The California ISO has revised the operating procedures referenced below.
2210Z Effectiveness Factors - All, version 27.4, effective Nov. 21, 2019
- 6310: Relabeled Table 3 (Parts 1 & 2) and added Control Point numbers; Table 3, Part 1: Added CP#11, Dos Amigos Pumping Plant - Panoche 230; added CP #12, LBN path flow (S->N); added CP #13 & 14, Path 15 flow (S->N). Table 3, Part 2: Added CP#11, Dos Amigos Pumping Plant - Panoche 230; added CP #12, LBN path flow (S->N); added CP #13 & 14, Path 15 flow (S->N). Updated to version 22.3, effective 11/01/19.
- Updated version and dates only for the following:
- 6110: version 9.0, effective 11/01/19
- 6140: version 6.4, effective 11/01/19
- 6610: version 12.9, effective 10/02/19
- 7820: version 15.16, effective 11/01/19
3210 Transmission Outages, version 16.9, effective Nov. 21, 2019
Section 3.1.1: Added new paragraph to address planned outages submitted as forced outages.
Section 5: Corrected section title.
Minor format and grammar updates.
ISO Operating Procedures - http://www.caiso.com/rules/Pages/OperatingProcedures/Default.aspx