Curtailed and Non-Operational Generating Units
Resource ID Resource Name Outage Type Capacity (MW) Curtailed (MW) Zone Name
ADLIN_1_UNITS GEYSERS AIDLIN AGGREGATE Forced 22.00 9.00 PGAE Gen
ADMEST_6_SOLAR Adams East Planned 19.00 0.00 SCE Gen
ALAMIT_7_UNIT 1 ALAMITOS GEN STA. UNIT 1 Forced 174.56 24.56 SCE Gen
ALAMIT_7_UNIT 2 ALAMITOS GEN STA. UNIT 2 Forced 175.00 85.00 SCE Gen
ALAMIT_7_UNIT 4 ALAMITOS GEN STA. UNIT 4 Planned 335.67 335.67 SCE Gen
ALAMO_6_UNIT ALAMO POWER PLANT Forced 17.00 17.00 SCE Gen
ALTA3A_2_CPCE4 Alta Wind 4 Forced 102.00 3.00 SCE Gen
ALTA3A_2_CPCE5 Alta Wind 5 Forced 168.00 6.00 SCE Gen
ALTA4A_2_CPCW1 Alta Wind 1 Forced 150.00 13.50 SCE Gen
ALTA4B_2_CPCW2 Alta Wind 2 Forced 150.00 6.00 SCE Gen
ALTA4B_2_CPCW3 Alta Wind 3 Forced 150.00 12.00 SCE Gen
ALTA4B_2_CPCW6 Mustang Hills Planned 150.00 6.00 SCE Gen
ALTA6B_2_WIND11 Alta Wind 11 Forced 90.00 3.75 SCE Gen
ALTA6E_2_WIND10 Alta Wind 10 Forced 138.00 21.15 SCE Gen
ALTWD_1_QF Altwind Forced 28.84 18.34 SCE Gen
ANAHM_7_CT ANAHEIM COMBUSTION TURBINE Forced 42.81 42.81 SCE Gen
ATWELL_1_SOLAR Atwell Island PV Solar Generating Faci. Forced 20.00 0.00 PGAE South
AVENAL_6_AVPARK Avenal Park Solar Project Forced 6.00 0.00 PGAE South
BALCHS_7_UNIT 1 BALCH 1 PH UNIT 1 Forced 33.00 2.00 PGAE South
BALCHS_7_UNIT 3 BALCH 2 PH UNIT 3 Forced 54.60 54.60 PGAE South
BARRE_6_PEAKER Barre Peaker Planned 47.00 47.00 SCE Gen
BDGRCK_1_UNITS BADGER CREEK LIMITED Forced 48.08 6.08 PGAE South
BEARMT_1_UNIT Bear Mountain Limited Planned 49.21 49.21 PGAE Gen
BELDEN_7_UNIT 1 BELDEN HYDRO Planned 119.00 119.00 PGAE Gen
BIGCRK_2_EXESWD BIG CREEK HYDRO PROJECT PSP Planned/Forced 820.00 410.00 SCE Gen
BIGSKY_2_BSKSR6 Big Sky Solar 6 Planned 20.00 0.00 SCE Gen
BIGSKY_2_SOLAR1 Antelope Big Sky Ranch Planned 20.00 0.00 SCE Gen
BIGSKY_2_SOLAR2 Big Sky Solar 4 Planned/Forced 40.00 0.00 SCE Gen
BIGSKY_2_SOLAR3 Big Sky Summer Planned/Forced 20.00 4.00 SCE Gen
BIGSKY_2_SOLAR4 Western Antelope Blue Sky Ranch B Planned/Forced 20.00 0.00 SCE Gen
BIGSKY_2_SOLAR5 Big Sky Solar 2 Forced 5.00 5.00 SCE Gen
BIGSKY_2_SOLAR6 Solverde 1 Planned/Forced 85.00 0.00 SCE Gen
BIGSKY_2_SOLAR7 Big Sky Solar 1 Planned/Forced 50.00 0.00 SCE Gen
BISHOP_1_ALAMO BISHOP CREEK PLANT 2 AND 6 Planned 13.40 1.40 SCE Gen
BISHOP_1_UNITS BISHOP CREEK PLANT 3 AND 4 Planned 15.80 10.30 SCE Gen
BLAST_1_WIND Mountain View IV Wind Planned 49.00 2.00 SCE Gen
BLULKE_6_BLUELK Blue Lake Power Forced 12.00 12.00 PGAE Gen
BLYTHE_1_SOLAR2 Blythe Green 1 Forced 20.00 0.00 SCE Gen
BNNIEN_7_ALTAPH ALTA POWER HOUSE Planned 1.00 1.00 PGAE Gen
BORDER_6_UNITA1 CalPeak Power Border Unit 1 Forced 51.25 3.25 SDGE Gen
BRDSLD_2_HIWIND High Winds Energy Center Forced 162.00 10.80 PGAE Gen
BRDSLD_2_MTZUM2 NextEra Energy Montezuma Wind II Forced 78.20 0.00 PGAE Gen
BRDSLD_2_MTZUMA FPL Energy Montezuma Wind Forced 36.80 0.00 PGAE Gen
BRDSLD_2_SHILO1 Shiloh I Wind Project Forced 150.00 6.00 PGAE Gen
BRDSLD_2_SHILO2 SHILOH WIND PROJECT 2 Forced 150.00 8.00 PGAE Gen
BRDSLD_2_SHLO3A Shiloh III Wind Project, LLC Forced 102.50 2.05 PGAE Gen
BRDSLD_2_SHLO3B Shiloh IV Wind Project Forced 100.00 0.00 PGAE Gen
BRODIE_2_WIND Coram Brodie Wind Project Forced 102.00 3.00 SCE Gen
BUCKBL_2_PL1X3 Blythe Energy Center Planned 493.63 493.63 SCE Gen
BUCKCK_2_HYDRO Lassen Station Hydro Forced 0.99 0.99 PGAE Gen
BUCKCK_7_PL1X2 BUCKS CREEK AGGREGATE Planned 57.25 0.00 PGAE Gen
BUCKWD_1_QF Buckwind Re-powering project Forced 16.50 1.50 SCE Gen
BURNYF_2_UNIT 1 Burney Forest Power Forced 31.00 24.00 PGAE Gen
BUTTVL_7_UNIT 1 BUTT VALLEY HYDRO Planned 39.50 39.50 PGAE North
CAMPFW_7_FARWST CAMP FAR WEST HYDRO Planned 8.00 8.00 PGAE Gen
CENTER_2_RHONDO MWD Rio Hondo Hydroelectric Recovery Pla Forced 1.91 1.91 SCE Gen
CENTER_6_PEAKER Center Peaker Forced 47.11 0.00 SCE Gen
CHALK_1_UNIT CHALK CLIFF LIMITED Forced 48.67 3.67 PGAE Gen
CHINO_6_SMPPAP AltaGas Pomona Energy Forced 44.00 44.00 SCE Gen
CHINO_7_MILIKN MN Milliken Genco LLC Forced 1.90 1.90 SCE Gen
CHWCHL_1_BIOMAS Chow II Biomass to Energy Planned 10.80 10.80 PGAE South
CLRKRD_6_LIMESD Lime Saddle Hydro Forced 2.00 2.00 PGAE Gen
CNTRVL_6_UNIT Centerville Forced 6.40 6.40 PGAE Gen
COCOPP_2_CTG1 Marsh Landing 1 Forced 204.20 3.00 PGAE South
COCOPP_2_CTG2 Marsh Landing 2 Forced 202.70 2.34 PGAE South
COCOPP_2_CTG3 Marsh Landing 3 Forced 208.96 9.04 PGAE South
COCOPP_2_CTG4 Marsh Landing 4 Forced 204.29 2.49 PGAE South
COCOSB_6_SOLAR Oakley Solar Project Forced 1.50 0.00 PGAE Gen
COGNAT_1_UNIT Stockton Biomas Planned 45.00 45.00 PGAE Gen
COLGAT_7_UNIT 1 Colgate Powerhouse Unit 1 Planned/Forced 176.72 12.72 PGAE North
COLGAT_7_UNIT 2 Colgate Powerhouse Unit 2 Planned/Forced 175.67 11.67 PGAE North
COLUSA_2_PL1X3 Colusa Generating Station Forced 641.00 18.16 PGAE North
CONTRL_1_LUNDY LUNDY Forced 3.00 0.00 SCE Gen
CONTRL_1_OXBOW Dixie Valley Geo Forced 60.00 3.00 SCE Gen
CRNEVL_6_CRNVA Crane Valley Forced 0.90 0.90 PGAE Gen
CRNEVL_6_SJQN 3 SAN JOAQUIN 3 Forced 4.20 4.20 PGAE Gen
CRSTWD_6_KUMYAY Kumeyaay Wind Farm Forced 50.00 2.00 SDGE Gen
CSTRVL_7_PL1X2 Marina Land Fill Gas Forced 4.53 2.03 PGAE South
DEERCR_6_UNIT 1 DEER CREEK Planned 7.00 7.00 PGAE North
DELAMO_2_SOLRC1 Golden Springs Building C1 Forced 1.16 0.00 SCE Gen
DELTA_2_PL1X4 DELTA ENERGY CENTER AGGREGATE Planned/Forced 880.00 332.00 PGAE Gen
DEXZEL_1_UNIT Western Power and Steam Cogeneration Planned 20.00 20.00 PGAE Gen
DINUBA_6_UNIT Dinuba Energy, Inc. Forced 12.00 12.00 PGAE South
DONNLS_7_UNIT Donnells Hydro Forced 72.00 6.50 PGAE Gen
DOUBLC_1_UNITS DOUBLE "C" LIMITED Forced 52.23 1.03 PGAE South
DREWS_6_PL1X4 Drews Generating Plant Forced 41.40 23.40 SCE Gen
DSABLA_7_UNIT De Sabla Hydro Planned 18.50 18.50 PGAE North
DSFLWR_2_WS2SR1 Willow Springs 2 Planned 100.00 0.00 SCE Gen
DSRTSN_2_SOLAR1 Desert Sunlight 300 Planned 300.00 0.00 SCE Gen
DSRTSN_2_SOLAR2 Desert Sunlight 250 Planned 250.00 0.00 SCE Gen
DUANE_1_PL1X3 DONALD VON RAESFELD POWER PROJECT Planned 147.80 147.80 PGAE South
EASTWD_7_UNIT EASTWOOD PUMP-GEN Forced 200.00 150.00 SCE Gen
ELCABO_5_ECWSCEDYN El Cabo Wind Forced 298.00 4.00 EIM ARI
ELCABO_5_ECWSCEDYN El Cabo Wind Forced 298.00 4.00 SCE Gen
ELCAJN_6_EB1BT1 Eastern BESS 1 Forced 7.50 0.00 SDGE Gen
ELECTR_7_PL1X3 ELECTRA PH UNIT 1 & 2 AGGREGATE Planned 93.00 31.30 PGAE North
ELKCRK_6_STONYG STONEY GORGE HYDRO AGGREGATE Planned 4.90 4.90 PGAE Gen
ELKHIL_2_PL1X3 ELK HILLS COMBINED CYCLE (AGGREGATE) Planned 551.70 326.70 PGAE Gen
ESCNDO_6_EB2BT2 Escondido BESS 2 Planned 10.00 2.50 SDGE Gen
ESCNDO_6_EB3BT3 Escondido BESS 3 Planned 10.00 2.50 SDGE Gen
ESCNDO_6_UNITB1 CalPeak Power Enterprise Unit 1 Forced 48.04 0.04 SDGE Gen
ESQUON_6_LNDFIL Neal Road Landfill Generating Facility Forced 2.10 2.10 PGAE Gen
ETIWND_2_FONTNA FONTANALYTLE CREEK POWERHOUSE P Forced 2.56 1.06 SCE Gen
ETIWND_2_RTS010 SPVP010 Fontana RT Solar Forced 1.50 1.50 SCE Gen
ETIWND_2_RTS026 SPVP026 Forced 6.00 2.00 SCE Gen
ETIWND_2_UNIT1 ETIWND_2_UNIT1 Forced 33.60 29.60 SCE Gen
EXCLSG_1_SOLAR Excelsior Solar Forced 60.00 28.00 PGAE Gen
FAIRHV_6_UNIT FAIRHAVEN POWER CO. Forced 18.75 0.00 PGAE North
FLOWD2_2_FPLWND DIABLO WINDS Forced 18.00 0.00 PGAE Gen
FLOWD_2_RT2WD2 Ridgetop 2 Forced 27.39 0.00 SCE Gen
FLOWD_2_WIND1 Cameron Ridge 2 Forced 11.90 0.00 SCE Gen
FORKBU_6_UNIT HYPOWER, INC. (FORKS OF BUTTE) Forced 14.30 0.00 PGAE Gen
FRNTBW_6_SOLAR1 Frontier Solar Forced 20.00 0.00 PGAE Gen
GARNET_1_SOLAR2 Garnet Solar Power Generation Station 1 Forced 4.00 0.00 SCE Gen
GARNET_1_UNITS GARNET GREEN POWER PROJECT AGGREGATE Forced 16.50 12.18 SCE Gen
GARNET_1_WIND GARNET WIND ENERGY CENTER Forced 6.50 0.50 SCE Gen
GARNET_1_WINDS Garnet Winds Aggregation Forced 22.50 0.00 SCE Gen
GARNET_1_WT3WND Wagner Wind Forced 6.00 0.00 SCE Gen
GARNET_2_DIFWD1 Difwind Forced 7.88 0.00 SCE Gen
GARNET_2_WIND2 Karen Avenue Wind Farm Planned 11.70 1.50 SCE Gen
GARNET_2_WPMWD6 WINTEC PALM Forced 5.93 5.93 SCE Gen
GATWAY_2_PL1X3 GATEWAY GENERATING STATION Planned 585.00 585.00 PGAE South
GEYS11_7_UNIT11 GEYSERS UNIT 11 (HEALDSBURG) Forced 74.40 0.00 PGAE Gen
GEYS12_7_UNIT12 GEYSERS UNIT 12 (HEALDSBURG) Forced 57.00 16.00 PGAE Gen
GEYS13_7_UNIT13 GEYSERS UNIT 13 (HEALDSBURG) Forced 95.00 48.00 PGAE Gen
GEYS14_7_UNIT14 GEYSERS UNIT 14 (HEALDSBURG) Forced 70.00 14.00 PGAE Gen
GEYS16_7_UNIT16 GEYSERS UNIT 16 (HEALDSBURG) Forced 85.00 42.00 PGAE Gen
GEYS17_7_UNIT17 GEYSERS UNIT 17 (HEALDSBURG) Forced 60.00 0.00 PGAE Gen
GEYS18_7_UNIT18 GEYSERS UNIT 18 (HEALDSBURG) Forced 72.00 27.00 PGAE Gen
GEYS20_7_UNIT20 GEYSERS UNIT 20 (HEALDSBURG) Forced 62.00 26.00 PGAE Gen
GILROY_1_UNIT GILROY COGEN AGGREGATE Planned 120.00 120.00 PGAE South
GLNARM_7_UNIT 1 GLEN ARM UNIT 1 Forced 22.07 22.07 SCE Gen
GLNARM_7_UNIT 2 GLEN ARM UNIT 2 Forced 22.30 22.30 SCE Gen
GOLETA_6_EXGEN EXXON COMPANY USA Forced 48.20 48.20 SCE Gen
GRIZLY_1_UNIT 1 GRIZZLY HYDRO Forced 20.00 20.00 PGAE North
GRNLF2_1_UNIT GREENLEAF II COGEN Planned 49.50 49.50 PGAE North
GRSCRK_6_BGCKWW BIG CREEK WATER WORKS - CEDAR FLAT Forced 5.00 5.00 PGAE Gen
GWFPWR_1_UNITS Hanford Peaker Plant Planned 98.46 98.46 PGAE Gen
GYS5X6_7_UNITS GEYSERS UNITS 5 & 6 AGGREGATE Forced 85.00 3.00 PGAE Gen
GYS7X8_7_UNITS GEYSERS UNITS 7 & 8 AGGREGATE Forced 82.00 5.00 PGAE Gen
HATLOS_6_BWDHY1 Bidwell Ditch Planned 2.00 2.00 PGAE Gen
HATLOS_6_LSCRK Lost Creek 1 & 2 Hydro Conversion Planned 1.70 1.70 PGAE Gen
HATRDG_2_WIND Hatchet Ridge Wind Farm Forced 102.00 5.40 PGAE Gen
HAYPRS_6_QFUNTS HAYPRESS HYDRO QF UNITS Forced 14.80 14.80 PGAE North
HELMPG_7_UNIT 1 HELMS PUMP-GEN UNIT 1 Forced 407.00 407.00 PGAE South
HELMPG_7_UNIT 2 HELMS PUMP-GEN UNIT 2 Planned/Forced 407.00 407.00 PGAE South
HENRTA_6_SOLAR1 Lemoore 1 Forced 1.50 1.50 PGAE Gen
HENRTA_6_UNITA1 GWF HENRIETTA PEAKER PLANT UNIT 1 Forced 49.98 1.65 PGAE South
HENRTA_6_UNITA2 GWF HENRIETTA PEAKER PLANT UNIT 2 Forced 49.42 1.20 PGAE South
HIDSRT_2_UNITS HIGH DESERT POWER PROJECT AGGREGATE Planned 830.00 830.00 SCE Gen
HMLTBR_6_UNITS HAMILTON BRANCH PH (AGGREGATE) Planned/Forced 4.90 4.90 PGAE Gen
HOLGAT_1_BORAX U.S. Borax, Unit 1 Forced 48.20 48.20 SCE Gen
HUMBPP_1_UNITS3 Humboldt Bay Generating Station 3 Forced 65.08 0.00 PGAE North
HUMBPP_6_UNITS Humboldt Bay Generating Station 1 Forced 97.62 0.00 PGAE North
HYTTHM_2_UNITS HYATT-THERMALITO PUMP-GEN (AGGREGATE) Planned/Forced 933.10 225.30 PGAE Gen
INDIGO_1_UNIT 2 INDIGO PEAKER UNIT 2 Forced 44.53 0.53 SCE Gen
INDVLY_1_UNITS Indian Valley Hydro Forced 3.01 3.01 PGAE North
INLDEM_5_UNIT 1 Inland Empire Energy Center, Unit 1 Planned 376.20 0.00 SCE Gen
INSKIP_2_UNIT INSKIP HYDRO Forced 8.00 8.00 PGAE North
INTKEP_2_UNITS CCSF Hetch_Hetchy Hydro Aggregate Planned/Forced 405.00 90.00 PGAE Gen
INTMNT_3_ANAHEIM Intermountain Power Project Planned 236.00 236.00 SCE Gen
INTMNT_3_RIVERSIDE IPPDYN Forced 137.00 137.00 SCE Gen
IVSLRP_2_SOLAR1 Silver Ridge Mount Signal Planned 200.00 0.00 SDGE Gen
JAWBNE_2_NSRWND North Sky River Wind Project Forced 160.00 14.40 SCE Gen
KEKAWK_6_UNIT STS HYDROPOWER LTD. (KEKAWAKA) Forced 5.50 5.50 PGAE Gen
KELSO_2_UNITS Mariposa Energy Forced 198.03 198.03 PGAE Gen
KERKH1_7_UNIT 1 KERKHOFF PH 1 UNIT #1 Forced 13.00 13.00 PGAE North
KERKH1_7_UNIT 1 KERKHOFF PH 1 UNIT #1 Forced 13.00 13.00 PGAE South
KERKH1_7_UNIT 3 KERKHOFF PH 1 UNIT #3 Forced 12.80 12.80 PGAE North
KERKH1_7_UNIT 3 KERKHOFF PH 1 UNIT #3 Forced 12.80 12.80 PGAE South
KERNFT_1_UNITS KERN FRONT LIMITED Forced 52.40 1.20 PGAE South
KINGRV_7_UNIT 1 KINGS RIVER HYDRO UNIT 1 Planned 51.20 51.20 PGAE South
KNGBRG_1_KBSLR1 Kingsburg1 Forced 1.50 0.00 PGAE South
KRAMER_1_SEGSR3 Kramer Junction 3 Forced 30.00 0.00 SCE Gen
KRAMER_1_SEGSR4 Kramer Junction 4 Forced 30.00 0.00 SCE Gen
KRAMER_2_SEGS89 LUZ SOLAR PARTNERS 8-9 AGGREGATE Forced 160.00 0.00 SCE Gen
KRNCNY_6_UNIT KERN CANYON Forced 11.50 11.50 PGAE South
LAKHDG_6_UNIT 1 Lake Hodges Pumped Storage-Unit1 Planned 20.00 20.00 SDGE Gen
LAKHDG_6_UNIT 2 Lake Hodges Pumped Storage-Unit2 Planned 20.00 20.00 SDGE Gen
LAPAC_6_UNIT LOUISIANA PACIFIC SAMOA Forced 20.00 20.00 PGAE Gen
LARKSP_6_UNIT 1 LARKSPUR PEAKER UNIT 1 Forced 46.10 2.10 SDGE Gen
LARKSP_6_UNIT 2 LARKSPUR PEAKER UNIT 2 Forced 47.98 4.98 SDGE Gen
LAROA2_2_UNITA1 LR2 Forced 322.00 6.00 SDGE Gen
LASSEN_6_UNITS Honey Lake Power Planned 30.00 30.00 PGAE North
LEBECS_2_UNITS Pastoria Energy Facility Planned 799.47 279.47 SCE Gen
LECEF_1_UNITS LOS ESTEROS ENERGY FACILITY AGGREGATE Forced 309.84 7.84 PGAE South
LIVOAK_1_UNIT 1 LIVE OAK LIMITED Forced 49.70 6.70 PGAE South
LMEC_1_PL1X3 Los Medanos Energy Center AGGREGATE Planned 580.00 0.00 PGAE Gen
LODI25_2_UNIT 1 LODI GAS TURBINE Planned 23.80 23.80 PGAE Gen
LODIEC_2_PL1X2 Lodi Energy Center Planned 302.58 302.58 PGAE Gen
MALAGA_1_PL1X2 Malaga Power Aggregate Forced 96.00 8.00 PGAE Gen
MALCHQ_7_UNIT 1 MALACHA HYDRO L.P. Forced 32.50 0.00 PGAE Gen
MALIN_5_GCPDDYN Grant County Hydro Facilities Forced 125.00 0.00 PGAE Gen
MANZNA_2_WIND Manzana Wind Forced 189.00 22.50 SCE Gen
METEC_2_PL1X3 Metcalf Energy Center Planned 593.16 0.00 PGAE Gen
MIDWD_2_WIND2 Coram Energy Forced 3.00 3.00 SCE Gen
MIRLOM_2_MLBBTA Mira Loma BESS A Forced 10.00 0.00 SCE Gen
MIRLOM_2_MLBBTB Mira Loma BESS B Forced 10.00 0.00 SCE Gen
MKTRCK_1_UNIT 1 MCKITTRICK LIMITED Forced 47.49 4.49 PGAE South
MNDALY_6_MCGRTH McGrath Beach Peaker Forced 47.20 0.00 SCE Gen
MNDOTA_1_SOLAR1 North Star Solar 1 Planned 60.00 0.00 PGAE Gen
MNDOTA_1_SOLAR2 Citizen Solar B Forced 5.00 1.00 PGAE Gen
MOJAVE_1_SIPHON MOJAVE SIPHON POWER PLANT Planned 14.36 0.00 SCE Gen
MONLTH_6_BOREL BOREL HYDRO UNITS 1-3 AGGREGATE Planned 11.00 11.00 SCE Gen
MONLTS_2_MONWD4 Monolith 4 Forced 4.75 0.00 SCE Gen
MONLTS_2_MONWD5 Monolith 5 Forced 4.04 0.00 SCE Gen
MONLTS_2_MONWD6 Monolith 6 Forced 5.25 0.00 SCE Gen
MONLTS_2_MONWD7 Monolith 7 Forced 4.76 0.00 SCE Gen
MRCHNT_2_PL1X3 Desert Star Energy Center Planned 494.58 494.58 SDGE Gen
MTWIND_1_UNIT 1 Mountain View Power Project I Planned/Forced 44.40 3.00 SCE Gen
MTWIND_1_UNIT 2 Mountain View Power Project II Forced 22.20 1.20 SCE Gen
NAROW2_2_UNIT Narrows Powerhouse Unit 2 Planned 55.00 2.00 PGAE North
NCPA_7_GP1UN2 NCPA GEO PLANT 1 UNIT 2 Planned 34.00 34.00 PGAE Gen
NCPA_7_GP2UN3 NCPA GEO PLANT 2 UNIT 3 Forced 42.42 42.42 PGAE Gen
NGILAA_5_SDGDYN NGILAA_5_SDGDYN Forced 57.00 1.00 EIM ARI
NGILAA_5_SDGDYN NGILAA_5_SDGDYN Forced 57.00 1.00 SDGE Gen
OAK C_7_UNIT 1 OAKLAND STATION C GT UNIT 1 Forced 55.00 1.50 PGAE South
OAK C_7_UNIT 3 OAKLAND STATION C GT UNIT 3 Forced 55.00 1.00 PGAE South
OASIS_6_SOLAR2 Oasis Solar Forced 20.00 0.00 SCE Gen
OILFLD_7_QFUNTS Nacimiento Hydroelectric Plant Forced 3.80 2.30 PGAE South
OLINDA_2_COYCRK MWD Coyote Creek Hydroelectric Recovery Forced 3.13 3.13 SCE Gen
OLINDA_2_LNDFL2 Brea Power II Planned 28.10 12.10 SCE Gen
OMAR_2_UNIT 1 KERN RIVER COGENERATION CO. UNIT 1 Forced 78.00 1.40 SCE Gen
OMAR_2_UNIT 2 KERN RIVER COGENERATION CO. UNIT 2 Forced 78.11 2.11 SCE Gen
OMAR_2_UNIT 3 KERN RIVER COGENERATION CO. UNIT 3 Forced 81.41 2.51 SCE Gen
ORMOND_7_UNIT 1 ORMOND BEACH GEN STA. UNIT 1 Planned 741.27 741.27 SCE Gen
OTMESA_2_PL1X3 OTAY MESA ENERGY CENTER Forced 603.68 3.68 SDGE Gen
OXMTN_6_LNDFIL Ox Mountain Landfill Generating Plant Forced 10.62 1.58 PGAE South
PACLUM_6_UNIT Humboldt Redwood Forced 28.80 19.80 PGAE North
PADUA_2_ONTARO ONTARIO/SIERRA HYDRO PSP Forced 1.92 0.42 SCE Gen
PANSEA_1_PANARO Mesa Wind Project Planned 30.00 21.81 SCE Gen
PINFLT_7_UNITS PINE FLAT HYDRO AGGREGATE Planned 210.00 60.00 PGAE Gen
PIOPIC_2_CTG1 Pio Pico Unit 1 Forced 111.30 1.51 SDGE Gen
PIOPIC_2_CTG2 Pio Pico Unit 2 Forced 112.70 0.60 SDGE Gen
PIOPIC_2_CTG3 Pio Pico Unit 3 Forced 112.00 0.24 SDGE Gen
PIT3_7_PL1X3 PIT PH 3 UNITS 1, 2 & 3 AGGREGATE Planned 70.60 24.60 PGAE North
PIT4_7_PL1X2 PIT PH 4 UNITS 1 & 2 AGGREGATE Planned 95.00 43.00 PGAE North
PIT7_7_UNIT 1 PIT PH 7 UNIT 1 Planned 55.70 55.70 PGAE North
PLACVL_1_CHILIB Chili Bar Hydro Planned 8.40 8.40 PGAE Gen
PLAINV_6_NLRSR1 North Lancaster Ranch Forced 20.00 0.00 SCE Gen
PLAINV_6_SOLARC Central Antelope Dry Ranch C Forced 20.00 0.00 SCE Gen
PNCHEG_2_PL1X4 PANOCHE ENERGY CENTER (Aggregated) Planned 401.00 401.00 PGAE Gen
PNCHPP_1_PL1X2 Midway Peaking Aggregate Forced 119.91 0.00 PGAE Gen
PNOCHE_1_PL1X2 Panoche Peaker Planned 49.97 49.97 PGAE South
PNOCHE_1_UNITA1 CalPeak Power Panoche Unit 1 Forced 52.01 4.01 PGAE Gen
POTTER_6_UNITS Potter Valley Planned 10.10 0.00 PGAE North
PVERDE_5_SCEDYN PVERDE_5_SCEDYN Planned 635.00 215.00 SCE Gen
PWEST_1_UNIT PACIFIC WEST 1 WIND GENERATION Forced 2.10 2.10 SCE Gen
RAMON_2_SCEDYN RAMON_2_SCEDYN Forced 359.60 268.60 SCE Gen
RAWHIDE_6_UNIT Chevron Wind Forced 16.50 1.50 EIM PAC
RECTOR_2_KAWH 1 KAWEAH PH 1 UNIT 1 Planned 2.25 2.25 SCE Gen
REDOND_7_UNIT 8 REDONDO GEN STA. UNIT 8 Planned 495.90 495.90 SCE Gen
REEDLY_6_SOLAR Terzian Forced 1.23 0.00 PGAE Gen
RENWD_1_QF Renwind re-powering project Forced 10.00 2.50 SCE Gen
RICHMN_1_CHVSR2 Chevron 8.5 Forced 8.50 2.00 PGAE Gen
RICHMN_7_BAYENV BAY ENVIRONMENTAL (NOVE POWER) Forced 2.50 2.50 PGAE Gen
ROSMDW_2_WIND1 Pacific Wind - Phase 1 Planned 140.00 6.00 SCE Gen
RTEDDY_2_SOLAR2 Rosamond West Solar 2 Planned 54.00 0.00 SCE Gen
RTREE_2_WIND2 Rising Tree 2 Forced 19.80 0.00 SCE Gen
RUSCTY_2_UNITS Russell City Energy Center Forced 620.50 7.80 PGAE South
RVSIDE_2_RERCU3 Riverside Energy Res. Ctr Unit 3 Forced 49.00 49.00 SCE Gen
RVSIDE_2_RERCU4 Riverside Energy Res. Ctr Unit 4 Forced 49.00 49.00 SCE Gen
SALTSP_7_UNITS SALT SPRINGS HYDRO AGGREGATE Planned 46.00 0.00 PGAE North
SANTFG_7_UNITS GEYSERS CALISTOGA AGGREGATE Forced 92.10 34.10 PGAE Gen
SANTGO_2_LNDFL1 Bowerman Power Forced 19.60 19.60 SCE Gen
SANWD_1_QF San Gorgonio Farms Wind Farm Planned 31.00 2.66 SCE Gen
SAUGUS_7_CHIQCN Chiquita Canyon Landfill Fac Planned 8.00 8.00 SCE Gen
SBERDO_2_RTS005 SPVP005 Redlands RT Solar Forced 2.50 0.00 SCE Gen
SBERDO_2_RTS016 SPVP016 Redlands RT Solar Forced 1.50 0.00 SCE Gen
SBERDO_2_SNTANA SANTA ANA PSP Forced 6.95 6.95 SCE Gen
SBERDO_6_MILLCK MILL CREEK PSP Forced 3.93 2.93 SCE Gen
SCEHOV_2_HOOVER SCEHOV_2_HOOVER Forced 287.01 156.01 SCE Gen
SCHLTE_1_PL1X3 Tracy Combined Cycle Power Plant Forced 336.04 12.22 PGAE Gen
SIERRA_1_UNITS HIGH SIERRA LIMITED Forced 52.43 1.23 PGAE Gen
SISQUC_1_SMARIA Santa Maria II LFG Power Plant Forced 1.42 0.35 PGAE Gen
SLUISP_2_UNITS SAN LUIS (GIANELLI) PUMP-GEN (AGGREGATE) Planned 374.43 54.43 PGAE Gen
SMUDGO_7_UNIT 1 SONOMA POWER PLANT Forced 53.00 3.00 PGAE Gen
SNCLRA_2_UNIT1 New Indy Oxnard Planned 27.80 27.80 SCE Gen
SPAULD_6_UNIT12 SPAULDING HYDRO PH 1 & 2 AGGREGATE Planned/Forced 11.40 11.40 PGAE North
SPBURN_2_UNIT 1 Burney Biomass Forced 22.00 22.00 PGAE North
SPIAND_1_ANDSN2 SPI Anderson 2 Planned 27.15 27.15 PGAE Gen
SPICER_1_UNITS SPICER HYDRO UNITS 1-3 AGGREGATE Forced 6.00 6.00 PGAE Gen
SPQUIN_6_SRPCQU Quincy Biomass Planned 24.00 24.00 PGAE North
SPRGVL_2_TULE TULE RIVER HYDRO PLANT (PG&E) Forced 6.40 0.00 SCE Gen
SPRGVL_2_TULESC TULE RIVER HYDRO PLANT (SCE) Forced 2.50 2.50 SCE Gen
STOILS_1_UNITS Chevron Richmond Refinery Forced 56.20 56.20 PGAE Gen
STROUD_6_SOLAR Stroud Solar Station Forced 20.00 1.00 PGAE South
SUNRIS_2_PL1X3 Sunrise Power Project AGGREGATE II Forced 586.02 586.02 PGAE Gen
SUNSET_2_UNITS MIDWAY SUNSET COGENERATION PLANT Forced 248.00 17.00 PGAE South
SUNSHN_2_LNDFL Sunshine Gas Producers Forced 20.00 5.80 SCE Gen
SYCAMR_2_UNIT 1 Sycamore Cogeneration Unit 1 Forced 85.00 1.36 SCE Gen
SYCAMR_2_UNIT 2 Sycamore Cogeneration Unit 2 Forced 85.00 4.95 SCE Gen
SYCAMR_2_UNIT 3 Sycamore Cogeneration Unit 3 Forced 85.00 5.31 SCE Gen
SYCAMR_2_UNIT 4 Sycamore Cogeneration Unit 4 Forced 85.00 5.67 SCE Gen
S_RITA_6_SOLAR1 Sun Harvest Solar Forced 1.50 0.80 PGAE Gen
TENGEN_2_PL1X2 Berry Cogen 42 Planned 40.20 22.70 SCE Gen
TERMEX_2_PL1X3 TDM Forced 625.00 0.00 SDGE Gen
TIGRCK_7_UNITS TIGER CREEK HYDRO AGGREGATE Planned 62.00 62.00 PGAE North
TUPMAN_1_BIOGAS ABEC Bidart-Stockale #1 Forced 0.60 0.31 PGAE Gen
TWISSL_6_SOLAR Nickel 1 ("NLH1") Forced 1.50 0.00 PGAE Gen
TXMCKT_6_UNIT McKittrick Cogen Forced 11.20 8.00 PGAE South
UNCHEM_1_UNIT CONTRA COSTA CARBON PLANT Forced 19.00 9.00 PGAE Gen
UNVRSY_1_UNIT 1 Berry Cogen 38 - Unit 1 Forced 38.00 38.00 PGAE Gen
USWND2_1_WIND1 Golden Hills A Planned 42.96 0.00 PGAE Gen
USWND2_1_WIND2 Golden Hills B Forced 42.96 0.00 PGAE Gen
USWND2_1_WIND3 Golden Hills C Forced 46.00 4.60 PGAE Gen
USWNDR_2_SMUD SOLANO WIND FARM Forced 102.18 0.00 PGAE Gen
USWNDR_2_SMUD2 Solano Wind Project Phase 3 Forced 127.80 0.00 PGAE Gen
USWPJR_2_UNITS Vasco Wind Forced 78.20 0.00 PGAE Gen
VACADX_1_NAS VACA-DIXON BATTERY Forced 1.85 1.85 PGAE North
VACADX_1_UNITA1 CalPeak Power Vaca Dixon Unit 1 Forced 50.61 2.61 PGAE Gen
VALLEY_5_PERRIS MWD Perris Hydroelectric Recovery Plant Planned/Forced 7.94 7.94 SCE Gen
VALLEY_5_RTS044 SPVP044 Forced 8.00 0.00 SCE Gen
VICTOR_1_SOLAR2 Alamo Solar Forced 20.00 10.00 SCE Gen
VILLPK_2_VALLYV MWD Valley View Hydroelectric Recovery P Forced 4.10 4.10 SCE Gen
VINCNT_2_WESTWD Oasis Power Plant Planned 59.00 1.00 SCE Gen
VLCNTR_6_VCSLR1 Valley Center 1 Forced 2.50 0.00 SDGE Gen
WALCRK_2_CTG1 Walnut Creek Energy Park Unit 1 Planned/Forced 96.43 96.43 SCE Gen
WALCRK_2_CTG2 Walnut Creek Energy Park Unit 2 Planned/Forced 96.91 96.91 SCE Gen
WALCRK_2_CTG3 Walnut Creek Energy Park Unit 3 Planned/Forced 96.65 96.65 SCE Gen
WALCRK_2_CTG4 Walnut Creek Energy Park Unit 4 Planned/Forced 96.49 96.49 SCE Gen
WALCRK_2_CTG5 Walnut Creek Energy Park Unit 5 Planned/Forced 96.65 96.65 SCE Gen
WDLEAF_7_UNIT 1 WOODLEAF HYDRO Forced 60.00 20.00 PGAE North
WEBER_6_FORWRD Forward Forced 4.20 2.10 PGAE Gen
WFRESN_1_SOLAR Joya Del Sol Forced 1.50 0.00 PGAE Gen
WHEATL_6_LNDFIL G2 ENERGY, OSTROM ROAD LLC Forced 3.55 1.75 PGAE Gen
WHTWTR_1_WINDA1 Whitewater Hill Wind Project Forced 61.50 11.50 SCE Gen
WNDMAS_2_UNIT 1 BUENA VISTA ENERGY, LLC Forced 38.00 2.00 PGAE Gen
WNDSTR_2_WIND Windstar Planned 120.00 4.00 SCE Gen
WRGHTP_7_AMENGY SMALL QF AGGREGATION - LOS BANOS Forced 2.50 1.50 PGAE Gen
YUBACT_1_SUNSWT YUBA CITY COGEN Planned 49.97 49.97 PGAE North
ZOND_6_UNIT ZOND WINDSYSTEMS INC. Forced 17.10 17.10 PGAE Gen
BRDGVL_7_BAKER Baker Station Hydro Forced 1.49 1.49
RATSKE_2_NROSR1 North Rosamond Solar Forced 150.00 0.00
STROUD_6_WWHSR1 Winter Wheat Solar Farm Forced 1.50 0.00


Outage Summary
Zone Name Number Of Outages MW's
Planned Forced Limitation Shutdown
EIM ARI 0 2 5.00 0.00
EIM PAC 0 1 1.50 0.00
PGAE Gen 34 83 1463.43 2157.96
PGAE North 20 18 183.25 443.03
PGAE South 10 34 91.27 1882.67
SCE Gen 51 122 1946.18 4256.79
SDGE Gen 6 18 30.40 534.58
0 4 0.00 1.49
Total 121 282 3721.03 9276.52


Report Generated on:
04/10/2019 08:30:00 (PPT)
Filtered Parameters:
Date = 04/11/2019
Resource = ALL
Area = ALL
States = ALL
Outage Origin = CAISO

System conditions are dynamic and may change, affecting the accuracy of this report. This report includes all outages, curtailments and temporary operating constraints reflecting normal operations that are effective at the time of the report. Because outages may overlap or may not all be simultaneously in effect at the time of this report, Other real-time reports may indicate a different total outage/curtailment than this report. This report reflects the best available data at the date and time of the report. It is a snapshot of conditions existing at the time the report was posted. This report is initiated once daily 1515 Pacific Time.

The content of these pages is subject to change without notice. Decisions based on information contained within the California ISO web site are the visitor's sole responsibility.