  • Bucket 4 – Trial operations approval
    Trial operations testing includes preliminary validation of meter data. Buckets 1 through 4 deliverables must be completed and accepted in order to request to synchronize to the grid. This Request can take up to 10 business days to complete. Metering and telemetry Point to Point testing must also be successfully completed. Final validation of metering and telemetry data will be conducted after synchronization using actual generation data.