ISO Logo
 
Notice
August 28, 2020

REQUESTED ACTION

Forward to Operating Department 

CATEGORIES

Operations
Notification of Revised ISO Operating Procedures 5210A, 5210B, 5310 and 5730

MESSAGE

The California ISO has revised the operating procedures referenced below.

 

5210A Transmission Desk Logging, version 8.0, effective Aug. 28, 2020.

Periodic Review:

Added Sections 1.6 & 1.7, which were taken from procedure 5210B, as they apply to Transmission Desk.

Minor format and grammar updates.

 

5210B Generation Desk Logging, version 7.0, effective Aug. 28, 2020.

Periodic Review:

Section 2: Reorganized Logging Types table by Log Title alphabetically.  Removed outdated items no longer utilized and included new ones that are.

Removed Sections 3 and 4, as they apply to Transmission Desk and better suited in procedure 5210A.

Minor format and grammar updates. .

 

5310 Generation Station Requirements and Communications, version 5.0, effective Aug. 28, 2020.

Periodic Review:

  • Updated Purpose and Responsible parties with Generator Operator (GOP) replacing Participating Generator (PG) throughout. This is to be consistent with OP 5110 using the North American Electric Reliability Corporation (NERC) definition versus tariff name
  • Removed Step 8 from 3.3.
  • Removed reference for PG to contact other ISO control room with new phone system this doesn’t apply
  • Updated Link in 3.1 to link Generation Outages 3220.
  • Minor format and grammar updates.

 

5730 Metering Exemptions from Compliance, version 3.0, effective Aug. 28, 2020.

Periodic Review:

Updated roles/responsibilities. 

Minor format and grammar updates.

 


CONTACT INFORMATION

ISO Procedure Control Desk at ProcedureControl@caiso.com

Engage with us!
isoball twitterball RSSball Facebookball YouTube
Daily Briefing
Sign up
for
Daily Briefing
ISO Today
Download
ISO Today
Flex Alerts
Sign up
for
Flex Alerts

California Independent System Operator | P.O. Box 639014 | Folsom, CA 95630 | United States