​Frequency response

This initiative will explore how to ensure acceptable dynamic response to frequency changes during the initial seconds to one minute following a large disturbance, which is critical for system reliability. Frequency response is provided by turbines and frequency responsive load. The system’s ability to respond sufficiently and quickly protects equipment by limiting the magnitude of the disturbance.

 

Outcome

Software deployment for BAL-003 consisted of the creation of a new settlements charge code for allocating costs associated with the procurement of Transferred Frequency Response Obligation. FERC approved the system changes in February 2017.

Implemented: September 30, 2016
FERC approval: February 2, 2017
Tariff amendment filing: April 21, 2016
Board of Governors approval: March 25, 2016

 