The California ISO has published an updated Business Requirements Specification (BRS) for the Energy Storage and Distributed Energy Resources Phase 3 (ESDER3) project to reflect revised implementation plans for ESDER3:
- Section 4:
- Updated project change statement to indicate the implementation time frames for each major element
- Inserted Fall 2019 for ESDER3A scopes:
- Bid Dispatchable Option
- Remove Single Load Serving Entity Requirement and Default Load Adjustment
- Customer Load Baseline Submittal
- Inserted Fall 2020 for ESDER3B scopes:
- Load Shift Product
- Behind-the-Meter Electric Vehicle Storage Equipment
- Section 5:
- Added column to indicate implementation period (2019-3A or 2020-3B)
- Updated Business Practice Manual impacts to align with implementation period
- Section 6:
- Subsection titles - added indication of implementation period (2019-3A or 2020-3B)
- Added subsection 6.5 - Manage Customer Load Baseline Submittals
- Changed text to RED for scopes to be implemented in 2020
The BRS is available on the ISO website at http://www.caiso.com/Documents/BusinessRequirementsSpecificationv12Clean-EnergyStorageandDistributedEnergyResourcesPhase3.pdf.
For more information on the ESDER3 implementation, please visit the Release Planning webpage on the ISO website at http://www.caiso.com/informed/Pages/ReleasePlanning/Default.aspx.