Late Schedules Submitted by Scheduling Coordinators
Delaying the Close of ISO Markets

Market Closing Date: 07/19/2008
 
Market Type: DA_CLOSE_REV_PREF_SCHEDS 12:00
  Reason for late close:  SC late validated schedules
  SC's submitting late validated schedules: BRS9 07/19/2008 12:27:54, CRLP 07/19/2008 12:14:42, SCE1 07/19/2008 12:24:25
 
Market Type: Hour Ahead Scheduled Closing 13:45
  Reason for late close:  SC late validated schedules
  SC's submitting late validated schedules: DYN1 07/19/2008 13:52:04
 
Market Type: Hour Ahead Scheduled Closing 14:45
  Reason for late close:  SC late validated schedules
  SC's submitting late validated schedules: MRNT 07/19/2008 14:47:22, PCG2 07/19/2008 14:47:40, MRNT 07/19/2008 14:50:43, PCG2 07/19/2008 14:47:40
 
Market Type: Hour Ahead Scheduled Closing 17:45
  Reason for late close:  SC late validated schedules
  SC's submitting late validated schedules: FPPM 07/19/2008 17:47:01, MVPP 07/19/2008 17:47:29, NECC 07/19/2008 17:47:08, PGAB 07/19/2008 17:47:18, SEES 07/19/2008 17:50:52
 
Market Type: Hour Ahead Scheduled Closing 21:45
  Reason for late close:  SC late validated schedules
  SC's submitting late validated schedules: CALJ 07/19/2008 21:52:40, CPSC 07/19/2008 21:46:08, PCPM 07/19/2008 21:49:10, PGAB 07/19/2008 21:53:00, PWRX 07/19/2008 21:45:31, SCE5 07/19/2008 21:57:52, TEMU 07/19/2008 21:49:19
 
Market Type: Hour Ahead Scheduled Closing 22:45
  Reason for late close:  SC late validated schedules
  SC's submitting late validated schedules: CRLP 07/19/2008 22:48:47, MRNT 07/19/2008 22:47:19, SETC 07/19/2008 22:48:08
 
Market Type: Hour Ahead Scheduled Closing 23:45
  Reason for late close:  SC late validated schedules
  SC's submitting late validated schedules: CNCO 07/19/2008 23:50:05, CRLP 07/19/2008 23:53:43, MRNT 07/19/2008 23:53:36
 
 
The Compliance Reports posted on this web page list instances where a Scheduling Coordinator has failed to comply with ISO Tariff Section 2.5.26 Penalties for Failure to Pass Tests and Rescission of Payment for Non-Delivery or Scheduling Protocol Section 3 Time Lines. These Compliance Reports are based on the best information available to the CAISO at the time a report is published. Given that multiple factors may cause this information to change, the accuracy of this information cannot be assured. These reports are provided solely for informational purposes. Reliance by any party on the contents of these reports, regardless of any errors, omissions, inaccuracies, and/or subsequent changed conditions shall not be the basis for any claim, demand or cause for action against the CAISO. Any decisions or actions by any party based in any way whatsoever on the contents of these report shall be the sole responsibility of that party. In no event shall the ISO be liable to any Market Participant for any losses, damages, claims, liability, costs or expense (including legal expenses) or consequential or indirect financial loss including but not limited to loss of profit, loss of earnings or revenue, loss of use, loss of contract or loss of goodwill arising from the publication of this data.
Produced at: 07/20/2008 03:00:05