Curtailed and Non-Operational Generating Units
Resource ID Resource Name Outage Type Capacity (MW) Curtailed (MW) Zone Name
ADLIN_1_UNITS GEYSERS AIDLIN AGGREGATE Forced 22.00 10.00 PGAE Gen
ADOBEE_1_SOLAR Adobe Solar Forced 20.00 0.00 PGAE Gen
ALAMIT_7_UNIT 2 ALAMITOS GEN STA. UNIT 2 Forced 175.00 85.00 SCE Gen
ALAMO_6_UNIT ALAMO POWER PLANT Forced 17.00 0.00 SCE Gen
ALTA3A_2_CPCE4 Alta Wind 4 Forced 102.00 3.00 SCE Gen
ALTA3A_2_CPCE5 Alta Wind 5 Forced 168.00 6.00 SCE Gen
ALTA3A_2_CPCE8 Alta Wind 8 Forced 150.00 0.00 SCE Gen
ALTA4A_2_CPCW1 Alta Wind 1 Forced 150.00 0.00 SCE Gen
ALTA4B_2_CPCW2 Alta Wind 2 Forced 150.00 6.00 SCE Gen
ALTA4B_2_CPCW3 Alta Wind 3 Forced 150.00 21.00 SCE Gen
ALTA4B_2_CPCW6 Mustang Hills Planned 150.00 6.00 SCE Gen
ALTA6B_2_WIND11 Alta Wind 11 Forced 90.00 0.35 SCE Gen
ALTA6E_2_WIND10 Alta Wind 10 Forced 138.00 12.60 SCE Gen
BALCHS_7_UNIT 1 BALCH 1 PH UNIT 1 Forced 33.00 2.00 PGAE South
BANGOR_6_HYDRO Virginia Ranch Dam Powerplant Forced 1.00 0.00 PGAE Gen
BCTSYS_5_PWXDYN BCTSYS_5_PWXDYN Forced 428.00 428.00 PGAE Gen
BGSKYN_2_AS2SR1 Antelope Solar 2 Forced 105.00 0.00 SCE Gen
BIGCRK_2_EXESWD BIG CREEK HYDRO PROJECT PSP Planned/Forced 820.00 479.00 SCE Gen
BIGSKY_2_SOLAR1 Antelope Big Sky Ranch Forced 20.00 0.00 SCE Gen
BIGSKY_2_SOLAR2 Big Sky Solar 4 Forced 40.00 0.00 SCE Gen
BIGSKY_2_SOLAR3 Big Sky Summer Forced 20.00 0.00 SCE Gen
BIGSKY_2_SOLAR4 Western Antelope Blue Sky Ranch B Forced 20.00 0.00 SCE Gen
BIGSKY_2_SOLAR5 Big Sky Solar 2 Forced 5.00 0.00 SCE Gen
BIGSKY_2_SOLAR6 Solverde 1 Forced 85.00 0.00 SCE Gen
BIGSKY_2_SOLAR7 Big Sky Solar 1 Forced 50.00 0.00 SCE Gen
BISHOP_1_ALAMO BISHOP CREEK PLANT 2 AND 6 Planned/Forced 13.40 6.00 SCE Gen
BISHOP_1_UNITS BISHOP CREEK PLANT 3 AND 4 Planned/Forced 15.80 2.75 SCE Gen
BLAST_1_WIND Mountain View IV Wind Planned 49.00 2.00 SCE Gen
BLCKBT_2_STONEY BLACK BUTTE HYDRO Forced 6.20 6.20 PGAE Gen
BLULKE_6_BLUELK Blue Lake Power Forced 12.00 12.00 PGAE Gen
BORDER_6_UNITA1 CalPeak Power Border Unit 1 Forced 51.25 3.25 SDGE Gen
BRDSLD_2_HIWIND High Winds Energy Center Forced 162.00 19.80 PGAE Gen
BRDSLD_2_MTZUM2 NextEra Energy Montezuma Wind II Forced 78.20 0.00 PGAE Gen
BRDSLD_2_MTZUMA FPL Energy Montezuma Wind Forced 36.80 0.00 PGAE Gen
BRDSLD_2_SHILO1 Shiloh I Wind Project Forced 150.00 12.00 PGAE Gen
BRDSLD_2_SHILO2 SHILOH WIND PROJECT 2 Forced 150.00 4.00 PGAE Gen
BRDSLD_2_SHLO3A Shiloh III Wind Project, LLC Forced 102.50 0.00 PGAE Gen
BRDSLD_2_SHLO3B Shiloh IV Wind Project Forced 100.00 9.80 PGAE Gen
BRODIE_2_WIND Coram Brodie Wind Project Forced 102.00 0.00 SCE Gen
BUCKCK_2_HYDRO Lassen Station Hydro Forced 0.99 0.99 PGAE Gen
BUCKWD_1_QF Buckwind Re-powering project Forced 16.50 0.00 SCE Gen
BUTTVL_7_UNIT 1 BUTT VALLEY HYDRO Forced 39.50 3.50 PGAE North
CALFTS_2_CFSSR1 California Flats Solar South Forced 150.00 0.00 PGAE Gen
CAMLOT_2_SOLAR2 Columbia Two Forced 15.00 15.00 SCE Gen
CCRITA_7_RPPCHF Rancho Penasquitos Hydro Facility Forced 5.25 5.25 SDGE Gen
CENTER_6_PEAKER Center Peaker Forced 47.11 0.00 SCE Gen
CHEVMN_2_UNITS CHEVRON U.S.A. UNITS 1 & 2 AGGREGATE Forced 124.87 0.00 SCE Gen
CHINO_6_SMPPAP AltaGas Pomona Energy Planned 44.00 44.00 SCE Gen
CHINO_7_MILIKN MN Milliken Genco LLC Forced 1.90 0.00 SCE Gen
CLRKRD_6_LIMESD Lime Saddle Hydro Forced 2.00 2.00 PGAE Gen
CNTRVL_6_UNIT Centerville Forced 6.40 6.40 PGAE Gen
COLGAT_7_UNIT 1 Colgate Powerhouse Unit 1 Forced 176.72 26.72 PGAE North
COLGAT_7_UNIT 2 Colgate Powerhouse Unit 2 Planned/Forced 175.67 175.67 PGAE North
CONTRL_1_LUNDY LUNDY Forced 3.00 2.35 SCE Gen
CONTRL_1_RUSHCK RUSH CREEK Forced 11.94 6.50 SCE Gen
CRESTA_7_PL1X2 CRESTA PH UNIT 1 & 2 AGGREGATE Planned 70.40 70.40 PGAE North
CRNEVL_6_CRNVA Crane Valley Planned 0.90 0.90 PGAE Gen
CRNEVL_6_SJQN 3 SAN JOAQUIN 3 Forced 4.20 4.20 PGAE Gen
CSTRVL_7_PL1X2 Marina Land Fill Gas Forced 4.53 0.00 PGAE South
DEERCR_6_UNIT 1 DEER CREEK Forced 7.00 0.00 PGAE North
DELTA_2_PL1X4 DELTA ENERGY CENTER AGGREGATE Planned/Forced 880.00 80.00 PGAE Gen
DINUBA_6_UNIT Dinuba Energy, Inc. Forced 12.00 12.00 PGAE South
DMDVLY_1_UNITS DIAMOND VALLEY LAKE PUMP-GEN PLANT Forced 21.00 21.00 SCE Gen
DREWS_6_PL1X4 Drews Generating Plant Forced 41.40 14.40 SCE Gen
DSFLWR_2_WS2SR1 Willow Springs 2 Forced 100.00 58.00 SCE Gen
DSRTSL_2_SOLAR1 Desert Stateline Forced 296.19 3.79 SCE Gen
DSRTSN_2_SOLAR2 Desert Sunlight 250 Forced 250.00 0.00 SCE Gen
DUANE_1_PL1X3 DONALD VON RAESFELD POWER PROJECT Forced 147.80 5.80 PGAE South
DVLCYN_1_UNITS DEVIL CANYON HYDRO UNITS 1-4 AGGREGATE Planned 236.80 16.80 SCE Gen
ELCABO_5_ECWSCEDYN El Cabo Wind Forced 298.00 12.00 EIM ARI
ELCABO_5_ECWSCEDYN El Cabo Wind Forced 298.00 12.00 SCE Gen
ELCAJN_6_EB1BT1 Eastern BESS 1 Planned 7.50 0.00 SDGE Gen
ELDORO_7_UNIT 1 El Dorado Unit 1 Forced 11.00 11.00 PGAE North
ELDORO_7_UNIT 2 El Dorado Unit 2 Forced 11.00 11.00 PGAE North
ELECTR_7_PL1X3 ELECTRA PH UNIT 1 & 2 AGGREGATE Planned 93.00 31.30 PGAE North
ELKCRK_6_STONYG STONEY GORGE HYDRO AGGREGATE Forced 4.90 4.90 PGAE Gen
ELKHIL_2_PL1X3 ELK HILLS COMBINED CYCLE (AGGREGATE) Forced 551.70 19.70 PGAE Gen
ELSEGN_2_UN1011 El Segundo Energy Center 5/6 Forced 263.00 16.00 SCE Gen
ELSEGN_2_UN2021 El Segundo Energy Center 7/8 Forced 263.68 16.68 SCE Gen
ENCINA_7_EA2 ENCINA UNIT 2 Forced 104.00 104.00 SDGE Gen
ENCINA_7_EA3 ENCINA UNIT 3 Forced 110.00 110.00 SDGE Gen
ENCINA_7_EA4 ENCINA UNIT 4 Forced 300.00 300.00 SDGE Gen
ENCINA_7_EA5 ENCINA UNIT 5 Forced 330.00 330.00 SDGE Gen
ENCINA_7_GT1 ENCINA GAS TURBINE UNIT 1 Forced 14.50 14.50 SDGE Gen
ESCNDO_6_UNITB1 CalPeak Power Enterprise Unit 1 Forced 48.04 0.04 SDGE Gen
ESQUON_6_LNDFIL Neal Road Landfill Generating Facility Forced 2.10 2.10 PGAE Gen
ETIWND_2_FONTNA FONTANALYTLE CREEK POWERHOUSE P Planned 2.56 1.76 SCE Gen
ETIWND_2_RTS010 SPVP010 Fontana RT Solar Forced 1.50 1.00 SCE Gen
ETIWND_2_RTS026 SPVP026 Forced 6.00 1.50 SCE Gen
ETIWND_2_UNIT1 ETIWND_2_UNIT1 Forced 33.60 29.60 SCE Gen
FAIRHV_6_UNIT FAIRHAVEN POWER CO. Forced 18.75 17.75 PGAE North
FLOWD2_2_FPLWND DIABLO WINDS Forced 18.00 0.00 PGAE Gen
FORKBU_6_UNIT HYPOWER, INC. (FORKS OF BUTTE) Forced 14.30 14.30 PGAE Gen
FRNTBW_6_SOLAR1 Frontier Solar Forced 20.00 0.00 PGAE Gen
FROGTN_1_UTICAA Angels Powerhouse Planned 1.40 1.40 PGAE Gen
GARNET_1_UNITS GARNET GREEN POWER PROJECT AGGREGATE Forced 16.50 12.00 SCE Gen
GARNET_1_WINDS Garnet Winds Aggregation Forced 22.50 0.00 SCE Gen
GARNET_2_DIFWD1 Difwind Planned 7.88 0.00 SCE Gen
GARNET_2_HYDRO Whitewater Hydro Forced 1.00 1.00 SCE Gen
GARNET_2_WIND2 Karen Avenue Wind Farm Planned 11.70 3.45 SCE Gen
GARNET_2_WIND4 Windustries Forced 9.80 0.00 SCE Gen
GARNET_2_WPMWD6 WINTEC PALM Forced 5.93 5.93 SCE Gen
GEYS11_7_UNIT11 GEYSERS UNIT 11 (HEALDSBURG) Forced 74.40 0.40 PGAE Gen
GEYS12_7_UNIT12 GEYSERS UNIT 12 (HEALDSBURG) Forced 57.00 17.00 PGAE Gen
GEYS13_7_UNIT13 GEYSERS UNIT 13 (HEALDSBURG) Forced 95.00 43.00 PGAE Gen
GEYS14_7_UNIT14 GEYSERS UNIT 14 (HEALDSBURG) Forced 70.00 16.00 PGAE Gen
GEYS16_7_UNIT16 GEYSERS UNIT 16 (HEALDSBURG) Forced 85.00 41.00 PGAE Gen
GEYS17_7_UNIT17 GEYSERS UNIT 17 (HEALDSBURG) Forced 60.00 2.00 PGAE Gen
GEYS18_7_UNIT18 GEYSERS UNIT 18 (HEALDSBURG) Forced 72.00 29.00 PGAE Gen
GEYS20_7_UNIT20 GEYSERS UNIT 20 (HEALDSBURG) Forced 62.00 25.00 PGAE Gen
GIFENS_6_BUGSL1 Burford Giffen Planned 20.00 0.00 PGAE Gen
GILROY_1_UNIT GILROY COGEN AGGREGATE Planned 120.00 0.00 PGAE South
GLNARM_7_UNIT 2 GLEN ARM UNIT 2 Forced 22.30 22.30 SCE Gen
GOLETA_6_EXGEN EXXON COMPANY USA Forced 48.20 48.20 SCE Gen
GONZLS_6_UNIT Johnson Canyon Landfill Forced 1.42 1.42 PGAE Gen
GRIZLY_1_UNIT 1 GRIZZLY HYDRO Forced 20.00 20.00 PGAE North
GRNLF1_1_UNITS Greenleaf 1 Planned 49.20 49.20 PGAE North
GRSCRK_6_BGCKWW BIG CREEK WATER WORKS - CEDAR FLAT Forced 5.00 5.00 PGAE Gen
GYS5X6_7_UNITS GEYSERS UNITS 5 & 6 AGGREGATE Forced 85.00 5.00 PGAE Gen
GYS7X8_7_UNITS GEYSERS UNITS 7 & 8 AGGREGATE Forced 82.00 6.00 PGAE Gen
HARBGN_7_UNITS HARBOR COGEN COMBINED CYCLE Forced 109.01 109.01 SCE Gen
HATRDG_2_WIND Hatchet Ridge Wind Farm Forced 102.00 8.00 PGAE Gen
HENRTA_6_SOLAR1 Lemoore 1 Forced 1.50 0.00 PGAE Gen
HIDSRT_2_UNITS HIGH DESERT POWER PROJECT AGGREGATE Forced 830.00 37.00 SCE Gen
HMLTBR_6_UNITS HAMILTON BRANCH PH (AGGREGATE) Planned/Forced 4.90 4.90 PGAE Gen
HUMBPP_1_UNITS3 Humboldt Bay Generating Station 3 Planned 65.08 16.27 PGAE North
HYTTHM_2_UNITS HYATT-THERMALITO PUMP-GEN (AGGREGATE) Planned/Forced 933.10 868.10 PGAE Gen
INDIGO_1_UNIT 2 INDIGO PEAKER UNIT 2 Forced 44.53 0.53 SCE Gen
INDVLY_1_UNITS Indian Valley Hydro Forced 3.01 3.01 PGAE North
INLDEM_5_UNIT 1 Inland Empire Energy Center, Unit 1 Planned 376.20 0.00 SCE Gen
INSKIP_2_UNIT INSKIP HYDRO Forced 8.00 8.00 PGAE North
INTKEP_2_UNITS CCSF Hetch_Hetchy Hydro Aggregate Forced 405.00 155.00 PGAE Gen
INTMNT_3_RIVERSIDE IPPDYN Forced 137.00 1.00 SCE Gen
JAWBNE_2_NSRWND North Sky River Wind Project Forced 160.00 11.20 SCE Gen
KELSO_2_UNITS Mariposa Energy Forced 198.03 198.03 PGAE Gen
KERKH1_7_UNIT 1 KERKHOFF PH 1 UNIT #1 Forced 13.00 13.00 PGAE North
KERKH1_7_UNIT 1 KERKHOFF PH 1 UNIT #1 Forced 13.00 13.00 PGAE South
KERKH1_7_UNIT 3 KERKHOFF PH 1 UNIT #3 Forced 12.80 12.80 PGAE North
KERKH1_7_UNIT 3 KERKHOFF PH 1 UNIT #3 Forced 12.80 12.80 PGAE South
KERRGN_1_UNIT 1 KERN RIVER HYDRO UNITS 1-4 AGGREGATE Forced 25.60 9.60 SCE Gen
KNTSTH_6_SOLAR Kent South Forced 20.00 1.41 PGAE South
KRAMER_1_SEGS37 LUZ SOLAR PARTNERS 3-7 AGGREGATE Planned 70.00 70.00 SCE Gen
KRNCNY_6_UNIT KERN CANYON Forced 11.50 11.50 PGAE South
LAPAC_6_UNIT LOUISIANA PACIFIC SAMOA Forced 20.00 20.00 PGAE Gen
LAPLMA_2_UNIT 1 La Paloma Generating Plant Unit #1 Forced 259.80 3.80 PGAE Gen
LAPLMA_2_UNIT 2 La Paloma Generating Plant Unit #2 Forced 260.20 8.20 PGAE Gen
LARKSP_6_UNIT 1 LARKSPUR PEAKER UNIT 1 Forced 46.10 2.10 SDGE Gen
LARKSP_6_UNIT 2 LARKSPUR PEAKER UNIT 2 Forced 47.98 4.98 SDGE Gen
LAROA2_2_UNITA1 LR2 Forced 322.00 7.00 SDGE Gen
LEBECS_2_UNITS Pastoria Energy Facility Planned 799.47 6.47 SCE Gen
LGHTHP_6_ICEGEN CARSON COGENERATION Forced 48.00 48.00 SCE Gen
LMEC_1_PL1X3 Los Medanos Energy Center AGGREGATE Planned/Forced 561.29 0.00 PGAE Gen
LODI25_2_UNIT 1 LODI GAS TURBINE Forced 23.80 23.80 PGAE Gen
LODIEC_2_PL1X2 Lodi Energy Center Forced 302.58 16.58 PGAE Gen
MALAGA_1_PL1X2 Malaga Power Aggregate Forced 96.00 8.00 PGAE Gen
MALCHQ_7_UNIT 1 MALACHA HYDRO L.P. Forced 32.50 0.00 PGAE Gen
MALIN_5_GCPDDYN Grant County Hydro Facilities Forced 125.00 0.00 PGAE Gen
MANZNA_2_WIND Manzana Wind Forced 189.00 19.50 SCE Gen
MCSWAN_6_UNITS MC SWAIN HYDRO Planned 10.00 10.00 PGAE South
MERCFL_6_UNIT Merced Falls Powerhouse Forced 3.50 3.50 PGAE South
METEC_2_PL1X3 Metcalf Energy Center Planned/Forced 593.16 1.16 PGAE Gen
MIRLOM_2_CORONA MWD Corona Hydroelectric Recovery Plant Forced 2.85 2.85 SCE Gen
MIRLOM_2_MLBBTA Mira Loma BESS A Forced 10.00 0.00 SCE Gen
MIRLOM_2_MLBBTB Mira Loma BESS B Forced 10.00 0.00 SCE Gen
MNDALY_6_MCGRTH McGrath Beach Peaker Forced 47.20 47.20 SCE Gen
MONLTH_6_BATTRY Tehachapi Storage Project Forced 7.99 0.00 SCE Gen
MONLTH_6_BOREL BOREL HYDRO UNITS 1-3 AGGREGATE Planned 11.00 11.00 SCE Gen
MONLTS_2_MONWD4 Monolith 4 Planned 4.75 0.00 SCE Gen
MONLTS_2_MONWD5 Monolith 5 Planned 4.04 0.00 SCE Gen
MONLTS_2_MONWD6 Monolith 6 Planned 5.25 0.00 SCE Gen
MONLTS_2_MONWD7 Monolith 7 Planned 4.76 0.00 SCE Gen
MOORPK_2_CALABS Calabasas Gas-to-Energy Facility Forced 6.96 6.96 SCE Gen
MRCHNT_2_PL1X3 Desert Star Energy Center Forced 494.58 4.58 SDGE Gen
MTNPOS_1_UNIT MT.POSO COGENERATION CO. Forced 46.64 0.00 PGAE South
MTWIND_1_UNIT 1 Mountain View Power Project I Planned/Forced 44.40 3.00 SCE Gen
MTWIND_1_UNIT 2 Mountain View Power Project II Planned/Forced 22.20 7.20 SCE Gen
MTWIND_1_UNIT 3 Mountain View Power Project III Forced 22.44 1.98 SCE Gen
NAROW2_2_UNIT Narrows Powerhouse Unit 2 Forced 55.00 43.50 PGAE North
NCPA_7_GP2UN3 NCPA GEO PLANT 2 UNIT 3 Forced 42.42 42.42 PGAE Gen
NGILAA_5_SDGDYN NGILAA_5_SDGDYN Planned 57.00 57.00 EIM ARI
NGILAA_5_SDGDYN NGILAA_5_SDGDYN Planned 57.00 57.00 SDGE Gen
OAK C_7_UNIT 1 OAKLAND STATION C GT UNIT 1 Forced 55.00 1.50 PGAE South
OAK C_7_UNIT 3 OAKLAND STATION C GT UNIT 3 Forced 55.00 1.00 PGAE South
OILFLD_7_QFUNTS Nacimiento Hydroelectric Plant Forced 3.80 3.80 PGAE South
ORTGA_6_ME1SL1 Merced 1 Planned 3.00 0.20 PGAE Gen
OTMESA_2_PL1X3 OTAY MESA ENERGY CENTER Forced 603.68 3.68 SDGE Gen
PACLUM_6_UNIT Humboldt Redwood Forced 28.80 6.80 PGAE North
PADUA_2_ONTARO ONTARIO/SIERRA HYDRO PSP Planned 1.92 1.42 SCE Gen
PANSEA_1_PANARO Mesa Wind Project Planned 30.00 21.68 SCE Gen
PGF1_2_PDRP34 Sunrun August 2018 Cohort 2 Forced 0.20 0.20 PGAE Gen
PHOENX_1_UNIT PHOENIX PH Forced 2.00 2.00 PGAE Gen
PINFLT_7_UNITS PINE FLAT HYDRO AGGREGATE Planned 210.00 210.00 PGAE Gen
PIT3_7_PL1X3 PIT PH 3 UNITS 1, 2 & 3 AGGREGATE Planned 70.60 24.60 PGAE North
PIT5_7_PL3X4 PIT PH 5 UNITS 3 & 4 AGGREGATE Forced 82.00 41.00 PGAE North
PLAINV_6_NLRSR1 North Lancaster Ranch Forced 20.00 0.00 SCE Gen
PLAINV_6_SOLARC Central Antelope Dry Ranch C Forced 20.00 0.00 SCE Gen
PNCHVS_2_SOLAR Panoche Valley Solar Forced 140.00 0.00 PGAE Gen
PNOCHE_1_UNITA1 CalPeak Power Panoche Unit 1 Forced 52.01 4.01 PGAE Gen
PWEST_1_UNIT PACIFIC WEST 1 WIND GENERATION Forced 2.10 2.10 SCE Gen
RAMON_2_SCEDYN RAMON_2_SCEDYN Forced 359.60 109.60 SCE Gen
RECTOR_2_KAWH 1 KAWEAH PH 1 UNIT 1 Planned 2.25 2.25 SCE Gen
REDOND_7_UNIT 6 REDONDO GEN STA. UNIT 6 Forced 175.00 55.00 SCE Gen
REEDLY_6_SOLAR Terzian Forced 1.23 0.00 PGAE Gen
RENWD_1_QF Renwind re-powering project Forced 10.00 0.00 SCE Gen
RICHMN_7_BAYENV BAY ENVIRONMENTAL (NOVE POWER) Forced 2.50 2.50 PGAE Gen
ROSMDW_2_WIND1 Pacific Wind - Phase 1 Planned 140.00 4.00 SCE Gen
RTREE_2_WIND2 Rising Tree 2 Forced 19.80 0.00 SCE Gen
SANDLT_2_SUNITS Mojave Solar Forced 275.00 137.50 SCE Gen
SANTFG_7_UNITS GEYSERS CALISTOGA AGGREGATE Forced 92.10 34.10 PGAE Gen
SANWD_1_QF San Gorgonio Farms Wind Farm Planned 31.00 3.92 SCE Gen
SBERDO_2_RTS005 SPVP005 Redlands RT Solar Forced 2.50 1.00 SCE Gen
SBERDO_2_RTS016 SPVP016 Redlands RT Solar Forced 1.50 1.00 SCE Gen
SBERDO_2_SNTANA SANTA ANA PSP Planned 6.95 5.55 SCE Gen
SBERDO_6_MILLCK MILL CREEK PSP Planned 3.93 2.73 SCE Gen
SCEC_1_PDRP17 CBP-DO-C-LSCE Forced 3.10 3.10 SCE Gen
SCEC_1_RDRR39 SEP-C-LSCE Forced 44.00 44.00 SCE Gen
SCEN_6_PDRP13 CBP-DO-N-LSCE Forced 3.12 3.12 SCE Gen
SCEN_6_RDRR13 SEP-N-LSCE Forced 11.00 11.00 SCE Gen
SCEW_2_PDRP35 CBP-DO-W-LSCE Forced 2.00 2.00 SCE Gen
SCEW_2_RDRR27 SEP-W-LSCE Forced 42.00 42.00 SCE Gen
SCHD_1_RDRR12 SEP-HD-LSCE Forced 3.00 3.00 SCE Gen
SCNW_6_PDRP05 CBP-DO-NW-LSCE Forced 1.10 1.10 SCE Gen
SCNW_6_RDRR11 SEP-NW-LSCE Forced 8.00 8.00 SCE Gen
SGREGY_6_SANGER Algonquin Power Sanger 2 Forced 48.30 48.30 PGAE Gen
SKERN_6_SOLAR1 South Kern Solar PV Plant Forced 20.00 1.00 PGAE South
SLUISP_2_UNITS SAN LUIS (GIANELLI) PUMP-GEN (AGGREGATE) Planned 374.43 134.43 PGAE Gen
SMUDGO_7_UNIT 1 SONOMA POWER PLANT Forced 53.00 1.00 PGAE Gen
SPAULD_6_UNIT12 SPAULDING HYDRO PH 1 & 2 AGGREGATE Forced 11.40 7.00 PGAE North
SPRGVL_2_TULE TULE RIVER HYDRO PLANT (PG&E) Forced 6.40 6.40 SCE Gen
SPRGVL_2_TULESC TULE RIVER HYDRO PLANT (SCE) Forced 2.50 2.50 SCE Gen
SUNRIS_2_PL1X3 Sunrise Power Project AGGREGATE II Forced 586.02 34.02 PGAE Gen
SUNSET_2_UNITS MIDWAY SUNSET COGENERATION PLANT Forced 248.00 12.00 PGAE South
SWIFT_1_NAS YERBA BUENA BATTERY Planned 4.80 3.30 PGAE South
SYCAMR_2_UNIT 1 Sycamore Cogeneration Unit 1 Forced 85.00 0.67 SCE Gen
SYCAMR_2_UNIT 2 Sycamore Cogeneration Unit 2 Forced 85.00 2.31 SCE Gen
SYCAMR_2_UNIT 3 Sycamore Cogeneration Unit 3 Forced 85.00 1.38 SCE Gen
SYCAMR_2_UNIT 4 Sycamore Cogeneration Unit 4 Forced 85.00 5.13 SCE Gen
TEHAPI_2_WIND1 Wind Wall Monolith 1 Forced 14.89 0.00 SCE Gen
TEHAPI_2_WIND2 Wind Wall Monolith 2 Forced 21.24 0.00 SCE Gen
TIFFNY_1_DILLON TIFFNY_1_DILLON Forced 45.00 1.00 SCE Gen
TKOPWR_6_HYDRO Bear Creek Hydroelectric Project Forced 2.83 2.83 PGAE Gen
TWISSL_6_SOLAR Nickel 1 ("NLH1") Forced 1.50 0.00 PGAE Gen
USWND2_1_WIND1 Golden Hills A Forced 42.96 1.79 PGAE Gen
USWND2_1_WIND2 Golden Hills B Forced 42.96 1.79 PGAE Gen
USWND2_1_WIND3 Golden Hills C Forced 46.00 0.00 PGAE Gen
USWNDR_2_SMUD SOLANO WIND FARM Planned/Forced 102.18 0.00 PGAE Gen
USWNDR_2_SMUD2 Solano Wind Project Phase 3 Planned/Forced 127.80 0.00 PGAE Gen
USWNDR_2_UNITS US WIND POWER(RUSSELL) Planned 8.00 0.00 PGAE Gen
USWPJR_2_UNITS Vasco Wind Forced 78.20 2.30 PGAE Gen
VACADX_1_NAS VACA-DIXON BATTERY Forced 1.85 1.85 PGAE North
VACADX_1_UNITA1 CalPeak Power Vaca Dixon Unit 1 Forced 50.61 2.61 PGAE Gen
VALLEY_5_REDMTN MWD Red Mountain Hydroelectric Recovery Forced 5.90 5.90 SCE Gen
VALLEY_5_RTS044 SPVP044 Forced 8.00 2.00 SCE Gen
VESTAL_2_KERN KERN RIVER PH 3 UNITS 1 & 2 AGGREGATE Forced 36.80 0.00 SCE Gen
VINCNT_2_WESTWD Oasis Power Plant Planned 59.00 4.00 SCE Gen
VOLTA_6_BAILCK Bailey Creek Ranch Forced 0.63 0.00 PGAE Gen
VSTAES_6_VESBT1 Vista Energy Storage Forced 40.00 0.00 SDGE Gen
WFRESN_1_SOLAR Joya Del Sol Forced 1.50 1.50 PGAE Gen
WHEATL_6_LNDFIL G2 ENERGY, OSTROM ROAD LLC Forced 3.55 1.95 PGAE Gen
WHTWTR_1_WINDA1 Whitewater Hill Wind Project Forced 61.50 11.50 SCE Gen
WISHON_6_UNITS Wishon/San Joaquin #1-A AGGREGATE Planned 18.40 7.20 PGAE Gen
WISTRA_2_WRSSR1 Wistaria Ranch Solar Planned 100.00 0.00 SDGE Gen
WNDMAS_2_UNIT 1 BUENA VISTA ENERGY, LLC Forced 38.00 1.00 PGAE Gen
WNDSTR_2_WIND Windstar Planned 120.00 4.00 SCE Gen
WRGHTP_7_AMENGY SMALL QF AGGREGATION - LOS BANOS Forced 2.50 1.50 PGAE Gen
ZOND_6_UNIT ZOND WINDSYSTEMS INC. Forced 17.10 17.10 PGAE Gen


Outage Summary
Zone Name Number Of Outages MW's
Planned Forced Limitation Shutdown
EIM ARI 1 1 12.00 57.00
PGAE Gen 21 87 1636.44 1063.39
PGAE North 7 17 218.44 375.93
PGAE South 4 17 28.01 66.60
SCE Gen 31 101 1298.40 588.92
SDGE Gen 3 14 25.63 920.75
Total 67 237 3218.92 3072.59


Report Generated on:
12/26/2018 08:30:00 (PPT)
Filtered Parameters:
Date = 12/27/2018
Resource = ALL
Area = ALL
States = ALL
Outage Origin = CAISO

System conditions are dynamic and may change, affecting the accuracy of this report. This report includes all outages, curtailments and temporary operating constraints reflecting normal operations that are effective at the time of the report. Because outages may overlap or may not all be simultaneously in effect at the time of this report, Other real-time reports may indicate a different total outage/curtailment than this report. This report reflects the best available data at the date and time of the report. It is a snapshot of conditions existing at the time the report was posted. This report is initiated once daily 1515 Pacific Time.

The content of these pages is subject to change without notice. Decisions based on information contained within the California ISO web site are the visitor's sole responsibility.