Curtailed and Non-Operational Generating Units
Resource ID Resource Name Outage Type Capacity (MW) Curtailed (MW) Zone Name
ALTA6B_2_WIND11 Alta Wind 11 Forced 90.00 0.00 SCE Gen
ALTA6E_2_WIND10 Alta Wind 10 Forced 138.00 0.00 SCE Gen
ANAHM_7_CT ANAHEIM COMBUSTION TURBINE Forced 42.81 42.81 SCE Gen
ARBWD_6_QF Wind Resource II Forced 19.95 0.65 SCE Gen
BIGCRK_2_EXESWD BIG CREEK HYDRO PROJECT PSP Planned/Forced 820.00 767.00 SCE Gen
BISHOP_1_ALAMO BISHOP CREEK PLANT 2 AND 6 Planned/Forced 13.40 4.50 SCE Gen
BISHOP_1_UNITS BISHOP CREEK PLANT 3 AND 4 Forced 15.80 9.05 SCE Gen
BLAST_1_WIND Mountain View IV Wind Planned 49.00 0.00 SCE Gen
BLKCRK_2_SOLAR1 McCoy Station Planned 250.00 139.00 SCE Gen
BORDER_6_UNITA1 CalPeak Power Border Unit 1 Planned 51.25 3.25 SDGE Gen
BUCKWD_1_QF Buckwind Re-powering project Forced 16.50 1.50 SCE Gen
BUTTVL_7_UNIT 1 BUTT VALLEY HYDRO Forced 40.00 4.00 PGAE North
CARBOU_7_PL4X5 CARIBOU PH 2 UNIT 4 & 5 AGGREGATE Planned/Forced 122.00 122.00 PGAE North
CCRITA_7_RPPCHF Rancho Penasquitos Hydro Facility Planned 5.25 5.25 SDGE Gen
CHINO_7_MILIKN MN Milliken Genco LLC Planned 1.90 1.90 SCE Gen
CNTNLA_2_SOLAR1 Centinela Solar Energy I Forced 125.00 10.00 SDGE Gen
COLEMN_2_UNIT Coleman Forced 13.00 11.00 PGAE North
COLGAT_7_UNIT 1 COLGATE HYDRO UNIT 1 Planned 176.72 176.72 PGAE North
COLGAT_7_UNIT 2 COLGATE HYDRO UNIT 2 Forced 175.67 41.67 PGAE North
COLUSA_2_PL1X3 Colusa Generating Station Forced 641.00 15.80 PGAE North
CONTRL_1_CASAD1 Mammoth G1 Forced 10.00 2.80 SCE Gen
CONTRL_1_CASAD3 Mammoth G3 Forced 14.00 0.70 SCE Gen
CRSTWD_6_KUMYAY Kumeyaay Wind Farm Forced 50.00 0.00 SDGE Gen
DSABLA_7_UNIT De Sabla Hydro Forced 18.50 18.50 PGAE North
DSRTSN_2_SOLAR1 Desert Sunlight 300 Forced 300.00 0.00 SCE Gen
ELCAJN_7_GT1 EL CAJON Forced 16.36 16.36 SDGE Gen
ELDORO_7_UNIT 1 El Dorado Unit 1 Planned 11.00 11.00 PGAE North
ELDORO_7_UNIT 2 El Dorado Unit 2 Planned 11.00 11.00 PGAE North
ENWIND_2_WIND2 Ridgetop I Planned 65.00 43.20 SCE Gen
ESCNDO_6_UNITB1 CalPeak Power Enterprise Unit 1 Planned 48.04 0.00 SDGE Gen
ETIWND_2_FONTNA FONTANALYTLE CREEK POWERHOUSE P Planned 2.56 2.06 SCE Gen
ETIWND_6_MWDETI ETIWANDA RECOVERY HYDRO Planned 24.00 24.00 SCE Gen
ETIWND_7_MIDVLY MN Mid Valley Genco LLC Planned 2.10 1.00 SCE Gen
ETIWND_7_UNIT 4 ETIWANDA GEN STA. UNIT 4 Forced 320.00 70.00 SCE Gen
GARNET_1_UNITS GARNET GREEN POWER PROJECT AGGREGATE Forced 16.50 14.50 SCE Gen
GARNET_1_WINDS Garnet Winds Aggregation Forced 22.50 1.50 SCE Gen
GARNET_2_WIND2 Karen Avenue Wind Farm Planned 11.70 3.00 SCE Gen
GLNARM_7_UNIT 2 GLEN ARM UNIT 2 Forced 22.30 22.30 SCE Gen
GRNLF1_1_UNITS GREENLEAF #1 COGEN AGGREGATE Forced 49.50 0.30 PGAE North
HAASPH_7_PL1X2 HAAS PH UNIT 1 & 2 AGGREGATE Forced 144.00 0.00 PGAE North
HARBGN_7_UNITS HARBOR COGEN COMBINED CYCLE Forced 109.01 9.01 SCE Gen
HIDSRT_2_UNITS HIGH DESERT POWER PROJECT AGGREGATE Forced 830.00 63.00 SCE Gen
HUMBPP_1_UNITS3 Humboldt Bay Generating Station 3 Forced 65.08 0.00 PGAE North
HUMBPP_6_UNITS Humboldt Bay Generating Station 1 Forced 97.62 32.54 PGAE North
INDIGO_1_UNIT 1 INDIGO PEAKER UNIT 1 Forced 44.00 1.00 SCE Gen
INDIGO_1_UNIT 2 INDIGO PEAKER UNIT 2 Forced 44.53 1.53 SCE Gen
INDIGO_1_UNIT 3 INDIGO PEAKER UNIT 3 Forced 43.69 0.69 SCE Gen
IVWEST_2_SOLAR1 Imperial Valley West ( Q # 608) Planned/Forced 150.00 4.00 SDGE Gen
JAWBNE_2_NSRWND North Sky River Wind Project Forced 160.00 6.40 SCE Gen
KERKH2_7_UNIT 1 KERKHOFF PH 2 UNIT #1 Planned 153.90 153.90 PGAE North
KERRGN_1_UNIT 1 KERN RIVER HYDRO UNITS 1-4 AGGREGATE Planned/Forced 25.60 6.60 SCE Gen
LARKSP_6_UNIT 1 LARKSPUR PEAKER UNIT 1 Forced 46.10 2.10 SDGE Gen
LARKSP_6_UNIT 2 LARKSPUR PEAKER UNIT 2 Forced 47.98 3.98 SDGE Gen
LAROA1_2_UNITA1 LR1 Planned 180.00 180.00 SDGE Gen
LAROA2_2_UNITA1 LR2 Forced 322.00 17.00 SDGE Gen
MANZNA_2_WIND Manzana Wind Forced 189.00 0.00 SCE Gen
MDFKRL_2_PROJCT MIDDLE FORK AND RALSTON PSP Planned 218.39 69.00 PGAE North
MNDALY_7_UNIT 1 MANDALAY GEN STA. UNIT 1 Planned 215.00 0.00 SCE Gen
MNDALY_7_UNIT 2 MANDALAY GEN STA. UNIT 2 Planned 215.29 0.00 SCE Gen
MONLTH_6_BOREL BOREL HYDRO UNITS 1-3 AGGREGATE Planned/Forced 11.00 11.00 SCE Gen
MOORPK_7_UNITA1 WEME- Simi Valley Landfill Planned 2.49 2.49 SCE Gen
MRCHNT_2_PL1X3 Desert Star Energy Center Forced 494.58 4.58 SCE Gen
MRGT_6_MMAREF Miramar Energy Facility Planned 48.00 48.00 SDGE Gen
MTWIND_1_UNIT 1 Mountain View Power Project I Planned/Forced 44.40 0.00 SCE Gen
MTWIND_1_UNIT 2 Mountain View Power Project II Planned 22.20 0.00 SCE Gen
MTWIND_1_UNIT 3 Mountain View Power Project III Forced 22.44 1.32 SCE Gen
NAROW2_2_UNIT NARROWS PH 2 UNIT Forced 55.00 55.00 PGAE North
OMAR_2_UNIT 1 KERN RIVER COGENERATION CO. UNIT 1 Forced 78.00 1.10 SCE Gen
OMAR_2_UNIT 2 KERN RIVER COGENERATION CO. UNIT 2 Forced 78.11 0.11 SCE Gen
OMAR_2_UNIT 3 KERN RIVER COGENERATION CO. UNIT 3 Forced 81.41 1.41 SCE Gen
OTMESA_2_PL1X3 OTAY MESA ENERGY CENTER Forced 603.68 12.68 SDGE Gen
PADUA_2_ONTARO ONTARIO/SIERRA HYDRO PSP Planned 1.92 1.42 SCE Gen
PANDOL_6_UNIT Covanta Delano, Inc. Forced 49.00 3.00 SCE Gen
PANSEA_1_PANARO Mesa Wind Project Forced 30.00 21.61 SCE Gen
PIT5_7_PL3X4 PIT PH 5 UNITS 3 & 4 AGGREGATE Planned 82.00 82.00 PGAE North
PIT7_7_UNIT 1 PIT PH 7 UNIT 1 Forced 55.70 1.70 PGAE North
POEPH_7_UNIT 1 POE HYDRO UNIT 1 Planned 69.00 69.00 PGAE North
POEPH_7_UNIT 2 POE HYDRO UNIT 2 Planned 68.50 68.50 PGAE North
POTTER_6_UNITS Potter Valley Planned/Forced 10.10 10.10 PGAE North
PWEST_1_UNIT PACIFIC WEST 1 WIND GENERATION Forced 2.10 2.10 SCE Gen
RCKCRK_7_UNIT 2 ROCK CREEK HYDRO UNIT 2 Planned 56.90 56.90 PGAE North
RECTOR_2_QF RECTOR QFS Forced 19.50 0.00 SCE Gen
RENWD_1_QF Renwind re-powering project Forced 10.00 0.00 SCE Gen
ROSMDW_2_WIND1 Pacific Wind - Phase 1 Forced 140.00 8.00 SDGE Gen
RVSIDE_2_RERCU3 Riverside Energy Res. Ctr Unit 3 Planned 49.00 49.00 SCE Gen
RVSIDE_2_RERCU4 Riverside Energy Res. Ctr Unit 4 Planned 49.00 49.00 SCE Gen
SAMPSN_6_KELCO1 KELCO QUALIFYING FACILITY Planned 25.00 7.40 SDGE Gen
SANTGO_6_COYOTE GAS RECOVERY SYS. (COYOTE CANYON) Forced 9.99 7.98 SCE Gen
SANWD_1_QF San Gorgonio Farms Wind Farm Planned 31.00 3.61 SCE Gen
SAUGUS_7_LOPEZ MM Lopez Energy Planned 6.10 0.90 SCE Gen
SBERDO_2_SNTANA SANTA ANA PSP Planned 6.95 5.95 SCE Gen
SBERDO_6_MILLCK MILL CREEK PSP Planned 3.93 3.23 SCE Gen
SLYCRK_1_UNIT 1 SLY CREEK HYDRO Forced 13.00 5.00 PGAE North
SNDBAR_7_UNIT 1 SAND BAR HYDRO Forced 18.60 18.60 PGAE North
SPAULD_6_UNIT12 SPAULDING HYDRO PH 1 & 2 AGGREGATE Forced 11.40 7.00 PGAE North
SPRGVL_2_TULESC TULE RIVER HYDRO PLANT (SCE) Forced 2.50 1.20 SCE Gen
SYCAMR_2_UNIT 1 Sycamore Cogeneration Unit 1 Planned 85.00 5.12 SCE Gen
SYCAMR_2_UNIT 2 Sycamore Cogeneration Unit 2 Planned 85.00 3.10 SCE Gen
SYCAMR_2_UNIT 3 Sycamore Cogeneration Unit 3 Planned 85.00 2.10 SCE Gen
SYCAMR_2_UNIT 4 Sycamore Cogeneration Unit 4 Planned 85.00 2.47 SCE Gen
TERMEX_2_PL1X3 TDM Forced 625.00 4.00 SDGE Gen
TIFFNY_1_DILLON TIFFNY_1_DILLON Forced 45.00 0.00 SCE Gen
TRNSWD_1_QF FPL Energy C Wind Forced 38.97 23.97 SCE Gen
VALLEY_7_BADLND VALLEY_7_BADLND Forced 1.30 1.30 SCE Gen
VALLEY_7_UNITA1 WM Energy, El Sobrante Landfill Forced 3.74 1.94 SCE Gen
VERNON_6_MALBRG Malburg Generating Station Planned 134.00 70.00 SCE Gen
VESTAL_2_KERN KERN RIVER PH 3 UNITS 1 & 2 AGGREGATE Forced 36.80 16.30 SCE Gen
VINCNT_2_WESTWD Oasis Power Plant Planned 60.00 0.00 SCE Gen
WALCRK_2_CTG1 Walnut Creek Energy Park Unit 1 Planned 96.43 0.00 SCE Gen
WALCRK_2_CTG2 Walnut Creek Energy Park Unit 2 Planned 96.91 0.00 SCE Gen
WALCRK_2_CTG3 Walnut Creek Energy Park Unit 3 Planned 96.65 0.00 SCE Gen
WALCRK_2_CTG4 Walnut Creek Energy Park Unit 4 Planned 96.49 0.00 SCE Gen
WALCRK_2_CTG5 Walnut Creek Energy Park Unit 5 Planned 96.65 0.00 SCE Gen
WALNUT_7_WCOVCT WALNUT_7_WCOVCT Forced 4.50 4.50 SCE Gen
WHTWTR_1_WINDA1 Whitewater Hill Wind Project Forced 61.50 16.50 SCE Gen
ADERA_1_SOLAR1 Adera Solar Planned 20.00 6.00
ADLIN_1_UNITS GEYSERS AIDLIN AGGREGATE Planned 22.00 6.00
ALLGNY_6_HYDRO1 Salmon Creek Hydroelectric Project Forced 0.52 0.52
ANZA_6_SOLAR1 Seville Solar One Planned 20.00 2.60
BCTSYS_5_PWXDYN BCTSYS_5_PWXDYN Forced 428.00 128.00
BDGRCK_1_UNITS BADGER CREEK LIMITED Forced 47.49 2.99
BEARDS_7_UNIT 1 Beardsley Hydro Planned 11.50 0.00
BEARMT_1_UNIT Bear Mountain Limited Forced 47.49 1.09
BELDEN_7_UNIT 1 BELDEN HYDRO Planned/Forced 119.00 119.00
BLCKBT_2_STONEY BLACK BUTTE HYDRO Forced 6.20 0.00
BLULKE_6_BLUELK Blue Lake Power Forced
BNNIEN_7_ALTAPH ALTA POWER HOUSE Planned 1.00 0.00
BRDSLD_2_HIWIND High Winds Energy Center Forced 162.00 7.20
BRDSLD_2_MTZUM2 NextEra Energy Montezuma Wind II Planned 78.20 0.00
BRDSLD_2_SHILO1 Shiloh I Wind Project Forced 150.00 0.00
BRDSLD_2_SHILO2 SHILOH WIND PROJECT 2 Planned 150.00 4.00
BRDSLD_2_SHLO3A Shiloh III Wind Project, LLC Forced 102.50 4.50
BRDSLD_2_SHLO3B Shiloh IV Wind Project Forced 100.00 0.00
BUCKCK_7_PL1X2 BUCKS CREEK AGGREGATE Planned 59.00 34.00
CAPWD_1_QF Edom Hills Wind Farm Forced 19.55 2.05
CHALK_1_UNIT CHALK CLIFF LIMITED Forced 47.49 1.89
CHWCHL_1_BIOMAS Chow II Biomass to Energy Planned 10.80 1.30
CLRKRD_6_LIMESD Lime Saddle Hydro Forced 2.00 1.00
CNTRVL_6_UNIT Centerville Forced 6.40 6.40
COCOPP_2_CTG1 Marsh Landing 1 Forced 204.20 3.63
COCOPP_2_CTG2 Marsh Landing 2 Forced 202.70 2.98
COCOPP_2_CTG3 Marsh Landing 3 Forced 208.96 9.67
COCOPP_2_CTG4 Marsh Landing 4 Forced 204.29 3.13
CONTAN_1_UNIT Graphic Packaging Cogen Forced 27.70 27.70
COTTLE_2_FRNKNH Frankenheimer Power Plant Forced 5.30 0.00
CSTRVL_7_PL1X2 Marina Land Fill Gas Planned 4.53 2.53
DALYCT_1_FCELL PGE San Francisco State Fuel Cell Forced 1.60 1.60
DEADCK_1_UNIT DEADCK_1_UNIT Forced 2.00 2.00
DELTA_2_PL1X4 DELTA ENERGY CENTER AGGREGATE Forced 880.00 29.00
DINUBA_6_UNIT DINUBA GENERATION PROJECT Forced 12.00 0.00
DOUBLC_1_UNITS DOUBLE "C" LIMITED Forced 52.23 0.53
DSRTSL_2_SOLAR1 Desert Stateline Forced 299.99 276.99
ELKCRK_6_STONYG STONEY GORGE HYDRO AGGREGATE Forced 4.90 0.00
ELKHIL_2_PL1X3 ELK HILLS COMBINED CYCLE (AGGREGATE) Forced 551.70 48.70
ELNIDP_6_BIOMAS El Nido Biomass to Energy Planned 10.50 1.00
ENWIND_2_WIND1 Cameron Ridge Planned 47.10 20.40
EXCHEC_7_UNIT 1 EXCHEQUER HYDRO Planned 94.50 94.50
FLOWD2_2_FPLWND DIABLO WINDS Forced 18.60 0.00
FORKBU_6_UNIT HYPOWER, INC. (FORKS OF BUTTE) Forced 14.30 14.30
FROGTN_7_UTICA FROGTN_7_UTICA Forced 6.20 6.20
GATWAY_2_PL1X3 GATEWAY GENERATING STATION Forced 562.50 0.00
GEYS11_7_UNIT11 GEYSERS UNIT 11 (HEALDSBURG) Forced 74.40 7.40
GEYS12_7_UNIT12 GEYSERS UNIT 12 (HEALDSBURG) Forced 57.00 4.00
GEYS13_7_UNIT13 GEYSERS UNIT 13 (HEALDSBURG) Planned/Forced 95.00 10.00
GEYS14_7_UNIT14 GEYSERS UNIT 14 (HEALDSBURG) Forced 70.00 10.00
GEYS16_7_UNIT16 GEYSERS UNIT 16 (HEALDSBURG) Forced 85.00 85.00
GEYS17_7_UNIT17 GEYSERS UNIT 17 (HEALDSBURG) Planned 60.00 0.00
GEYS18_7_UNIT18 GEYSERS UNIT 18 (HEALDSBURG) Forced 72.00 72.00
GEYS20_7_UNIT20 GEYSERS UNIT 20 (HEALDSBURG) Forced 62.00 62.00
GRIFFI_2_LSPDYN Griffith Energy Forced 570.00 370.00
GWFPWR_1_UNITS HANFORD PEAKER PLANT Forced 98.46 0.66
GYS5X6_7_UNITS GEYSERS UNITS 5 & 6 AGGREGATE Forced 85.00 0.00
GYS7X8_7_UNITS GEYSERS UNITS 7 & 8 AGGREGATE Forced 82.00 4.00
GYSRVL_7_WSPRNG Sonoma CWA Warm Springs Hydro Forced 3.75 2.37
HATRDG_2_WIND Hatchet Ridge Wind Farm Forced 102.00 7.70
HELMPG_7_UNIT 1 HELMS PUMP-GEN UNIT 1 Planned 407.00 407.00
HENRTA_6_UNITA1 GWF HENRIETTA PEAKER PLANT UNIT 1 Forced 49.98 1.40
HENRTA_6_UNITA2 GWF HENRIETTA PEAKER PLANT UNIT 2 Forced 49.42 0.95
HMLTBR_6_UNITS HAMILTON BRANCH PH (AGGREGATE) Planned/Forced 4.90 4.90
HYTTHM_2_UNITS HYATT-THERMALITO PUMP-GEN (AGGREGATE) Planned/Forced 933.10 630.10
INTKEP_2_UNITS CCSF Hetch_Hetchy Hydro Aggregate Forced 405.00 33.00
INTMNT_3_RIVERSIDE IPPDYN Forced 137.00 1.00
KELSO_2_UNITS Mariposa Energy Forced 196.00 0.00
KERNFT_1_UNITS KERN FRONT LIMITED Forced 52.40 0.50
KIRKER_7_KELCYN KELLER CANYON LANDFILL GEN FACILICITY Forced 3.56 1.91
KRNCNY_6_UNIT KERN CANYON Planned 11.50 1.00
LAMONT_1_SOLAR3 Woodmere Solar Farm Planned/Forced 14.99 0.00
LAMONT_1_SOLAR4 Hayworth Solar Farm Planned 26.66 0.00
LAPAC_6_UNIT LOUISIANA PACIFIC SAMOA Forced 20.00 20.00
LAPLMA_2_UNIT 1 La Paloma Generating Plant Unit #1 Forced 259.80 4.80
LAPLMA_2_UNIT 2 La Paloma Generating Plant Unit #2 Forced 260.20 260.20
LAPLMA_2_UNIT 3 La Paloma Generating Plant Unit #3 Forced 256.15 56.15
LAPLMA_2_UNIT 4 LA PALOMA GENERATING PLANT, UNIT #4 Forced 259.54 8.54
LASSEN_6_AGV1 AGV 1 Planned 1.80 1.80
LECEF_1_UNITS LOS ESTEROS ENERGY FACILITY AGGREGATE Forced 294.00 2.40
LITLRK_6_SOLAR2 Palmdale 18 Planned/Forced 2.00 0.00
LIVOAK_1_UNIT 1 LIVE OAK LIMITED Forced 47.49 47.49
LMEC_1_PL1X3 Los Medanos Energy Center AGGREGATE Forced 561.29 5.29
LODIEC_2_PL1X2 Lodi Energy Center Forced 302.58 11.78
MALAGA_1_PL1X2 Malaga Power Aggregate Planned 96.00 0.00
MARCPW_6_SOLAR1 Maricopa West Solar PV Planned 20.00 4.00
MCSWAN_6_UNITS MC SWAIN HYDRO Planned 10.00 10.00
MERCFL_6_UNIT MERCED FALLS Forced 3.50 3.50
METEC_2_PL1X3 Metcalf Energy Center Forced 593.16 8.16
MIDWD_2_WIND1 Windland Refresh 2 Forced 7.81 7.81
MKTRCK_1_UNIT 1 MCKITTRICK LIMITED Forced 47.49 1.39
MNDOTA_1_SOLAR2 Citizen Solar B Planned 5.00 1.00
MOSSLD_7_UNIT 7 MOSS LANDING UNIT 7 Forced 755.00 15.00
MTNPOS_1_UNIT MT.POSO COGENERATION CO. Forced 46.64 4.64
NCPA_7_GP2UN3 NCPA GEO PLANT 2 UNIT 3 Planned 42.42 42.42
OAK C_7_UNIT 1 OAKLAND STATION C GT UNIT 1 Forced 55.00 0.00
OAK C_7_UNIT 3 OAKLAND STATION C GT UNIT 3 Forced 55.00 0.00
OILFLD_7_QFUNTS Nacimiento Hydroelectric Plant Forced 3.80 3.80
OLDRIV_6_BIOGAS Bidart Old River 1 Forced 2.00 1.00
OXMTN_6_LNDFIL Ox Mountain Landfill Generating Plant Forced 10.62 1.62
PARDEB_6_UNITS Pardee Power House Planned 30.00 10.00
PINFLT_7_UNITS PINE FLAT HYDRO AGGREGATE Planned/Forced 210.00 210.00
PITTSP_7_UNIT 6 PITTSBURG UNIT 6 Planned 317.00 317.00
PITTSP_7_UNIT 7 PITTSBURG UNIT 7 Planned 530.00 130.00
PLAINV_6_SOLAR3 Sierra Solar Greenworks LLC Planned 20.00 5.20
PNCHPP_1_PL1X2 Midway Peaking Aggregate Forced 119.91 60.79
PNOCHE_1_UNITA1 CalPeak Power Panoche Unit 1 Planned 52.01 4.01
PRIMM_2_SOLAR1 Silver State South Planned 250.00 195.00
RAMON_2_SCEDYN RAMON_2_SCEDYN Forced 471.60 93.60
REDBLF_6_UNIT RED BLUFF PEAKER PLANT Forced 44.00 0.00
RICHMN_7_BAYENV BAY ENVIRONMENTAL (NOVE POWER) Forced 2.50 2.50
RUSCTY_2_UNITS Russell City Energy Center Forced 620.00 0.00
SANTFG_7_UNITS GEYSERS CALISTOGA AGGREGATE Forced 92.10 34.10
SCEHOV_2_HOOVER SCEHOV_2_HOOVER Planned 525.00 211.00
SCHLTE_1_PL1X3 Tracy Combined Cycle Power Plant Forced 332.28 2.68
SIERRA_1_UNITS HIGH SIERRA LIMITED Forced 52.43 0.73
SKERN_6_SOLAR1 South Kern Solar PV Plant Forced 20.00 6.00
SLST13_2_SOLAR1 Quinto Solar PV Project Forced 107.60 44.00
SLUISP_2_UNITS SAN LUIS (GIANELLI) PUMP-GEN (AGGREGATE) Planned/Forced 374.43 246.43
SMUDGO_7_UNIT 1 SONOMA POWER PLANT Forced 53.00 25.00
SNMALF_6_UNITS Sonoma County Landfill Planned 7.50 4.10
STOILS_1_UNITS Chevron Richmond Refinery Forced 113.90 0.00
SUNRIS_2_PL1X3 Sunrise Power Project AGGREGATE II Forced 586.02 9.02
SUNSET_2_UNITS MIDWAY SUNSET COGENERATION PLANT Forced 248.00 11.00
SUNSHN_2_LNDFL Sunshine Gas Producers Forced 20.00 2.00
SWIFT_1_NAS YERBA BUENA BATTERY Forced 4.80 4.80
THMENG_1_UNIT 1 Tracy Biomass Forced 18.50 18.50
TUPMAN_1_BIOGAS ABEC Bidart-Stockale #1 Forced 0.60 0.60
UNCHEM_1_UNIT CONTRA COSTA CARBON PLANT Forced 19.00 14.00
USWND1_2_UNITS US WIND POWER#1(WALKER) Forced 38.90 38.90
USWND2_1_UNITS US WIND POWER#2(PATTERSON) Forced 138.50 138.50
USWNDR_2_SMUD SOLANO WIND FARM Forced 102.18 3.00
USWNDR_2_SMUD2 Solano Wind Project Phase 3 Forced 127.80 0.00
USWPFK_6_FRICK GREEN RIDGE POWER LLC (FRICK) Forced 10.90 10.90
VACADX_1_UNITA1 CalPeak Power Vaca Dixon Unit 1 Planned 50.61 2.61
VLYHOM_7_SSJID Woodward Power Plant Forced 3.00 0.00
WDFRDF_2_UNITS WEST FORD FLAT AGGREGATE Forced 32.60 32.60
WHEATL_6_LNDFIL G2 ENERGY, OSTROM ROAD LLC Forced 3.00 1.50
WISE_1_UNIT 1 Wise Hydro Unit 1 Planned 14.50 14.50
WNDMAS_2_UNIT 1 BUENA VISTA ENERGY, LLC Forced 38.00 0.00
ZOND_6_UNIT ZOND WINDSYSTEMS INC. Forced 17.10 17.10


Outage Summary
Zone Name Number Of Outages MW's
Planned Forced Limitation Shutdown
PGAE North 14 20 1041.23 853.22
SCE Gen 42 60 1558.01 210.40
SDGE Gen 7 12 322.02 249.61
55 154 5034.75 2106.04
Total 118 246 7956.01 3419.27


Report Generated on:
11/25/2015 15:15:04 (PPT)
Filtered Parameters:
Date = 11/25/2015
Resource = ALL
Area = ALL
States = ALL
Outage Origin = CAISO
Configurable Parameters:
Time = 3:15PM PPT

System conditions are dynamic and may change, affecting the accuracy of this report. This report includes all outages, curtailments and temporary operating constraints reflecting normal operations that are effective at the time of the report. Because outages may overlap or may not all be simultaneously in effect at the time of this report, Other real-time reports may indicate a different total outage/curtailment than this report. This report reflects the best available data at the date and time of the report. It is a snapshot of conditions existing at the time the report was posted. This report is initiated once daily 1515 Pacific Time.

The content of these pages is subject to change without notice. Decisions based on information contained within the California ISO web site are the visitor's sole responsibility.