  • Outcome
    The tariff now specifies the ISO process for seeking FERC approval, on a case-by-case basis, to allocate reliability-related penalties either directly to participants whose actions caused or contributed to violations or to all participants when cause cannot be established. The tariff also includes procedural protections for a participant who may be subject to a direct allocation request. — Effective: March 5, 2012; FERC order: May 25, 2012 (ER12-760); Tariff amendment filing: Jan 4, 2012 (ER12-760); Board of Governors approval: Dec. 15, 2011