The California ISO has revised the operating procedures referenced below.
1510 Pre-schedule and Check-out Validation, version 6.1, effective Dec. 6, 2022
Periodic Review: Updated North American Electric Reliability Corporation (NERC) Requirements, updated from ISO to CAISO throughout, and minor format and grammar edits. Removed history prior to five years.
2550 Inadvertent Interchange ATEC Payback, version 6.2, effective Dec. 6, 2022
Section 3.2: Updated to align with NERC Standard BAL-004-WECC-3 Reliability Standard Audit Worksheet (RSAW) evidence. Minor format and grammar edits.
5360B Black Start Resource Test Report Form, version 2.2, effective Dec. 6, 2022
Minor update to include updated Section C.18, form fields and minor punctuation edits.