August 1, 2022
REQUESTED ACTION
Information Only
Forward to Operating Department
CATEGORIES
Operations
Primary frequency response requirements to support California ISO compliance with Reliability Standard BAL-003-1.1
MESSAGE

Under the California ISO’s tariff and applicable interconnection agreements, certain resources within the ISO’s balancing authority area have an obligation to provide primary frequency response capability:

 

  • Participating generators equipped with a governor (ISO Tariff Section 4.6.5.1); 
  • Resources certified to provide spinning reserve (ISO Tariff Section 8.4.4); and 
  • Resources, synchronous or non-synchronous, that have a requirement to comply with Federal Energy Regulatory Commission Order No. 842 (Essential Reliability Services and the Evolving Bulk-Power System—Primary Frequency Response 162 FERC ¶ 61,128 (2018).

 

Scheduling coordinators for these resources and resource owners/operators should validate whether they have configured their resource controls to provide primary frequency response capability consistent with the ISO tariff and their applicable interconnection agreements.

CONTACT INFORMATION

Please contact Ali Miremadi at amiremadi@caiso.com with any questions.