARKSP_6_UNIT 2 | LARKSPUR PEAKER UNIT 2 | Forced | 47.98 | 6.98 | SDGE Gen | 
      
        | LAROA1_2_UNITA1 | LR1 | Planned | 180.00 | 180.00 | SDGE Gen | 
      
        | LAROA2_2_UNITA1 | LR2 | Forced | 322.00 | 27.00 | SDGE Gen | 
      
        | MANZNA_2_WIND | Manzana Wind | Forced | 189.00 | 0.00 | SCE Gen | 
      
        | MIRLOM_6_PEAKER | Mira Loma Peaker | Forced | 46.00 | 0.00 | SCE Gen | 
      
        | MONLTH_6_BOREL | BOREL HYDRO UNITS 1-3 AGGREGATE | Planned/Forced | 11.00 | 11.00 | SCE Gen | 
      
        | MOORPK_7_UNITA1 | WEME- Simi Valley Landfill | Planned | 2.49 | 0.99 | SCE Gen | 
      
        | MRCHNT_2_PL1X3 | Desert Star Energy Center | Forced | 494.58 | 39.58 | SCE Gen | 
      
        | MRGT_6_MEF2 | Miramar Energy Facility II | Planned | 47.90 | 0.00 | SDGE Gen | 
      
        | MRGT_6_MMAREF | Miramar Energy Facility | Planned | 48.00 | 48.00 | SDGE Gen | 
      
        | MRGT_7_UNITS | MIRAMAR COMBUSTION TURBINE AGGREGATE | Forced | 36.00 | 36.00 | SDGE Gen | 
      
        | MTWIND_1_UNIT 1 | Mountain View Power Project I | Planned/Forced | 44.40 | 0.00 | SCE Gen | 
      
        | MTWIND_1_UNIT 2 | Mountain View Power Project II | Planned | 22.20 | 0.00 | SCE Gen | 
      
        | MTWIND_1_UNIT 3 | Mountain View Power Project III | Forced | 22.44 | 0.66 | SCE Gen | 
      
        | NAROW1_2_UNIT | NARROWS PH 1 UNIT | Planned | 12.00 | 12.00 | PGAE North | 
      
        | NAROW2_2_UNIT | NARROWS PH 2 UNIT | Forced | 55.00 | 55.00 | PGAE North | 
      
        | NEENCH_6_SOLAR | Alpine Solar | Planned | 66.00 | 66.00 | SCE Gen | 
      
        | OGROVE_6_PL1X2 | Orange Grove Energy Center | Forced | 99.90 | 4.23 | SDGE Gen | 
      
        | OMAR_2_UNIT 1 | KERN RIVER COGENERATION CO. UNIT 1 | Forced | 78.00 | 6.20 | SCE Gen | 
      
        | OMAR_2_UNIT 2 | KERN RIVER COGENERATION CO. UNIT 2 | Forced | 78.11 | 4.41 | SCE Gen | 
      
        | OMAR_2_UNIT 3 | KERN RIVER COGENERATION CO. UNIT 3 | Forced | 81.41 | 5.21 | SCE Gen | 
      
        | OTMESA_2_PL1X3 | OTAY MESA ENERGY CENTER | Forced | 603.68 | 49.68 | SDGE Gen | 
      
        | PACLUM_6_UNIT | PACIFIC LUMBER (HUMBOLDT) | Forced | 28.80 | 28.80 | PGAE North | 
      
        | PADUA_2_ONTARO | ONTARIO/SIERRA HYDRO PSP | Planned/Forced | 1.92 | 1.22 | SCE Gen | 
      
        | PANDOL_6_UNIT | Covanta Delano, Inc. | Forced | 49.00 | 3.00 | SCE Gen | 
      
        | PANSEA_1_PANARO | Mesa Wind Project | Forced | 30.00 | 24.55 | SDGE Gen | 
      
        | PIT6_7_UNIT 1 | PIT PH 6 UNIT 1 | Forced | 39.00 | 0.00 | PGAE North | 
      
        | PIT7_7_UNIT 1 | PIT PH 7 UNIT 1 | Forced | 55.70 | 1.70 | PGAE North | 
      
        | POTTER_6_UNITS | Potter Valley | Forced | 10.10 | 8.30 | PGAE North | 
      
        | PWEST_1_UNIT | PACIFIC WEST 1 WIND GENERATION | Forced | 2.10 | 0.70 | SCE Gen | 
      
        | RECTOR_2_KAWEAH | KAWEAH PH 2 & 3 PSP AGGREGATE | Planned/Forced | 6.55 | 2.00 | SCE Gen | 
      
        | RECTOR_2_KAWH 1 | KAWEAH PH 1 UNIT 1 | Forced | 2.25 | 2.25 | SCE Gen | 
      
        | RECTOR_2_QF | RECTOR QFS | Forced | 19.50 | 14.00 | SCE Gen | 
      
        | REDOND_7_UNIT 5 | REDONDO GEN STA. UNIT 5 | Forced | 178.87 | 0.00 | SCE Gen | 
      
        | REDOND_7_UNIT 8 | REDONDO GEN STA. UNIT 8 | Forced | 495.90 | 245.90 | SCE Gen | 
      
        | RENWD_1_QF | Renwind re-powering project | Forced | 10.00 | 0.00 | SCE Gen | 
      
        | ROSMDW_2_WIND1 | Pacific Wind - Phase 1 | Planned | 140.00 | 8.00 | SDGE Gen | 
      
        | RTREE_2_WIND2 | Rising Tree 2 | Forced | 19.80 | 0.00 | SCE Gen | 
      
        | RVSIDE_2_RERCU3 | Riverside Energy Res. Ctr Unit 3 | Forced | 49.00 | 49.00 | SCE Gen | 
      
        | RVSIDE_2_RERCU4 | Riverside Energy Res. Ctr Unit 4 | Forced | 49.00 | 49.00 | SCE Gen | 
      
        | RVSIDE_6_RERCU1 | Riverside Energy Res. Ctr Unit 1 | Forced | 48.35 | 48.35 | SCE Gen | 
      
        | RVSIDE_6_RERCU2 | Riverside Energy Res. Ctr Unit 2 | Forced | 48.50 | 48.50 | SCE Gen | 
      
        | RVSIDE_6_SPRING | SPRINGS GENERATION PROJECT AGGREGATE | Forced | 36.00 | 36.00 | SCE Gen | 
      
        | SALTSP_7_UNITS | SALT SPRINGS HYDRO AGGREGATE | Forced | 46.00 | 46.00 | PGAE North | 
      
        | SAMPSN_6_KELCO1 | KELCO QUALIFYING FACILITY | Planned | 25.00 | 7.40 | SDGE Gen | 
      
        | SANTGO_6_COYOTE | GAS RECOVERY SYS. (COYOTE CANYON) | Forced | 9.99 | 5.49 | SCE Gen | 
      
        | SANWD_1_QF | San Gorgonio Farms Wind Farm | Planned | 31.00 | 7.70 | SCE Gen | 
      
        | SAUGUS_7_LOPEZ | MM Lopez Energy | Planned | 6.10 | 0.90 | SCE Gen | 
      
        | SBERDO_2_PSP3 | Mountainview Gen Sta. Unit 3 | Forced | 525.00 | 13.00 | SCE Gen | 
      
        | SBERDO_2_PSP4 | Mountainview Gen Sta. Unit 4 | Forced | 525.00 | 13.00 | SCE Gen | 
      
        | SBERDO_2_SNTANA | SANTA ANA PSP | Planned | 6.95 | 6.95 | SCE Gen | 
      
        | SBERDO_6_MILLCK | MILL CREEK PSP | Planned | 3.93 | 3.23 | SCE Gen | 
      
        | SLYCRK_1_UNIT 1 | SLY CREEK HYDRO | Planned | 13.00 | 0.00 | PGAE North | 
      
        | SPIAND_1_UNIT | SIERRA PACIFIC IND. (ANDERSON) | Forced | 5.70 | 5.70 | PGAE North | 
      
        | SPRGAP_1_UNIT 1 | SPRING GAP HYDRO | Planned | 7.00 | 7.00 | PGAE North | 
      
        | SPRGVL_2_TULESC | TULE RIVER HYDRO PLANT (SCE) | Forced | 2.50 | 0.00 | SCE Gen | 
      
        | SYCAMR_2_UNIT 1 | Sycamore Cogeneration Unit 1 | Planned | 85.00 | 9.64 | SCE Gen | 
      
        | SYCAMR_2_UNIT 2 | Sycamore Cogeneration Unit 2 | Planned | 85.00 | 9.55 | SCE Gen | 
      
        | SYCAMR_2_UNIT 3 | Sycamore Cogeneration Unit 3 | Forced | 85.00 | 8.37 | SCE Gen | 
      
        | SYCAMR_2_UNIT 4 | Sycamore Cogeneration Unit 4 | Planned | 85.00 | 8.96 | SCE Gen | 
      
        | TERMEX_2_PL1X3 | TDM | Forced | 625.00 | 22.00 | SDGE Gen | 
      
        | TIFFNY_1_DILLON | TIFFNY_1_DILLON | Forced | 45.00 | 1.00 | SCE Gen | 
      
        | TIGRCK_7_UNITS | TIGER CREEK HYDRO AGGREGATE | Forced | 62.00 | 62.00 | PGAE North | 
      
        | VALLEY_7_BADLND | VALLEY_7_BADLND | Forced | 1.30 | 0.40 | SCE Gen | 
      
        | VALLEY_7_UNITA1 | WM Energy, El Sobrante Landfill | Forced | 3.74 | 1.74 | SCE Gen | 
      
        | VESTAL_2_KERN | KERN RIVER PH 3 UNITS 1 & 2 AGGREGATE | Forced | 36.80 | 0.00 | SCE Gen | 
      
        | VINCNT_2_WESTWD | Oasis Power Plant | Planned | 60.00 | 9.00 | SCE Gen | 
      
        | WALCRK_2_CTG1 | Walnut Creek Energy Park Unit 1 | Planned | 96.43 | 0.00 | SCE Gen | 
      
        | WALCRK_2_CTG2 | Walnut Creek Energy Park Unit 2 | Planned | 96.91 | 0.00 | SCE Gen | 
      
        | WALCRK_2_CTG3 | Walnut Creek Energy Park Unit 3 | Planned | 96.65 | 0.00 | SCE Gen | 
      
        | WALCRK_2_CTG4 | Walnut Creek Energy Park Unit 4 | Planned | 96.49 | 0.00 | SCE Gen | 
      
        | WALCRK_2_CTG5 | Walnut Creek Energy Park Unit 5 | Planned | 96.65 | 0.00 | SCE Gen | 
      
        | WALNUT_7_WCOVCT | WALNUT_7_WCOVCT | Forced | 4.50 | 4.50 | SCE Gen | 
      
        | WHTWTR_1_WINDA1 | Whitewater Hill Wind Project | Forced | 61.50 | 22.50 | SCE Gen | 
      
        | ADLIN_1_UNITS | GEYSERS AIDLIN AGGREGATE | Planned | 22.00 | 6.00 |  | 
      
        | ALLGNY_6_HYDRO1 | Salmon Creek Hydroelectric Project | Forced | 0.52 | 0.00 |  | 
      
        | BALCHS_7_UNIT 1 | BALCH 1 PH UNIT 1 | Planned | 33.00 | 0.00 |  | 
      
        | BCTSYS_5_PWXDYN | BCTSYS_5_PWXDYN | Forced | 428.00 | 245.00 |  | 
      
        | BDGRCK_1_UNITS | BADGER CREEK LIMITED | Forced | 47.49 | 5.09 |  | 
      
        | BEARMT_1_UNIT | BEAR MOUNTAIN LIMITED | Forced | 47.49 | 1.79 |  | 
      
        | BELDEN_7_UNIT 1 | BELDEN HYDRO | Forced | 119.00 | 5.00 |  | 
      
        | BLCKBT_2_STONEY | BLACK BUTTE HYDRO | Forced | 6.20 | 6.20 |  | 
      
        | BLULKE_6_BLUELK | Blue Lake Power | Forced | 12.00 | 12.00 |  | 
      
        | BNNIEN_7_ALTAPH | ALTA POWER HOUSE | Planned | 1.00 | 1.00 |  | 
      
        | BRDSLD_2_HIWIND | High Winds Energy Center | Forced | 162.00 | 12.60 |  | 
      
        | BRDSLD_2_SHILO1 | Shiloh I Wind Project | Forced | 150.00 | 1.50 |  | 
      
        | BRDSLD_2_SHILO2 | SHILOH WIND PROJECT 2 | Planned | 150.00 | 4.00 |  | 
      
        | BRDSLD_2_SHLO3A | Shiloh III Wind Project, LLC | Forced | 102.50 | 8.50 |  | 
      
        | BRDSLD_2_SHLO3B | Shiloh IV Wind Project | Forced | 100.00 | 0.00 |  | 
      
        | BUCKCK_7_OAKFLT | Oak Flat | Planned | 1.30 | 1.30 |  | 
      
        | BUCKCK_7_PL1X2 | BUCKS CREEK AGGREGATE | Planned | 59.00 | 59.00 |  | 
      
        | CANTUA_1_SOLAR | Cantua Solar Station | Planned | 20.00 | 0.00 |  | 
      
        | CHALK_1_UNIT | CHALK CLIFF LIMITED | Forced | 47.49 | 4.79 |  | 
      
        | CHWCHL_1_BIOMAS | Chow II Biomass to Energy | Planned/Forced | 10.80 | 1.30 |  | 
      
        | CNTRVL_6_UNIT | Centerville | Forced | 6.40 | 6.40 |  | 
      
        | COCOPP_2_CTG1 | Marsh Landing 1 | Forced | 204.20 | 12.43 |  | 
      
        | COCOPP_2_CTG2 | Marsh Landing 2 | Forced | 202.70 | 11.74 |  | 
      
        | COCOPP_2_CTG3 | Marsh Landing 3 | Forced | 208.96 | 18.41 |  | 
      
        | COCOPP_2_CTG4 | Marsh Landing 4 | Forced | 204.29 | 11.95 |  | 
      
        | CSCCOG_1_UNIT 1 | SANTA CLARA CO-GEN | Forced | 7.00 | 0.00 |  | 
      
        | CSTRVL_7_PL1X2 | Marina Land Fill Gas | Planned | 4.53 | 1.53 |  | 
      
        | CUMBIA_1_SOLAR | Columbia Solar Energy II | Planned/Forced | 19.00 | 0.00 |  | 
      
        | DALYCT_1_FCELL | PGE San Francisco State Fuel Cell | Forced | 1.60 | 1.00 |  | 
      
        | DEADCK_1_UNIT | DEADCK_1_UNIT | Forced | 2.00 | 2.00 |  | 
      
        | DELTA_2_PL1X4 | DELTA ENERGY CENTER AGGREGATE | Forced | 880.00 | 100.00 |  | 
      
        | DIABLO_7_UNIT 1 | Diablo Canyon Unit 1 | Forced | 1150.00 | 0.00 |  | 
      
        | DINUBA_6_UNIT | DINUBA GENERATION PROJECT | Planned | 12.00 | 2.00 |  | 
      
        | DOUBLC_1_UNITS | DOUBLE "C" LIMITED | Forced | 52.23 | 3.53 |  | 
      
        | ELKCRK_6_STONYG | STONEY GORGE HYDRO AGGREGATE | Planned/Forced | 4.90 | 4.90 |  | 
      
        | ELKHIL_2_PL1X3 | ELK HILLS COMBINED CYCLE (AGGREGATE) | Forced | 551.70 | 72.70 |  | 
      
        | ELNIDP_6_BIOMAS | El Nido Biomass to Energy | Planned | 10.50 | 0.70 |  | 
      
        | ENWIND_2_WIND1 | Cameron Ridge | Forced | 47.10 | 23.20 |  | 
      
        | EXCHEC_7_UNIT 1 | EXCHEQUER HYDRO | Forced | 94.50 | 74.50 |  | 
      
        | FLOWD2_2_FPLWND | DIABLO WINDS | Forced | 18.60 | 0.00 |  | 
      
        | FORKBU_6_UNIT | HYPOWER, INC. (FORKS OF BUTTE) | Forced | 14.30 | 14.30 |  | 
      
        | GARNET_2_WIND2 | Karen Avenue Wind Farm | Planned | 11.70 | 1.38 |  | 
      
        | GATWAY_2_PL1X3 | GATEWAY GENERATING STATION | Forced | 562.50 | 59.50 |  | 
      
        | GEYS11_7_UNIT11 | GEYSERS UNIT 11 (HEALDSBURG) | Planned/Forced | 74.40 | 6.40 |  | 
      
        | GEYS12_7_UNIT12 | GEYSERS UNIT 12 (HEALDSBURG) | Planned | 57.00 | 10.00 |  | 
      
        | GEYS13_7_UNIT13 | GEYSERS UNIT 13 (HEALDSBURG) | Planned | 95.00 | 41.00 |  | 
      
        | GEYS14_7_UNIT14 | GEYSERS UNIT 14 (HEALDSBURG) | Planned | 70.00 | 19.00 |  | 
      
        | GEYS16_7_UNIT16 | GEYSERS UNIT 16 (HEALDSBURG) | Planned | 85.00 | 42.00 |  | 
      
        | GEYS17_7_UNIT17 | GEYSERS UNIT 17 (HEALDSBURG) | Planned | 60.00 | 5.00 |  | 
      
        | GEYS18_7_UNIT18 | GEYSERS UNIT 18 (HEALDSBURG) | Planned | 72.00 | 29.00 |  | 
      
        | GEYS20_7_UNIT20 | GEYSERS UNIT 20 (HEALDSBURG) | Planned | 62.00 | 27.00 |  | 
      
        | GIFFEN_6_SOLAR | Giffen Solar Station | Planned | 10.00 | 0.00 |  | 
      
        | GILROY_1_UNIT | GILROY COGEN AGGREGATE | Forced | 120.00 | 12.00 |  | 
      
        | GWFPWR_1_UNITS | HANFORD PEAKER PLANT | Forced | 98.46 | 53.12 |  | 
      
        | GYS5X6_7_UNITS | GEYSERS UNITS 5 & 6 AGGREGATE | Forced | 85.00 | 0.00 |  | 
      
        | GYS7X8_7_UNITS | GEYSERS UNITS 7 & 8 AGGREGATE | Forced | 82.00 | 39.00 |  | 
      
        | GYSRVL_7_WSPRNG | Sonoma CWA Warm Springs Hydro | Forced | 3.75 | 2.44 |  | 
      
        | HALSEY_6_UNIT | HALSEY HYDRO | Forced | 13.50 | 13.50 |  | 
      
        | HATRDG_2_WIND | Hatchet Ridge Wind Farm | Forced | 102.00 | 3.10 |  | 
      
        | HELMPG_7_UNIT 1 | HELMS PUMP-GEN UNIT 1 | Planned | 407.00 | 0.00 |  | 
      
        | HENRTA_6_UNITA1 | GWF HENRIETTA PEAKER PLANT UNIT 1 | Forced | 49.98 | 4.95 |  | 
      
        | HENRTA_6_UNITA2 | GWF HENRIETTA PEAKER PLANT UNIT 2 | Forced | 49.42 | 4.49 |  | 
      
        | HMLTBR_6_UNITS | HAMILTON BRANCH PH (AGGREGATE) | Forced | 4.90 | 4.90 |  | 
      
        | HURON_6_SOLAR | Huron Solar Station | Planned | 20.00 | 0.00 |  | 
      
        | HYTTHM_2_UNITS | HYATT-THERMALITO PUMP-GEN (AGGREGATE) | Planned/Forced | 933.10 | 730.10 |  | 
      
        | INTKEP_2_UNITS | CCSF Hetch_Hetchy Hydro Aggregate | Forced | 405.00 | 88.00 |  | 
      
        | INTMNT_3_RIVERSIDE | IPPDYN | Forced | 137.00 | 1.00 |  | 
      
        | KELSO_2_UNITS | Mariposa Energy | Forced | 196.00 | 4.32 |  | 
      
        | KERNFT_1_UNITS | KERN FRONT LIMITED | Forced | 52.40 | 3.10 |  | 
      
        | KIRKER_7_KELCYN | KELLER CANYON LANDFILL GEN FACILICITY | Planned | 3.56 | 1.91 |  | 
      
        | KRNCNY_6_UNIT | KERN CANYON | Planned | 11.50 | 1.00 |  | 
      
        | LAMONT_1_SOLAR5 | Redcrest Solar Farm | Planned | 16.66 | 1.46 |  | 
      
        | LAPAC_6_UNIT | LOUISIANA PACIFIC SAMOA | Forced | 20.00 | 20.00 |  | 
      
        | LAPLMA_2_UNIT 1 | La Paloma Generating Plant Unit #1 | Forced | 259.80 | 7.80 |  | 
      
        | LAPLMA_2_UNIT 2 | La Paloma Generating Plant Unit #2 | Forced | 260.20 | 4.20 |  | 
      
        | LAPLMA_2_UNIT 3 | La Paloma Generating Plant Unit #3 | Forced | 256.15 | 3.15 |  | 
      
        | LAPLMA_2_UNIT 4 | LA PALOMA GENERATING PLANT, UNIT #4 | Forced | 259.54 | 4.54 |  | 
      
        | LASSEN_6_AGV1 | AGV 1 | Planned | 1.80 | 1.80 |  | 
      
        | LECEF_1_UNITS | LOS ESTEROS ENERGY FACILITY AGGREGATE | Forced | 294.00 | 13.70 |  | 
      
        | LIVOAK_1_UNIT 1 | LIVE OAK LIMITED | Forced | 47.49 | 5.09 |  | 
      
        | LMEC_1_PL1X3 | Los Medanos Energy Center AGGREGATE | Forced | 561.29 | 7.29 |  | 
      
        | LODIEC_2_PL1X2 | Lodi Energy Center | Forced | 302.58 | 25.58 |  | 
      
        | MALAGA_1_PL1X2 | Malaga Power Aggregate | Planned | 96.00 | 3.99 |  | 
      
        | MERCFL_6_UNIT | MERCED FALLS | Forced | 3.50 | 3.50 |  | 
      
        | METEC_2_PL1X3 | Metcalf Energy Center | Forced | 593.16 | 18.16 |  | 
      
        | MIDWD_2_WIND1 | Windland Refresh 2 | Forced | 7.81 | 7.81 |  | 
      
        | MKTRCK_1_UNIT 1 | MCKITTRICK LIMITED | Forced | 47.49 | 2.99 |  | 
      
        | MOSSLD_7_UNIT 7 | MOSS LANDING UNIT 7 | Forced | 755.70 | 15.70 |  | 
      
        | MTNPOS_1_UNIT | MT.POSO COGENERATION CO. | Forced | 46.64 | 6.64 |  | 
      
        | NCPA_7_GP2UN3 | NCPA GEO PLANT 2 UNIT 3 | Planned | 42.42 | 42.42 |  | 
      
        | OAK C_7_UNIT 1 | OAKLAND STATION C GT UNIT 1 | Forced | 55.00 | 0.00 |  | 
      
        | OAK C_7_UNIT 3 | OAKLAND STATION C GT UNIT 3 | Forced | 55.00 | 0.00 |  | 
      
        | OLDRIV_6_BIOGAS | Bidart Old River 1 | Forced | 2.00 | 1.00 |  | 
      
        | OXMTN_6_LNDFIL | Ox Mountain Landfill Generating Plant | Planned | 10.62 | 1.72 |  | 
      
        | PINFLT_7_UNITS | PINE FLAT HYDRO AGGREGATE | Planned/Forced | 210.00 | 210.00 |  | 
      
        | PITTSP_7_UNIT 5 | PITTSBURG UNIT 5 | Forced | 312.00 | 30.00 |  | 
      
        | PITTSP_7_UNIT 6 | PITTSBURG UNIT 6 | Forced | 317.00 | 317.00 |  | 
      
        | PITTSP_7_UNIT 7 | PITTSBURG UNIT 7 | Planned | 530.00 | 130.00 |  | 
      
        | PLSNTG_7_LNCLND | Lincoln Landfill Power Plant | Forced | 4.98 | 3.18 |  | 
      
        | PNCHEG_2_PL1X4 | PANOCHE ENERGY CENTER (Aggregated) | Forced | 400.00 | 3.10 |  | 
      
        | PNCHPP_1_PL1X2 | Midway Peaking Aggregate | Forced | 119.91 | 11.37 |  | 
      
        | PNOCHE_1_UNITA1 | CalPeak Power Panoche Unit 1 | Planned | 52.01 | 4.01 |  | 
      
        | RAMON_2_SCEDYN | RAMON_2_SCEDYN | Planned | 471.60 | 92.60 |  | 
      
        | REDBLF_6_UNIT | RED BLUFF PEAKER PLANT | Forced | 44.00 | 2.00 |  | 
      
        | RICHMN_7_BAYENV | BAY ENVIRONMENTAL (NOVE POWER) | Forced | 2.50 | 2.50 |  | 
      
        | RTREE_2_WIND3 | Rising Tree 3 | Forced | 99.00 | 0.00 |  | 
      
        | RUSCTY_2_UNITS | Russell City Energy Center | Forced | 620.00 | 11.20 |  | 
      
        | SANTFG_7_UNITS | GEYSERS CALISTOGA AGGREGATE | Planned | 92.10 | 39.10 |  | 
      
        | SCEHOV_2_HOOVER | SCEHOV_2_HOOVER | Planned | 525.00 | 130.00 |  | 
      
        | SCHLTE_1_PL1X3 | Tracy Combined Cycle Power Plant | Forced | 332.28 | 20.21 |  | 
      
        | SIERRA_1_UNITS | HIGH SIERRA LIMITED | Forced | 52.43 | 3.13 |  | 
      
        | SKERN_6_SOLAR1 | South Kern Solar PV Plant | Forced | 20.00 | 6.00 |  | 
      
        | SLST13_2_SOLAR1 | Quinto Solar PV Project | Planned | 107.60 | 16.60 |  | 
      
        | SLUISP_2_UNITS | SAN LUIS (GIANELLI) PUMP-GEN (AGGREGATE) | Planned/Forced | 374.43 | 246.43 |  | 
      
        | SMUDGO_7_UNIT 1 | SONOMA POWER PLANT | Planned | 53.00 | 20.00 |  | 
      
        | SNMALF_6_UNITS | Sonoma County Landfill | Planned | 7.50 | 4.10 |  | 
      
        | SPICER_1_UNITS | SPICER HYDRO UNITS 1-3 AGGREGATE | Forced | 6.00 | 6.00 |  | 
      
        | STROUD_6_SOLAR | Stroud Solar Station | Planned | 20.00 | 0.00 |  | 
      
        | SUNRIS_2_PL1X3 | Sunrise Power Project AGGREGATE II | Forced | 586.02 | 33.02 |  | 
      
        | SUNSET_2_UNITS | MIDWAY SUNSET COGENERATION PLANT | Forced | 248.00 | 36.00 |  | 
      
        | SUTTER_2_PL1X3 | SUTTER POWER PLANT AGGREGATE | Forced | 525.00 | 0.00 |  | 
      
        | SWIFT_1_NAS | YERBA BUENA BATTERY | Forced | 4.80 | 4.80 |  | 
      
        | THMENG_1_UNIT 1 | THERMAL ENERGY DEV. CORP. | Forced | 18.50 | 18.50 |  | 
      
        | UKIAH_7_LAKEMN | UKIAH LAKE MENDOCINO HYDRO | Planned/Forced | 3.50 | 3.50 |  | 
      
        | USWNDR_2_SMUD | SOLANO WIND FARM | Forced | 102.18 | 0.00 |  | 
      
        | USWNDR_2_SMUD2 | Solano Wind Project Phase 3 | Forced | 127.80 | 0.00 |  | 
      
        | VACADX_1_UNITA1 | CalPeak Power Vaca Dixon Unit 1 | Planned | 50.61 | 2.61 |  | 
      
        | VICTOR_1_SOLAR4 | Adelanto Solar | Planned | 20.00 | 0.00 |  | 
      
        | WDFRDF_2_UNITS | WEST FORD FLAT AGGREGATE | Planned | 32.60 | 9.60 |  | 
      
        | WESTPT_2_UNIT | West Point Hydro Plant | Forced | 14.00 | 14.00 |  | 
      
        | WNDMAS_2_UNIT 1 | BUENA VISTA ENERGY, LLC | Forced | 38.00 | 0.00 |  |