The California ISO has revised the operating procedure referenced below.
2710 Market Disruption - RTM Failure and Suspension, version 5.2, effective Feb. 16, 2023.
Updated all instances of Energy Imbalance Market (EIM) to Western Energy Imbalance Market (WEIM) and spelled out first instance. Removed history prior to five years.
5140 California ISO Market Participant Inquiries, version 4.3, effective Feb. 16, 2023.
Updated title to reflect California ISO and purpose to reflect first instance as California ISO (CAISO). Updated from EIM to WEIM with first instance spelled out in Sections 1 and 2.
5210E Real-Time Market Desk Logging, version 2.2, effective Feb. 16, 2023.
Periodic Review: Updated all instances of EIM to WEIM, spelling out the first instance. Updated remaining instances of ISO to CAISO, “Real Time” to “Real-Time”, “Day Ahead” to “Day-Ahead”, and “A/S” to “AS”. Removed history prior to five years.
5750 Settlement Quality Meter Data (SQMD) Plan – Submission & Approval Process (External), version 2.4, effective Feb. 16, 2023.
Section 2.2: Updated reference to “Western” Energy Imbalance Market (WEIM).
Section 3.1.2: Updated all applicable instances of EIM to WEIM.
Minor edit under Operationally Affected Parties for procedures consistency.
The California ISO’s operating procedures are available on the Operating Procedures webpage.