Curtailed and Non-Operational Generating Units
Resource ID Resource Name Outage Type Capacity (MW) Curtailed (MW) Zone Name
ADLIN_1_UNITS GEYSERS AIDLIN AGGREGATE Forced 22.00 8.00 PGAE Gen
ADOBEE_1_SOLAR Adobe Solar Forced 20.00 0.00 PGAE Gen
AGRICO_6_PL3N5 Fresno Peaker Planned 22.69 22.69 PGAE South
AGRICO_7_UNIT Fresno Cogen Planned 50.60 50.60 PGAE South
ALAMIT_2_PL1X3 Alamitos Energy Center Unit 7 Forced 674.70 11.70 SCE Gen
ALAMIT_7_UNIT 5 ALAMITOS GEN STA. UNIT 5 Forced 480.00 0.00 SCE Gen
ALHMBR_1_ALHSLR SG Alhambra Planned 50.00 0.00 SDGE Gen
ALMEGT_1_UNIT 1 ALAMEDA GT UNIT 1 Forced 25.00 4.00 PGAE South
ALMEGT_1_UNIT 2 ALAMEDA GT UNIT 2 Forced 25.00 4.00 PGAE South
ALTA3A_2_CPCE4 Alta Wind 4 Forced 102.00 0.00 SCE Gen
ALTA3A_2_CPCE5 Alta Wind 5 Forced 168.00 0.00 SCE Gen
ALTA3A_2_CPCE8 Alta Wind 8 Forced 150.00 6.00 SCE Gen
ALTA4A_2_CPCW1 Alta Wind 1 Forced 150.00 0.00 SCE Gen
ALTA4B_2_CPCW2 Alta Wind 2 Forced 150.00 6.00 SCE Gen
ALTA4B_2_CPCW3 Alta Wind 3 Forced 150.00 9.00 SCE Gen
ALTA4B_2_CPCW6 Mustang Hills Planned 150.00 6.00 SCE Gen
ALTA6B_2_WIND11 Alta Wind 11 Forced 88.15 0.00 SCE Gen
ALTA6E_2_WIND10 Alta Wind 10 Forced 134.84 2.85 SCE Gen
ANAHM_2_CANYN2 CANYON POWER PLANT UNIT 2 Planned 49.40 0.00 SCE Gen
ANZA_6_SOLAR1 Seville Solar One Forced 20.00 0.00 SDGE Gen
ARKANS_1_ARKSLR SG Arkansas Planned 50.00 0.00 SDGE Gen
ARVINN_6_ORION2 Orion 2 Solar Forced 8.00 0.00 PGAE Gen
AVSOLR_2_SOLAR AV SOLAR RANCH 1 Planned 241.50 0.00 SCE Gen
BASICE_2_UNITS King City Cogen Forced 120.00 0.00 PGAE Gen
BCTSYS_5_PWXDYN BCTSYS_5_PWXDYN Forced 428.00 428.00 PGAE Gen
BDGRCK_1_UNITS BADGER CREEK LIMITED Forced 48.08 6.08 PGAE South
BEARDS_7_UNIT 1 Beardsley Hydro Planned 11.50 11.50 PGAE Gen
BEARMT_1_UNIT Bear Mountain Limited Planned/Forced 49.21 49.21 PGAE Gen
BEJNLS_5_BV2SCEDYN Broadview 2 Forced 167.00 167.00 APS Gen
BEJNLS_5_BV2SCEDYN Broadview 2 Forced 167.00 167.00 SCE Gen
BEKWJS_5_BV1SCEDYN Broadview 1 Forced 130.00 130.00 APS Gen
BEKWJS_5_BV1SCEDYN Broadview 1 Forced 130.00 130.00 SCE Gen
BELDEN_7_UNIT 1 BELDEN HYDRO Forced 119.00 102.66 PGAE Gen
BGSKYN_2_AS2SR1 Antelope Solar 2 Forced 105.00 0.00 SCE Gen
BGSKYN_2_ASPSR2 Antelope Solar 2 San Pablo Forced 100.00 0.00 SCE Gen
BGSKYN_2_BS3SR3 Big Sky Solar 3 Forced 20.00 0.00 SCE Gen
BIGCRK_2_EXESWD BIG CREEK HYDRO PROJECT PSP Forced 820.00 820.00 SCE Gen
BIGCRK_7_DAM7 DAM 7 AT BIG CREEK (FISHWATER GEN) Forced 0.30 0.00 SCE Gen
BIGCRK_7_MAMRES MAMMOTH POOL RESERVOIR (FISHWATER Forced 1.25 0.00 SCE Gen
BIGSKY_2_BSKSR6 Big Sky Solar 6 Forced 20.00 0.00 SCE Gen
BIGSKY_2_BSKSR7 Big Sky Solar 7 Forced 20.00 0.00 SCE Gen
BIGSKY_2_BSKSR8 Big Sky Solar 8 Forced 20.00 0.00 SCE Gen
BIGSKY_2_SOLAR2 Big Sky Solar 4 Forced 40.00 0.00 SCE Gen
BIGSKY_2_SOLAR3 Big Sky Summer Forced 20.00 0.00 SCE Gen
BIGSKY_2_SOLAR4 Western Antelope Blue Sky Ranch B Forced 20.00 0.00 SCE Gen
BIGSKY_2_SOLAR5 Big Sky Solar 2 Forced 5.00 0.00 SCE Gen
BIGSKY_2_SOLAR6 Solverde 1 Forced 85.00 0.00 SCE Gen
BIGSKY_2_SOLAR7 Big Sky Solar 1 Forced 50.00 0.00 SCE Gen
BIOMAS_1_UNIT 1 WOODLAND BIOMASS Forced 25.50 25.50 PGAE North
BISHOP_1_ALAMO BISHOP CREEK PLANT 2 AND 6 Forced 13.40 0.00 SCE Gen
BISHOP_1_UNITS BISHOP CREEK PLANT 3 AND 4 Forced 15.80 8.80 SCE Gen
BKRFLD_2_SOLAR1 Bakersfield 111 Forced 1.38 0.00 PGAE Gen
BLACK_7_UNIT 1 JAMES B. BLACK 1 Forced 85.00 0.00 PGAE North
BLACK_7_UNIT 2 JAMES B. BLACK 2 Forced 84.10 0.00 PGAE North
BLAST_1_WIND Mountain View IV Wind Planned 49.00 2.00 SCE Gen
BLM_2_UNITS BLM EAST Facility Forced 72.00 41.00 SCE Gen
BNNIEN_7_ALTAPH ALTA POWER HOUSE Forced 1.00 0.94 PGAE Gen
BRDSLD_2_HIWIND High Winds Energy Center Forced 162.00 10.80 PGAE Gen
BRDSLD_2_MTZUM2 NextEra Energy Montezuma Wind II Forced 78.20 0.00 PGAE Gen
BRDSLD_2_MTZUMA FPL Energy Montezuma Wind Forced 36.80 4.60 PGAE Gen
BRDSLD_2_SHILO1 Shiloh I Wind Project Forced 150.00 0.00 PGAE Gen
BRDSLD_2_SHILO2 SHILOH WIND PROJECT 2 Planned/Forced 150.00 150.00 PGAE Gen
BRDSLD_2_SHLO3A Shiloh III Wind Project, LLC Forced 102.50 0.00 PGAE Gen
BRDSLD_2_SHLO3B Shiloh IV Wind Project Forced 100.00 0.00 PGAE Gen
BRODIE_2_WIND Coram Brodie Wind Project Forced 102.00 0.00 SCE Gen
BUCKBL_2_PL1X3 Blythe Energy Center Planned/Forced 493.63 157.63 SCE Gen
BUCKCK_7_OAKFLT Oak Flat Forced 1.30 0.66 PGAE Gen
BUCKCK_7_PL1X2 BUCKS CREEK AGGREGATE Planned 57.25 57.25 PGAE Gen
BUCKWD_1_QF Buckwind Re-powering project Forced 16.50 3.00 SCE Gen
BURNYF_2_UNIT 1 Burney Forest Power Planned 29.00 29.00 PGAE Gen
CABZON_1_WINDA1 Cabazon Wind Project Planned 41.00 0.00 SCE Gen
CALGEN_1_UNITS Coso Navy 1 Forced 80.00 28.00 SCE Gen
CALPIN_1_AGNEW Agnews Power Plant Forced 28.56 28.56 PGAE Gen
CAMCHE_1_PL1X3 CAMANCHE UNITS 1, 2 & 3 AGGREGATE Forced 9.99 9.18 PGAE Gen
CARBOU_7_PL2X3 CARIBOU PH 1 UNIT 2 & 3 AGGREGATE Forced 49.00 49.00 PGAE North
CARBOU_7_PL4X5 CARIBOU PH 2 UNIT 4 & 5 AGGREGATE Forced 120.00 90.07 PGAE North
CARBOU_7_UNIT 1 CARIBOU PH 1 UNIT 1 Planned/Forced 24.00 24.00 PGAE North
CARLS1_2_CARCT1 Carlsbad 1 Planned/Forced 422.00 0.00 SDGE Gen
CARLS2_1_CARCT1 Carlsbad 2 Planned/Forced 105.50 0.00 SDGE Gen
CAVLSR_2_BSOLAR California Valley Solar Ranch-Phase B Forced 40.00 0.00 PGAE Gen
CAVLSR_2_RSOLAR California Valley Solar Ranch-Phase A Forced 210.00 0.00 PGAE Gen
CENTER_2_RHONDO MWD Rio Hondo Hydroelectric Recovery Pla Forced 1.91 1.91 SCE Gen
CENTER_6_PEAKER Center Peaker Planned/Forced 47.11 47.11 SCE Gen
CENTRY_6_PL1X4 CENTURY GENERATING PLANT (AGGREGATE) Forced 41.40 0.00 SCE Gen
CHALK_1_UNIT CHALK CLIFF LIMITED Forced 48.67 6.67 PGAE Gen
CHICPK_7_UNIT 1 Chicago Park Powerhouse Forced 42.00 25.00 PGAE North
CHINO_2_APEBT1 Pomona Energy Storage Forced 20.00 2.80 SCE Gen
CHINO_7_MILIKN MN Milliken Genco LLC Planned 1.90 1.90 SCE Gen
CHWCHL_1_BIOMAS Chow II Biomass to Energy Planned 10.80 10.80 PGAE South
CLOVDL_1_SOLAR Cloverdale Solar I Forced 1.50 0.00 PGAE Gen
CLOVER_2_UNIT Clover Creek Forced 0.99 0.99 PGAE Gen
CLRKRD_6_LIMESD Lime Saddle Hydro Forced 2.00 2.00 PGAE Gen
CNTRVL_6_UNIT Centerville Forced 6.40 6.40 PGAE Gen
COCOPP_2_CTG1 Marsh Landing 1 Forced 204.20 1.51 PGAE South
COCOPP_2_CTG2 Marsh Landing 2 Forced 202.70 0.86 PGAE South
COCOPP_2_CTG3 Marsh Landing 3 Forced 208.96 7.56 PGAE South
COCOPP_2_CTG4 Marsh Landing 4 Forced 204.29 1.00 PGAE South
COCOSB_6_SOLAR Oakley Solar Project Forced 1.50 0.00 PGAE Gen
COGNAT_1_UNIT Stockton Biomas Planned 45.00 45.00 PGAE Gen
COLGAT_7_UNIT 1 Colgate Powerhouse Unit 1 Planned 176.72 24.72 PGAE North
COLGAT_7_UNIT 2 Colgate Powerhouse Unit 2 Planned 175.67 23.67 PGAE North
COLTON_6_AGUAM1 AGUA MANSA UNIT 1 (CITY OF COLTON) Forced 43.00 2.00 SCE Gen
COLUSA_2_PL1X3 Colusa Generating Station Forced 641.00 18.11 PGAE North
CONTRL_1_LUNDY LUNDY Planned/Forced 3.00 3.00 SCE Gen
CONTRL_1_OXBOW Dixie Valley Geo Forced 60.00 3.50 SCE Gen
CONTRL_1_POOLE POOLE HYDRO PLANT 1 Forced 10.90 10.90 SCE Gen
CONTRL_1_RUSHCK RUSH CREEK Forced 11.94 9.94 SCE Gen
CORRAL_6_SJOAQN Ameresco San Joaquin Forced 4.30 4.30 PGAE Gen
COVERD_2_HCKHY1 HATCHET CREEK Forced 6.89 6.89 PGAE Gen
COVERD_2_RCKHY1 ROARING CREEK Forced 2.00 2.00 PGAE Gen
COWCRK_2_UNIT Cow Creek Hydro Forced 2.00 2.00 PGAE Gen
CPVERD_2_SOLAR Campo Verde Solar Planned/Forced 139.00 0.00 SDGE Gen
CRESTA_7_PL1X2 CRESTA PH UNIT 1 & 2 AGGREGATE Forced 70.40 63.84 PGAE North
CRNEVL_6_SJQN 2 SAN JOAQUIN 2 Forced 3.20 3.20 PGAE Gen
CRNEVL_6_SJQN 3 SAN JOAQUIN 3 Forced 4.20 4.20 PGAE Gen
CROKET_7_UNIT CROCKETT COGEN Planned 240.00 240.00 PGAE North
CRSTWD_6_KUMYAY Kumeyaay Wind Farm Forced 50.00 2.00 SDGE Gen
CSCCOG_1_UNIT 1 SANTA CLARA CO-GEN Forced 7.00 0.00 PGAE South
CSCGNR_1_UNIT 1 GIANERA PEAKER UNIT 1 Forced 24.75 2.15 PGAE South
CSCGNR_1_UNIT 2 GIANERA PEAKER UNIT 2 Forced 24.75 2.15 PGAE South
CSTOGA_6_LNDFIL Clover Flat Land Fill Gas Forced 0.85 0.85 PGAE Gen
CSTRVL_7_PL1X2 Marina Land Fill Gas Forced 4.53 0.33 PGAE South
CUMMNG_6_SUNCT1 SunSelect 1 Forced 4.00 2.15 SCE Gen
DAIRLD_1_MD2BM1 Madera Digester Genset 2 Forced 0.80 0.00 PGAE Gen
DALYCT_1_FCELL PGE San Francisco State Fuel Cell Forced 1.60 1.60 PGAE Gen
DAVIS_1_SOLAR1 Grasslands 3 Forced 1.00 0.00 PGAE Gen
DAVIS_1_SOLAR2 Grasslands 4 Forced 1.00 0.00 PGAE Gen
DEADCK_1_UNIT DEADCK_1_UNIT Forced 2.00 2.00 PGAE Gen
DELAMO_2_SOLRC1 Golden Springs Building C1 Forced 1.16 0.00 SCE Gen
DELSUR_6_CREST Delsur Aggregate Solar Resources Forced 10.00 0.00 SCE Gen
DELSUR_6_DRYFRB Dry Farm Ranch B Forced 5.00 0.00 SCE Gen
DELSUR_6_SOLAR1 Summer Solar North Forced 6.50 0.00 SCE Gen
DELSUR_6_SOLAR5 Radiance Solar 5 Forced 1.50 0.00 SCE Gen
DELTA_2_PL1X4 DELTA ENERGY CENTER AGGREGATE Forced 880.00 20.00 PGAE Gen
DEVERS_1_SEPV05 SEPV 5 Forced 2.00 0.00 SCE Gen
DEXZEL_1_UNIT Western Power and Steam Cogeneration Forced 20.00 0.00 PGAE Gen
DIABLO_7_UNIT 1 Diablo Canyon Unit 1 Planned 1150.00 1150.00 PGAE South
DMDVLY_1_UNITS DIAMOND VALLEY LAKE PUMP-GEN PLANT Forced 21.00 21.00 SCE Gen
DOSMGO_2_NSPIN DOSMGO_2_NSPIN Planned/Forced 159.00 159.00 PGAE Gen
DOUBLC_1_UNITS DOUBLE "C" LIMITED Forced 52.23 3.73 PGAE South
DRACKR_2_D4SR4B Dracker Solar Unit 4B Planned 62.50 62.50 SCE Gen
DRACKR_2_SOLAR2 Dracker Solar Unit 2 Forced 125.00 0.00 SCE Gen
DREWS_6_PL1X4 Drews Generating Plant Forced 41.40 20.70 SCE Gen
DRUM_7_PL1X2 Drum PH 1 Units 1 & 2 Aggregate Forced 26.00 1.00 PGAE North
DRUM_7_PL3X4 Drum PH 1 Units 3 & 4 Aggregate Planned/Forced 28.90 28.90 PGAE North
DRUM_7_UNIT 5 DRUM PH 2 UNIT 5 Forced 50.00 0.00 PGAE North
DSABLA_7_UNIT De Sabla Hydro Forced 18.50 18.50 PGAE North
DUANE_1_PL1X3 DONALD VON RAESFELD POWER PROJECT Forced 147.80 15.80 PGAE South
DUTCH1_7_UNIT 1 DUTCH FLAT 1 PH Forced 22.00 0.00 PGAE North
DUTCH2_7_UNIT 1 DUTCH FLAT 2 PH Forced 26.00 26.00 PGAE North
DVLCYN_1_UNITS DEVIL CANYON HYDRO UNITS 1-4 AGGREGATE Planned/Forced 235.00 0.00 SCE Gen
EASTWD_7_UNIT EASTWOOD PUMP-GEN Forced 200.00 200.00 SCE Gen
ELCABO_5_ECWSCEDYN El Cabo Wind Planned 298.00 298.00 APS Gen
ELCABO_5_ECWSCEDYN El Cabo Wind Planned 298.00 298.00 SCE Gen
ELCAJN_6_EB1BT1 Eastern BESS 1 Planned 7.50 1.25 SDGE Gen
ELCAJN_6_LM6K El Cajon Energy Center Forced 48.10 0.00 SDGE Gen
ELCAJN_6_UNITA1 Cuyamaca Peak Energy Plant Planned 45.42 0.00 SDGE Gen
ELDORO_7_UNIT 1 El Dorado Unit 1 Planned 11.00 11.00 PGAE North
ELDORO_7_UNIT 2 El Dorado Unit 2 Planned 11.00 11.00 PGAE North
ELECTR_7_PL1X3 ELECTRA PH UNIT 1 & 2 AGGREGATE Planned 93.00 23.20 PGAE North
ELKCRK_6_STONYG STONEY GORGE HYDRO AGGREGATE Forced 4.90 4.90 PGAE Gen
ELKHIL_2_PL1X3 ELK HILLS COMBINED CYCLE (AGGREGATE) Planned 551.70 43.70 PGAE Gen
ELNIDP_6_BIOMAS El Nido Biomass to Energy Forced 10.50 10.50 PGAE South
ELSEGN_2_UN1011 El Segundo Energy Center 5/6 Forced 263.00 0.00 SCE Gen
ELSEGN_2_UN2021 El Segundo Energy Center 7/8 Forced 263.68 0.00 SCE Gen
ENERSJ_2_WIND ESJ Wind Energy Forced 155.10 0.00 SDGE Gen
ESCNDO_6_EB2BT2 Escondido BESS 2 Forced 10.00 10.00 SDGE Gen
ESCNDO_6_PL1X2 MMC Escondido Aggregate Forced 48.71 48.71 SDGE Gen
ESCO_6_GLMQF Goal Line Cogen Planned/Forced 49.90 49.90 SDGE Gen
ESQUON_6_LNDFIL Neal Road Landfill Generating Facility Forced 2.10 0.00 PGAE Gen
ETIWND_2_FONTNA FONTANALYTLE CREEK POWERHOUSE P Planned 2.56 1.36 SCE Gen
ETIWND_2_UNIT1 ETIWND_2_UNIT1 Planned 33.60 31.60 SCE Gen
ETIWND_6_MWDETI ETIWANDA RECOVERY HYDRO Forced 24.00 24.00 SCE Gen
EXCHEC_7_UNIT 1 EXCHEQUER HYDRO Forced 94.50 11.50 PGAE South
EXCLSG_1_SOLAR Excelsior Solar Forced 60.00 0.00 PGAE Gen
FAIRHV_6_UNIT FAIRHAVEN POWER CO. Forced 18.75 18.75 PGAE North
FLOWD2_2_FPLWND DIABLO WINDS Forced 18.00 1.20 PGAE Gen
FMEADO_7_UNIT FRENCH MEADOWS HYDRO Forced 16.00 7.00 PGAE North
FORBST_7_UNIT 1 FORBESTOWN HYDRO Forced 37.50 37.50 PGAE North
FROGTN_1_UTICAM Murphys Powerhouse Planned/Forced 3.60 2.00 PGAE Gen
GARNET_1_UNITS GARNET GREEN POWER PROJECT AGGREGATE Forced 16.50 9.00 SCE Gen
GARNET_1_WINDS Garnet Winds Aggregation Forced 22.50 0.00 SCE Gen
GARNET_2_WIND2 Karen Avenue Wind Farm Planned 11.70 1.50 SCE Gen
GARNET_2_WPMWD6 WINTEC PALM Forced 5.93 5.93 SCE Gen
GATEWY_2_GESBT1 Gateway Energy Stroage Forced 250.00 250.00 SDGE Gen
GATWAY_2_PL1X3 GATEWAY GENERATING STATION Forced 585.00 65.79 PGAE South
GEYS11_7_UNIT11 GEYSERS UNIT 11 (HEALDSBURG) Forced 74.40 0.00 PGAE Gen
GEYS12_7_UNIT12 GEYSERS UNIT 12 (HEALDSBURG) Forced 57.00 9.00 PGAE Gen
GEYS13_7_UNIT13 GEYSERS UNIT 13 (HEALDSBURG) Forced 95.00 95.00 PGAE Gen
GEYS14_7_UNIT14 GEYSERS UNIT 14 (HEALDSBURG) Forced 70.00 2.00 PGAE Gen
GEYS16_7_UNIT16 GEYSERS UNIT 16 (HEALDSBURG) Forced 85.00 30.00 PGAE Gen
GEYS17_2_BOTRCK Bottle Rock Geothermal Forced 10.01 10.01 PGAE North
GEYS17_7_UNIT17 GEYSERS UNIT 17 (HEALDSBURG) Forced 60.00 0.00 PGAE Gen
GEYS18_7_UNIT18 GEYSERS UNIT 18 (HEALDSBURG) Forced 72.00 72.00 PGAE Gen
GEYS20_7_UNIT20 GEYSERS UNIT 20 (HEALDSBURG) Forced 62.00 62.00 PGAE Gen
GIFFEN_6_SOLAR1 Aspiration Solar G Forced 9.00 0.00 PGAE Gen
GILROY_1_UNIT GILROY COGEN AGGREGATE Forced 120.00 12.00 PGAE South
GLNARM_7_UNIT 1 GLEN ARM UNIT 1 Planned 22.07 0.00 SCE Gen
GLNARM_7_UNIT 2 GLEN ARM UNIT 2 Forced 22.30 22.30 SCE Gen
GOLETA_6_ELLWOD ELLWOOD ENERGY SUPPORT FACILITY Forced 54.00 54.00 SCE Gen
GOLETA_6_EXGEN EXXON COMPANY USA Forced 48.20 48.20 SCE Gen
GRADYW_5_GDYWD1 Grady Wind Forced 200.00 200.00 APS Gen
GRIZLY_1_UNIT 1 GRIZZLY HYDRO Planned/Forced 20.00 20.00 PGAE North
GRNLF2_1_UNIT GREENLEAF II COGEN Forced 49.20 2.20 PGAE North
GRNVLY_7_SCLAND SANTA CRUZ LANDFILL GENERATING PLANT Forced 3.04 0.00 PGAE South
GRSCRK_6_BGCKWW BIG CREEK WATER WORKS - CEDAR FLAT Forced 5.00 5.00 PGAE Gen
GUERNS_6_HD3BM3 Hanford Digester Genset 3 Forced 1.00 1.00 PGAE Gen
GUERNS_6_VH2BM1 Hanford Digester Genset 2 Forced 1.00 1.00 PGAE Gen
GWFPWR_1_UNITS Hanford Peaker Plant Forced 98.46 1.73 PGAE Gen
GYS5X6_7_UNITS GEYSERS UNITS 5 & 6 AGGREGATE Forced 85.00 1.00 PGAE Gen
GYS7X8_7_UNITS GEYSERS UNITS 7 & 8 AGGREGATE Forced 82.00 3.00 PGAE Gen
HALSEY_6_UNIT HALSEY HYDRO Forced 13.50 7.10 PGAE Gen
HATLOS_6_BWDHY1 Bidwell Ditch Forced 2.00 0.50 PGAE Gen
HATLOS_6_LSCRK Lost Creek 1 & 2 Hydro Conversion Forced 1.70 0.70 PGAE Gen
HATRDG_2_WIND Hatchet Ridge Wind Farm Forced 102.00 0.00 PGAE Gen
HELMPG_7_UNIT 1 HELMS PUMP-GEN UNIT 1 Forced 407.00 0.00 PGAE South
HELMPG_7_UNIT 2 HELMS PUMP-GEN UNIT 2 Planned 407.00 407.00 PGAE South
HENRTA_6_SOLAR1 Lemoore 1 Forced 1.50 1.50 PGAE Gen
HENRTA_6_UNITA1 GWF HENRIETTA PEAKER PLANT UNIT 1 Forced 49.98 2.65 PGAE South
HENRTA_6_UNITA2 GWF HENRIETTA PEAKER PLANT UNIT 2 Forced 49.42 1.49 PGAE South
HIDSRT_2_UNITS HIGH DESERT POWER PROJECT AGGREGATE Forced 830.00 81.00 SCE Gen
HINSON_6_LBECH1 Long Beach Unit 1 Forced 63.00 7.00 SCE Gen
HINSON_6_LBECH2 Long Beach Unit 2 Forced 63.00 9.00 SCE Gen
HINSON_6_LBECH3 Long Beach Unit 3 Forced 63.00 12.00 SCE Gen
HINSON_6_LBECH4 Long Beach Unit 4 Forced 63.00 14.00 SCE Gen
HMLTBR_6_UNITS HAMILTON BRANCH PH (AGGREGATE) Forced 4.90 4.90 PGAE Gen
HNTGBH_2_PL1X3 Huntington Beach Energy Forced 673.80 5.80 SCE Gen
HNTGBH_7_UNIT 2 HUNTINGTON BEACH GEN STA. UNIT 2 Forced 225.80 35.80 SCE Gen
HOOVER_2_MWDDYN HOOVER Forced 249.00 96.00 SCE Gen
HOOVER_2_VEADYN HOOVER Forced 16.00 5.00 SCE Gen
HUMBPP_1_UNITS3 Humboldt Bay Generating Station 3 Planned/Forced 65.08 32.54 PGAE North
HUMBPP_6_UNITS Humboldt Bay Generating Station 1 Planned/Forced 97.62 16.27 PGAE North
HYTTHM_2_UNITS HYATT-THERMALITO PUMP-GEN (AGGREGATE) Planned/Forced 933.10 168.10 PGAE Gen
INDIGO_1_UNIT 1 INDIGO PEAKER UNIT 1 Planned 44.00 0.00 SCE Gen
INDIGO_1_UNIT 2 INDIGO PEAKER UNIT 2 Planned 44.53 0.00 SCE Gen
INDIGO_1_UNIT 3 INDIGO PEAKER UNIT 3 Planned 43.69 0.00 SCE Gen
INLDEM_5_UNIT 1 Inland Empire Energy Center, Unit 1 Planned 376.20 376.20 SCE Gen
INSKIP_2_UNIT INSKIP HYDRO Forced 8.00 8.00 PGAE North
INTKEP_2_UNITS CCSF Hetch_Hetchy Hydro Aggregate Forced 405.00 195.00 PGAE Gen
IVANPA_1_UNIT3 Ivanpah 3 Forced 133.00 6.00 SCE Gen
JAWBNE_2_NSRWND North Sky River Wind Project Forced 160.00 1.60 SCE Gen
JAWBNE_2_SRWND Sky River Forced 77.00 0.00 SCE Gen
JOANEC_2_STABT1 Santa Ana Storage 1 Forced 20.00 20.00 SCE Gen
KANSAS_6_SOLAR RE Kansas South Forced 20.00 0.00 PGAE South
KEKAWK_6_UNIT STS HYDROPOWER LTD. (KEKAWAKA) Forced 5.50 5.50 PGAE Gen
KELSO_2_UNITS Mariposa Energy Forced 198.03 1.13 PGAE Gen
KERKH1_7_UNIT 1 KERKHOFF PH 1 UNIT #1 Forced 13.00 13.00 PGAE North
KERKH1_7_UNIT 1 KERKHOFF PH 1 UNIT #1 Forced 13.00 13.00 PGAE South
KERKH1_7_UNIT 3 KERKHOFF PH 1 UNIT #3 Forced 12.80 12.80 PGAE North
KERKH1_7_UNIT 3 KERKHOFF PH 1 UNIT #3 Forced 12.80 12.80 PGAE South
KERNFT_1_UNITS KERN FRONT LIMITED Forced 52.40 5.20 PGAE South
KERRGN_1_UNIT 1 KERN RIVER HYDRO UNITS 1-4 AGGREGATE Forced 25.60 14.60 SCE Gen
KILARC_2_UNIT 1 KILARC HYDRO Forced 1.50 1.50 PGAE North
KRAMER_2_SEGS 8 KRAMER JUNCTION 8 Forced 80.00 0.00 SCE Gen
KRAMER_2_SEGS89 LUZ SOLAR PARTNERS 8-9 AGGREGATE Forced 80.00 0.00 SCE Gen
LACIEN_2_VENICE MWD Venice Hydroelectric Recovery Plant Forced 9.95 9.95 SCE Gen
LAMONT_1_SOLAR2 Redwood Solar Farm 4 Forced 20.00 0.00 PGAE Gen
LAMONT_1_SOLAR4 Hayworth Solar Farm Forced 26.66 12.66 PGAE South
LAPLMA_2_UNIT 1 La Paloma Generating Plant Unit #1 Forced 267.00 4.00 PGAE Gen
LAPLMA_2_UNIT 2 La Paloma Generating Plant Unit #2 Forced 266.00 18.00 PGAE Gen
LAPLMA_2_UNIT 3 La Paloma Generating Plant Unit #3 Forced 266.00 21.00 PGAE Gen
LAPLMA_2_UNIT 4 LA PALOMA GENERATING PLANT, UNIT #4 Forced 253.29 0.00 PGAE Gen
LAROA2_2_UNITA1 LR2 Forced 322.00 22.00 SDGE Gen
LEBECS_2_UNITS Pastoria Energy Facility Forced 799.47 10.47 SCE Gen
LECEF_1_UNITS LOS ESTEROS ENERGY FACILITY AGGREGATE Forced 309.84 5.84 PGAE South
LIVOAK_1_UNIT 1 LIVE OAK LIMITED Planned/Forced 49.70 6.70 PGAE South
LMBEPK_2_UNITA1 Lambie Energy Center, Unit #1 Forced 47.50 0.00 PGAE Gen
LMBEPK_2_UNITA2 Creed Energy Center, Unit #1 Planned 47.60 47.60 PGAE Gen
LMBEPK_2_UNITA3 Goose Haven Energy Center, Unit #1 Forced 47.40 0.00 PGAE Gen
LMEC_1_PL1X3 Los Medanos Energy Center AGGREGATE Forced 580.00 24.00 PGAE Gen
LNCSTR_6_SOLAR2 SEPV Sierra NGR Forced 2.75 1.55 SCE Gen
LOCKFD_1_BEARCK Bear Creek Solar Forced 1.50 0.00 PGAE Gen
LOCKFD_1_KSOLAR Kettleman Solar Forced 1.00 0.00 PGAE South
LODI25_2_UNIT 1 LODI GAS TURBINE Forced 25.00 3.00 PGAE Gen
LODIEC_2_PL1X2 Lodi Energy Center Forced 302.58 10.58 PGAE Gen
LOWGAP_7_QFUNTS Matthews Dam Hydro Forced 1.35 1.35 PGAE North
MAGNLA_6_COLTON Magnolia Power Project Planned 12.00 2.00 SCE Gen
MAGUND_1_BKSSR2 Bakersfield Solar 1 Forced 5.25 0.00 PGAE Gen
MALCHQ_7_UNIT 1 MALACHA HYDRO L.P. Forced 32.50 0.00 PGAE Gen
MANZNA_2_WIND Manzana Wind Forced 189.00 3.00 SCE Gen
MDFKRL_2_PROJCT MIDDLE FORK AND RALSTON PSP Planned 210.00 210.00 PGAE North
METEC_2_PL1X3 Metcalf Energy Center Forced 593.16 40.16 PGAE Gen
MIDWYS_2_MIDSL1 Midway Solar Farm Forced 49.90 49.90 PGAE Gen
MIRLOM_2_MLBBTA Mira Loma BESS A Planned 10.00 0.00 SCE Gen
MIRLOM_2_MLBBTB Mira Loma BESS B Planned 10.00 0.00 SCE Gen
MKTRCK_1_UNIT 1 MCKITTRICK LIMITED Forced 47.49 5.49 PGAE South
MOJAVW_2_SOLAR Mojave West Forced 20.00 0.00 SCE Gen
MONLTH_6_BATTRY Tehachapi Storage Project Forced 7.99 3.99 SCE Gen
MONLTH_6_BOREL BOREL HYDRO UNITS 1-3 AGGREGATE Forced 11.00 11.00 SCE Gen
MRCHNT_2_PL1X3 Desert Star Energy Center Planned/Forced 494.58 494.58 SDGE Gen
MRGT_6_MEF2 Miramar Energy Facility II Planned 44.00 0.00 SDGE Gen
MRGT_6_MMAREF Miramar Energy Facility Planned 45.00 45.00 SDGE Gen
MTWIND_1_UNIT 1 Mountain View Power Project I Planned/Forced 44.40 6.00 SCE Gen
MTWIND_1_UNIT 2 Mountain View Power Project II Planned/Forced 22.20 2.40 SCE Gen
MTWIND_1_UNIT 3 Mountain View Power Project III Forced 22.44 3.04 SCE Gen
NAROW1_2_UNIT NARROWS PH 1 UNIT Planned 12.00 1.50 PGAE North
NAROW2_2_UNIT Narrows Powerhouse Unit 2 Planned 55.00 55.00 PGAE North
NCPA_7_GP1UN1 NCPA GEO PLANT 1 UNIT 1 Planned/Forced 38.85 38.85 PGAE Gen
NCPA_7_GP1UN2 NCPA GEO PLANT 1 UNIT 2 Planned/Forced 39.94 39.94 PGAE Gen
NCPA_7_GP2UN3 NCPA GEO PLANT 2 UNIT 3 Forced 42.42 42.42 PGAE Gen
NGILAA_5_SDGDYN NGILAA_5_SDGDYN Forced 57.00 4.00 APS Gen
NGILAA_5_SDGDYN NGILAA_5_SDGDYN Forced 57.00 4.00 SDGE Gen
NHOGAN_6_UNITS NEW HOGAN PH AGGREGATE Forced 4.00 4.00 PGAE Gen
OAK C_7_UNIT 1 OAKLAND STATION C GT UNIT 1 Forced 55.00 1.50 PGAE South
OAK C_7_UNIT 3 OAKLAND STATION C GT UNIT 3 Forced 55.00 1.00 PGAE South
OASIS_6_CREST CREST Contracts Forced 13.50 0.00 SCE Gen
OGROVE_6_PL1X2 Orange Grove Energy Center Forced 96.00 0.00 SDGE Gen
OILFLD_7_QFUNTS Nacimiento Hydroelectric Plant Planned 3.80 3.66 PGAE South
OLDRIV_6_CESDBM Ces Dairy Biogas Forced 1.00 0.00 PGAE Gen
OLDRIV_6_LKVBM1 Lakeview Dairy Biogas Forced 1.00 0.00 PGAE Gen
OLINDA_2_COYCRK MWD Coyote Creek Hydroelectric Recovery Forced 3.13 3.13 SCE Gen
OLINDA_2_LNDFL2 Brea Power II Planned/Forced 28.10 22.10 SCE Gen
OMAR_2_UNIT 1 KERN RIVER COGENERATION CO. UNIT 1 Forced 78.00 0.00 SCE Gen
OMAR_2_UNIT 2 KERN RIVER COGENERATION CO. UNIT 2 Forced 78.11 5.01 SCE Gen
OMAR_2_UNIT 3 KERN RIVER COGENERATION CO. UNIT 3 Forced 81.41 5.41 SCE Gen
OMAR_2_UNIT 4 KERN RIVER COGENERATION CO. UNIT 4 Forced 81.44 0.00 SCE Gen
ORLND_6_HIGHLI High Line Canal Hydro Planned 0.50 0.50 PGAE Gen
ORMOND_7_UNIT 1 ORMOND BEACH GEN STA. UNIT 1 Forced 741.27 91.27 SCE Gen
ORMOND_7_UNIT 2 ORMOND BEACH GEN STA. UNIT 2 Forced 750.00 50.00 SCE Gen
OTAY_6_PL1X2 Chula Vista Energy Center, LLC Planned 35.50 35.50 SDGE Gen
OTMESA_2_PL1X3 OTAY MESA ENERGY CENTER Forced 603.68 18.68 SDGE Gen
OXBOW_6_DRUM OXBOW HYDRO Planned 5.80 5.80 PGAE North
OXMTN_6_LNDFIL Ox Mountain Landfill Generating Plant Forced 10.62 10.62 PGAE South
PACLUM_6_UNIT Humboldt Redwood Forced 28.80 6.80 PGAE North
PADUA_2_ONTARO ONTARIO/SIERRA HYDRO PSP Planned 1.92 0.72 SCE Gen
PADUA_6_MWDSDM San Dimas Hydroelectric Recovery Plant Forced 9.90 9.90 SCE Gen
PALALT_7_COBUG Cooperatively Owned Back Up Generator Forced 4.50 4.50 PGAE Gen
PALOMR_2_PL1X3 Palomar Energy Center Forced 575.00 275.00 SDGE Gen
PANSEA_1_PANARO Mesa Wind Project Planned 30.00 24.80 SCE Gen
PARDEB_6_UNITS Pardee Power House Forced 30.00 30.00 PGAE Gen
PEORIA_1_SOLAR Sonora 1 Forced 1.50 0.00 PGAE Gen
PINFLT_7_UNITS PINE FLAT HYDRO AGGREGATE Planned 198.51 198.51 PGAE Gen
PIOPIC_2_CTG1 Pio Pico Unit 1 Forced 111.30 4.25 SDGE Gen
PIOPIC_2_CTG2 Pio Pico Unit 2 Forced 112.70 2.82 SDGE Gen
PIOPIC_2_CTG3 Pio Pico Unit 3 Forced 112.00 3.00 SDGE Gen
PIT1_7_UNIT 1 PIT PH 1 UNIT 1 Planned/Forced 32.00 32.00 PGAE North
PIT1_7_UNIT 2 PIT PH 1 UNIT 2 Planned/Forced 32.00 32.00 PGAE North
PIT3_7_PL1X3 PIT PH 3 UNITS 1, 2 & 3 AGGREGATE Planned 70.60 43.60 PGAE North
PIT5_7_PL1X2 PIT PH 5 UNITS 1 & 2 AGGREGATE Planned 82.00 82.00 PGAE North
PIT6_7_UNIT 1 PIT PH 6 UNIT 1 Forced 39.00 0.17 PGAE North
PIT6_7_UNIT 2 PIT PH 6 UNIT 2 Forced 40.00 1.17 PGAE North
PIT7_7_UNIT 1 PIT PH 7 UNIT 1 Forced 55.70 2.07 PGAE North
PIT7_7_UNIT 2 PIT PH 7 UNIT 2 Forced 54.60 0.97 PGAE North
PLAINV_6_BSOLAR Western Antelope Blue Sky Ranch A Forced 20.00 2.00 SCE Gen
PLAINV_6_SOLAR3 Sierra Solar Greenworks LLC Forced 20.00 3.00 SCE Gen
PLMSSR_6_HISIER High Sierra Cogeneration Aggregate Forced 6.00 6.00 PGAE Gen
PMPJCK_1_SOLAR1 Pumpjack Solar I Planned 20.00 0.00 PGAE Gen
PNCHEG_2_PL1X4 PANOCHE ENERGY CENTER (Aggregated) Planned/Forced 401.00 401.00 PGAE Gen
PNCHPP_1_PL1X2 Midway Peaking Aggregate Forced 119.91 3.91 PGAE Gen
PNOCHE_1_PL1X2 Panoche Peaker Forced 49.97 4.97 PGAE South
PNOCHE_1_UNITA1 CalPeak Power Panoche Unit 1 Forced 52.01 0.00 PGAE Gen
POEPH_7_UNIT 1 POE HYDRO UNIT 1 Forced 69.00 67.00 PGAE North
POEPH_7_UNIT 2 POE HYDRO UNIT 2 Forced 68.50 61.27 PGAE North
POTTER_6_UNITS Potter Valley Forced 10.10 4.80 PGAE North
PWEST_1_UNIT PACIFIC WEST 1 WIND GENERATION Forced 2.10 2.10 SCE Gen
RAMON_2_SCEDYN RAMON_2_SCEDYN Forced 106.18 42.18 SCE Gen
RCKCRK_7_UNIT 2 ROCK CREEK HYDRO UNIT 2 Forced 56.90 56.90 PGAE North
RDWAY_1_CREST CREST Contracts Forced 6.50 0.00 SCE Gen
RECTOR_2_KAWEAH KAWEAH PH 2 & 3 PSP AGGREGATE Planned/Forced 6.55 6.55 SCE Gen
RECTOR_2_KAWH 1 KAWEAH PH 1 UNIT 1 Forced 2.25 2.25 SCE Gen
RECTOR_2_QF Kaweah Unit 1 Planned 17.00 17.00 SCE Gen
RECTOR_2_TFDBM1 Two Fiets Dairy Digester Forced 0.80 0.80 SCE Gen
REDOND_7_UNIT 5 REDONDO GEN STA. UNIT 5 Forced 178.87 68.87 SCE Gen
REDOND_7_UNIT 6 REDONDO GEN STA. UNIT 6 Forced 175.00 55.00 SCE Gen
REDOND_7_UNIT 8 REDONDO GEN STA. UNIT 8 Forced 480.00 480.00 SCE Gen
RENWD_1_QF Renwind re-powering project Forced 10.00 1.00 SCE Gen
RICHMN_1_CHVSR2 Chevron 8.5 Forced 8.50 8.50 PGAE Gen
RICHMN_7_BAYENV BAY ENVIRONMENTAL (NOVE POWER) Forced 2.50 2.50 PGAE Gen
RIOBRV_6_UNIT 1 RIO BRAVO HYDRO Forced 14.00 14.00 PGAE Gen
RNDSBG_1_HZASR1 Hazel A Forced 2.99 0.00 SCE Gen
ROLLIN_6_UNIT ROLLINS HYDRO Forced 13.50 8.02 PGAE North
ROSMDW_2_WIND1 Pacific Wind - Phase 1 Planned 140.00 0.00 SCE Gen
ROSMND_6_SOLAR Lancaster B Forced 3.00 0.00 SCE Gen
RTEDDY_2_SC1SR3 Rosamond West Solar Clean Forced 40.00 40.00 SCE Gen
RTEDDY_2_SEBSR3 Rosamond West Solar East Bay 3 Forced 56.00 56.00 SCE Gen
RTEDDY_2_SEBSR4 Rosamond West Solar East Bay 4 Forced 56.00 56.00 SCE Gen
RTEDDY_2_SOLAR1 Rosamond West Solar 1 Forced 54.00 18.00 SCE Gen
RTEDDY_2_SOLAR2 Rosamond West Solar 2 Forced 54.00 12.00 SCE Gen
RTEDDY_2_SPASR4 Rosamond West Solar Palo Alto Forced 26.00 26.00 SCE Gen
RTEDDY_2_SRXSR4 Rosamond West Solar Rosie X Forced 14.00 14.00 SCE Gen
RTREE_2_WIND2 Rising Tree 2 Forced 19.80 0.00 SCE Gen
RUSCTY_2_UNITS Russell City Energy Center Forced 620.50 14.40 PGAE South
RVRVEW_1_UNITA1 Riverview Energy Center (GP Antioch) Forced 47.60 12.60 PGAE Gen
RVSIDE_2_RERCU3 Riverside Energy Res. Ctr Unit 3 Forced 49.00 0.00 SCE Gen
RVSIDE_2_RERCU4 Riverside Energy Res. Ctr Unit 4 Forced 49.00 0.00 SCE Gen
RVSIDE_6_RERCU1 Riverside Energy Res. Ctr Unit 1 Forced 48.35 0.00 SCE Gen
RVSIDE_6_RERCU2 Riverside Energy Res. Ctr Unit 2 Forced 48.50 0.00 SCE Gen
RVSIDE_6_SPRING SPRINGS GENERATION PROJECT AGGREGATE Forced 36.00 0.00 SCE Gen
SANDLT_2_SUNITS Mojave Solar Forced 275.00 50.00 SCE Gen
SANTFG_7_UNITS GEYSERS CALISTOGA AGGREGATE Forced 92.10 92.10 PGAE Gen
SANWD_1_QF San Gorgonio Farms Wind Farm Planned 31.00 5.18 SCE Gen
SBERDO_2_PSP3 Mountainview Gen Sta. Unit 3 Forced 555.00 4.00 SCE Gen
SBERDO_2_PSP4 Mountainview Gen Sta. Unit 4 Forced 555.00 0.00 SCE Gen
SBERDO_2_SNTANA SANTA ANA PSP Planned 6.95 6.95 SCE Gen
SBERDO_6_MILLCK MILL CREEK PSP Planned/Forced 3.93 3.33 SCE Gen
SCEC_1_PDRP124 LCR AMS Hybrid West LA 1-C-LCRLL Forced 1.56 0.00 SCE Gen
SCEC_1_PDRP172 LCR AMS Hybrid West LA 1-C-LSCE Forced 0.52 0.00 SCE Gen
SCEC_1_PDRP173 LCR AMS Hybrid West LA 2-C-LSCE Forced 1.97 0.00 SCE Gen
SCEC_1_PDRP34 LCR AMS Hybrid West LA 1-C-LCRLL Forced 0.23 0.00 SCE Gen
SCEHOV_2_HOOVER SCEHOV_2_HOOVER Forced 287.01 112.01 SCE Gen
SCEW_2_PDRP114 LCR AMS Hybrid West LA 1-W-SCE Forced 18.71 0.00 SCE Gen
SCEW_2_PDRP115 LCR AMS Hybrid West LA 1-W-LCRLL Forced 3.50 1.85 SCE Gen
SCEW_2_PDRP158 LCR AMS Hybrid West LA 1-W-LCEM1 Forced 0.26 0.00 SCE Gen
SCEW_2_PDRP159 LCR AMS Hybrid West LA 1-W-LNEI1 Forced 1.45 0.00 SCE Gen
SCEW_2_PDRP160 LCR AMS Hybrid West LA 2-W-LSCE Forced 7.82 0.00 SCE Gen
SCEW_2_PDRP162 LCR AMS Hybrid West LA 2-W-LNEI1 Forced 0.24 0.00 SCE Gen
SCEW_2_PDRP163 LCR AMS Hybrid West LA 2-W-LPIPO Forced 2.64 0.00 SCE Gen
SCEW_2_PDRP164 LCR AMS Hybrid West LA 2-W-LLACC Forced 0.45 0.00 SCE Gen
SCEW_2_PDRP167 LCR AMS Hybrid West LA 1-W-2-SCE Forced 9.05 0.00 SCE Gen
SCEW_2_PDRP169 LCR AMS Hybrid West LA 1-C-LUCOP Forced 1.80 0.00 SCE Gen
SCEW_2_PDRP22 LCR AMS Hybrid West LA 1-W-LPIPO Forced 0.70 0.00 SCE Gen
SCHLTE_1_PL1X3 Tracy Combined Cycle Power Plant Forced 336.04 18.51 PGAE Gen
SCHNDR_1_OS2BM2 Open Sky Digester Genset 2 Forced 0.80 0.80 PGAE Gen
SCHNDR_1_WSTSDE Westside Solar Station Forced 15.00 1.00 PGAE Gen
SEGS_1_SR2SL2 Sunray 2 Forced 20.00 20.00 SCE Gen
SENTNL_2_CTG2 Sentinel Unit 2 Forced 95.34 3.34 SCE Gen
SENTNL_2_CTG3 Sentinel Unit 3 Forced 96.85 96.85 SCE Gen
SENTNL_2_CTG4 Sentinel Unit 4 Forced 102.47 102.47 SCE Gen
SENTNL_2_CTG5 Sentinel Unit 5 Forced 103.81 103.81 SCE Gen
SENTNL_2_CTG6 Sentinel Unit 6 Forced 100.99 100.99 SCE Gen
SENTNL_2_CTG7 Sentinel Unit 7 Forced 97.06 5.06 SCE Gen
SENTNL_2_CTG8 Sentinel Unit 8 Forced 101.80 9.80 SCE Gen
SGREGY_6_SANGER Algonquin Power Sanger 2 Planned 48.30 0.00 PGAE Gen
SHUTLE_6_CREST CREST Contracts Forced 4.00 0.00 SCE Gen
SIERRA_1_UNITS HIGH SIERRA LIMITED Forced 52.43 3.93 PGAE Gen
SLST13_2_SOLAR1 Quinto Solar PV Project Planned/Forced 107.60 0.00 PGAE Gen
SLSTR1_2_SOLAR1 Solar Star 1 Forced 310.00 0.00 SCE Gen
SLSTR2_2_SOLAR2 Solar Star 2 Forced 276.00 0.00 SCE Gen
SLUISP_2_UNITS SAN LUIS (GIANELLI) PUMP-GEN (AGGREGATE) Planned 374.43 104.43 PGAE Gen
SLYCRK_1_UNIT 1 SLY CREEK HYDRO Forced 13.00 13.00 PGAE North
SMPRIP_1_SMPSON Ripon Cogeneration Unit 1 Planned 46.05 46.05 PGAE Gen
SMUDGO_7_UNIT 1 SONOMA POWER PLANT Forced 53.00 53.00 PGAE Gen
SNCLRA_2_UNIT1 New Indy Oxnard Planned 27.80 16.80 SCE Gen
SNDBAR_7_UNIT 1 SANDBAR Planned 16.20 16.20 PGAE North
SOUTH_2_UNIT SOUTH HYDRO Planned 7.10 7.10 PGAE Gen
SPAULD_6_UNIT12 SPAULDING HYDRO PH 1 & 2 AGGREGATE Forced 11.40 11.40 PGAE North
SPRGVL_2_CREST Springerville Aggregate Solar Resources Forced 14.00 1.50 SCE Gen
SPRGVL_2_TULESC TULE RIVER HYDRO PLANT (SCE) Forced 2.50 2.50 SCE Gen
STANIS_7_UNIT 1 STANISLAUS HYDRO Planned 91.00 91.00 PGAE North
STANTN_2_STAGT1 Stanton 1 Forced 49.65 0.00 SCE Gen
STANTN_2_STAGT2 Stanton 2 Forced 49.65 0.00 SCE Gen
STIGCT_2_LODI LODI STIG UNIT Forced 49.90 0.90 PGAE Gen
STROUD_6_SOLAR Stroud Solar Station Forced 20.00 2.00 PGAE South
SUNRIS_2_PL1X3 Sunrise Power Project AGGREGATE II Forced 586.02 24.02 PGAE Gen
SUNSET_2_UNITS MIDWAY SUNSET COGENERATION PLANT Planned/Forced 248.00 89.00 PGAE South
SUNSHN_2_LNDFL Sunshine Gas Producers Forced 20.00 5.50 SCE Gen
SWIFT_1_NAS YERBA BUENA BATTERY Forced 4.80 2.80 PGAE South
SYCAMR_2_UNIT 1 Sycamore Cogeneration Unit 1 Forced 86.00 7.53 SCE Gen
SYCAMR_2_UNIT 2 Sycamore Cogeneration Unit 2 Forced 78.00 6.00 SCE Gen
SYCAMR_2_UNIT 3 Sycamore Cogeneration Unit 3 Forced 78.00 6.00 SCE Gen
SYCAMR_2_UNIT 4 Sycamore Cogeneration Unit 4 Forced 78.00 7.00 SCE Gen
TANHIL_6_SOLART Berry Cogen 18 Forced 17.00 0.00 PGAE South
TENGEN_2_PL1X2 Berry Cogen 42 Planned 40.20 40.20 SCE Gen
TERMEX_2_PL1X3 TDM Planned/Forced 625.00 6.00 SDGE Gen
TIFFNY_1_DILLON TIFFNY_1_DILLON Forced 45.00 1.00 SCE Gen
TKOPWR_6_HYDRO Bear Creek Hydroelectric Project Planned/Forced 2.83 2.83 PGAE Gen
TRNQL8_2_AMASR1 Tranquillity 8 Amarillo Forced 20.00 0.00 PGAE Gen
TRNQL8_2_ROJSR1 Tranquillity 8 Rojo Forced 100.00 0.00 PGAE Gen
TRNQL8_2_VERSR1 Tranquillity 8 Verde Forced 60.00 0.00 PGAE Gen
TRNSWD_1_QF FPL Energy C Wind Forced 38.97 38.97 SCE Gen
TX-ELK_6_SOLAR1 Castor Forced 1.50 0.00 PGAE Gen
UNOCAL_1_UNITS TOSCO (RODEO PLANT) Forced 49.85 0.00 PGAE South
USWND2_1_WIND1 Golden Hills A Planned 42.96 0.00 PGAE Gen
USWND2_1_WIND2 Golden Hills B Planned/Forced 42.96 1.79 PGAE Gen
USWND2_1_WIND3 Golden Hills C Planned/Forced 46.00 9.20 PGAE Gen
USWNDR_2_LABWD1 LaBrisa Wind Project Forced 9.00 1.50 PGAE Gen
USWNDR_2_SMUD SOLANO WIND FARM Forced 102.18 4.32 PGAE Gen
USWNDR_2_SMUD2 Solano Wind Project Phase 3 Forced 127.80 0.00 PGAE Gen
USWPJR_2_UNITS Vasco Wind Forced 78.20 9.20 PGAE Gen
VACADX_1_NAS VACA-DIXON BATTERY Forced 1.85 1.85 PGAE North
VACADX_1_UNITA1 CalPeak Power Vaca Dixon Unit 1 Forced 50.61 50.61 PGAE Gen
VALLEY_5_PERRIS MWD Perris Hydroelectric Recovery Plant Forced 7.94 7.94 SCE Gen
VALLEY_5_REDMTN MWD Red Mountain Hydroelectric Recovery Forced 5.90 5.90 SCE Gen
VERNON_6_GONZL1 H. Gonzales Unit #1 Forced 5.75 5.75 SCE Gen
VESTAL_2_KERN KERN RIVER PH 3 UNITS 1 & 2 AGGREGATE Forced 36.80 36.30 SCE Gen
VICTOR_1_CREST Victor Aggregate Solar Resources Forced 24.50 0.00 SCE Gen
VICTOR_1_SLRHES Sunedison - Hesperia Forced 1.50 0.00 SCE Gen
VILLPK_2_VALLYV MWD Valley View Hydroelectric Recovery P Forced 4.10 4.10 SCE Gen
VILLPK_6_MWDYOR Yorba Linda Hydroelectric Recovery Plant Forced 5.10 5.10 SCE Gen
VINCNT_2_WESTWD Oasis Power Plant Forced 59.00 59.00 SCE Gen
VLCNTR_6_VCSLR Cole Grade Forced 2.33 0.00 SDGE Gen
VSTAES_6_VESBT1 Vista Energy Storage Forced 40.00 1.50 SDGE Gen
WADHAM_6_UNIT Wadham Energy LP Planned 29.07 29.07 PGAE North
WALCRK_2_CTG1 Walnut Creek Energy Park Unit 1 Forced 96.43 96.43 SCE Gen
WALCRK_2_CTG2 Walnut Creek Energy Park Unit 2 Forced 96.91 0.00 SCE Gen
WALCRK_2_CTG3 Walnut Creek Energy Park Unit 3 Forced 96.65 96.65 SCE Gen
WALCRK_2_CTG4 Walnut Creek Energy Park Unit 4 Forced 96.49 0.00 SCE Gen
WALCRK_2_CTG5 Walnut Creek Energy Park Unit 5 Forced 96.65 96.65 SCE Gen
WARNE_2_UNIT WARNE HYDRO AGGREGATE Planned/Forced 76.00 76.00 SCE Gen
WDLEAF_7_UNIT 1 WOODLEAF HYDRO Forced 60.00 60.00 PGAE North
WFRESN_1_SOLAR Joya Del Sol Forced 1.50 0.00 PGAE Gen
WHTWTR_1_WINDA1 Whitewater Hill Wind Project Forced 61.50 26.50 SCE Gen
WISE_1_UNIT 1 Wise Hydro Unit 1 Forced 14.50 5.40 PGAE Gen
WISE_1_UNIT 2 WISE HYDRO UNIT 2 Planned/Forced 3.20 3.20 PGAE North
WNDMAS_2_UNIT 1 BUENA VISTA ENERGY, LLC Forced 38.00 2.00 PGAE Gen
YUBACT_6_UNITA1 Yuba City Energy Center (Calpine) Forced 47.60 2.60 PGAE North
ZOND_6_UNIT ZOND WINDSYSTEMS INC. Forced 17.10 17.10 PGAE Gen
ALMASL_2_GS1SR1 Almasol Generating Station 1 Forced 125.00 0.00
ALMASL_2_GS4SR4 Almasol Generating Station 4 Forced 100.00 100.00
APLHIL_1_SFKHY1 South Fork Powerhouse Forced 2.68 0.00
CABALO_2_M2BSR1 Mustang 2 Barbaro Solar Planned 50.00 50.00
CABALO_2_M2WSR2 Mustang 2 Whirlaway Solar Forced 100.00 100.00
DSRTHV_2_DH1SR1 Desert Harvest Forced 80.00 0.00
DSRTHV_2_DH2BT1 Desert Harvest BESS Forced 35.00 35.00
DSRTHV_2_DH2SR2 Desert Harvest 2 Forced 35.00 0.00
MALIN_5_HERMDYN MALIN_5_HERMDYN Forced 308.00 308.00
SUTTER_2_CISO Sutter Power Plant Pseudo-CISO Forced 275.00 13.00
VOLTA_7_PONHY1 VOLTA_7_PONHY1 Forced 1.25 1.25


Outage Summary
Zone Name Number Of Outages MW's
Planned Forced Limitation Shutdown
APS Gen 1 5 4.00 795.00
PGAE Gen 39 173 953.12 2404.56
PGAE North 30 55 527.59 1256.23
PGAE South 8 68 297.82 1688.01
SCE Gen 38 227 1396.84 4014.89
SDGE Gen 14 31 340.50 933.69
1 17 13.00 594.25
Total 131 576 3532.87 11686.63


Report Generated on:
10/06/2020 08:30:00 (PPT)
Filtered Parameters:
Date = 10/06/2020
Resource = ALL
Area = ALL
States = ALL
Outage Origin = CAISO

The content of these pages is subject to change without notice. Decisions based on information contained within the California ISO web site are the visitor's sole responsibility.