  • Bucket 3 – Market preparation
    These items are the most critical to reach the desired implementation date with the ISO. The Bucket 3 deliverables need careful consideration and planning. All the bucket 3 items are required and need to be accepted 30 days in advance of estimated Implementation date of the resource. Please refer to the New Resource Implementation Guide for further details on each specific document required.
    • Letter of Intent (LOI) to become a Participating Intermittent Resource
      PIRP resources must complete the Letter of Intent in addition to the standard Participating Generator certification agreements.
    • Resource entity management - generator resource data template (GRDT)
      The Scheduling Coordinator must review and submit the final version of the Generator Resource Data Template (GRDT) on behalf of the legal owner/developer.
    • Scheduling Coordinator selection and acceptance
      The Scheduling Coordinator association cannot be completed until Bucket 1-2 requirements are fulfilled, the Resource ID is in the Full Network Model (FNM) production build, and the final Generator Resource Data Template has been accepted.
    • Metering and telemetry
    • RIG engineering
      Agreements and certificate requests must be submitted to the ISO before starting telemetry testing. Project owners must submit a Device Certificate Request Form (ARRF) with the Certificate Signing Request (CSR) file to Certificate Requests. Please allow 10 business days for review and approvals.