  • Outcome
    This amendment requires participating transmission owners to submit a request for a planned transmission maintenance outage or a change to an approved maintenance outage at least seven days in advance of the start date for the outage. The timeline for submitting the required advance notice is calculated by excluding the day the request is submitted and the day the outage is scheduled to commence. — Effective: Aug. 6, 2012; FERC approval: July 25, 2012; Tariff amendment filing: Jun 6, 2012 (ER12-1972); Board of Governors approval: Feb. 16, 2012