Skip Ribbon Commands
Skip to main content
Sign In

 

  • Generator interconnection and deliverability allocation procedures reassessment
    This initiative will examine topics that arose following the first annual reassessment of the generation interconnection and deliverability allocation procedures. These topics include potential adjustments to cost caps and interconnection financial posting requirements resulting from a reassessment, and possible use of forfeited funds from interconnection customer project withdrawals to offset financial impacts on remaining customers in the queue and applicable participating transmission owners.
    • Outcome
      FERC approval: Aug 5, 2014; Tariff amendment filing: Jun 19, 2014 (ER14-2225); Board of Governors approval: May 29, 2014
    • Generator interconnection and deliverability allocation procedures reassessment - papers and proposals