  • Generator project downsizing
    This initiative will explore additional opportunities for customers in cluster 4 and earlier in the generator interconnection study queue to downsize the capacity of their projects.
    • Outcome
      Effective Jan 01, 2013 FERC conditionally accepted the ISO tariff amendment that allows interconnection customers in the queue prior to cluster five to submit a one-time request to downsize the capacity of their projects by Jan 04, 2013. — FERC approval: Sep 25, 2013; Tariff amendment filing: Oct 29, 2012 (ER13-218); Board of Governors approval: Sep 13, 2012
    • Generator project downsizing - papers and proposals