| Resource ID | Resource Name | Outage Type | Capacity (MW) | Curtailed (MW) | Zone Name | 
      
      
        | ALAMIT_7_UNIT 1 | ALAMITOS GEN STA. UNIT 1 | Planned | 174.56 | 0.00 | SCE Gen | 
      
        | ALAMIT_7_UNIT 2 | ALAMITOS GEN STA. UNIT 2 | Forced | 175.00 | 0.00 | SCE Gen | 
      
        | ALTA3A_2_CPCE8 | CPC East - Alta Wind 8 | Planned | 150.00 | 0.00 | SCE Gen | 
      
        | ALTA4B_2_CPCW6 | CPC West - Alta Wind 6 | Planned | 150.00 | 0.00 | SCE Gen | 
      
        | ALTA6B_2_WIND11 | Alta Wind 11 | Forced | 90.00 | 0.00 | SCE Gen | 
      
        | ALTA6E_2_WIND10 | Alta Wind 10 | Forced | 138.00 | 0.00 | SCE Gen | 
      
        | ANAHM_7_CT | ANAHEIM COMBUSTION TURBINE | Forced | 42.81 | 42.81 | SCE Gen | 
      
        | ARBWD_6_QF | Wind Resource II | Forced | 19.95 | 0.65 | SCE Gen | 
      
        | BIGCRK_2_EXESWD | BIG CREEK HYDRO PROJECT PSP | Planned | 820.00 | 767.00 | SCE Gen | 
      
        | BISHOP_1_ALAMO | BISHOP CREEK PLANT 2  AND  6 | Planned/Forced | 13.40 | 4.50 | SCE Gen | 
      
        | BISHOP_1_UNITS | BISHOP CREEK PLANT 3  AND  4 | Forced | 15.80 | 9.05 | SCE Gen | 
      
        | BLACK_7_UNIT 1 | JAMES B. BLACK 1 | Forced | 85.00 | 0.00 | PGAE North | 
      
        | BLACK_7_UNIT 2 | JAMES B. BLACK 2 | Forced | 84.10 | 0.00 | PGAE North | 
      
        | BLAST_1_WIND | Mountain View IV Wind | Planned/Forced | 49.00 | 0.00 | SCE Gen | 
      
        | BLKCRK_2_SOLAR1 | McCoy Station | Planned | 250.00 | 136.00 | SCE Gen | 
      
        | BORDER_6_UNITA1 | CalPeak Power Border Unit 1 | Planned | 51.25 | 3.25 | SDGE Gen | 
      
        | BUCKBL_2_PL1X3 | Blythe Energy Center | Forced | 493.00 | 0.00 | SCE Gen | 
      
        | BUCKWD_1_QF | Buckwind Re-powering project | Forced | 16.50 | 1.50 | SCE Gen | 
      
        | BUTTVL_7_UNIT 1 | BUTT VALLEY HYDRO | Planned/Forced | 40.00 | 4.00 | PGAE North | 
      
        | CARBOU_7_PL4X5 | CARIBOU PH 2 UNIT 4 & 5 AGGREGATE | Planned/Forced | 122.00 | 122.00 | PGAE North | 
      
        | CBRLLO_6_PLSTP1 | POINT LOMA SEWAGE TREATMENT PLANT | Planned | 4.83 | 0.00 | SDGE Gen | 
      
        | CCRITA_7_RPPCHF | Rancho Penasquitos Hydro Facility | Planned | 5.25 | 5.25 | SDGE Gen | 
      
        | CHINO_6_SMPPAP | SIMPSON PAPER | Planned | 44.00 | 0.00 | SCE Gen | 
      
        | CHINO_7_MILIKN | MN Milliken Genco LLC | Planned | 1.90 | 1.90 | SCE Gen | 
      
        | CNTNLA_2_SOLAR1 | Centinela Solar Energy I | Forced | 125.00 | 10.00 | SDGE Gen | 
      
        | COLEMN_2_UNIT | Coleman | Forced | 13.00 | 11.00 | PGAE North | 
      
        | COLGAT_7_UNIT 1 | COLGATE HYDRO UNIT 1 | Planned | 176.72 | 176.72 | PGAE North | 
      
        | COLGAT_7_UNIT 2 | COLGATE HYDRO UNIT 2 | Forced | 175.67 | 41.67 | PGAE North | 
      
        | COLUSA_2_PL1X3 | Colusa Generating Station | Forced | 641.00 | 15.80 | PGAE North | 
      
        | CONTRL_1_CASAD1 | Mammoth G1 | Forced | 10.00 | 2.80 | SCE Gen | 
      
        | CONTRL_1_CASAD3 | Mammoth G3 | Forced | 14.00 | 0.90 | SCE Gen | 
      
        | CRELMN_6_RAMON1 | Ramona 1 | Planned | 2.00 | 0.00 | SDGE Gen | 
      
        | CRELMN_6_RAMON2 | Ramona 2 | Planned | 5.00 | 0.00 | SDGE Gen | 
      
        | CRSTWD_6_KUMYAY | Kumeyaay Wind Farm | Forced | 50.00 | 0.00 | SDGE Gen | 
      
        | CSLR4S_2_SOLAR | Csolar IV South | Planned | 130.00 | 0.00 | SDGE Gen | 
      
        | DEVERS_1_SOLAR1 | SEPV8 | Planned | 12.00 | 0.00 | SCE Gen | 
      
        | DSABLA_7_UNIT | De Sabla Hydro | Forced | 18.50 | 18.50 | PGAE North | 
      
        | DSRTSN_2_SOLAR1 | Desert Sunlight 300 | Planned/Forced | 300.00 | 0.00 | SCE Gen | 
      
        | DVLCYN_1_UNITS | DEVIL CANYON HYDRO UNITS 1-4 AGGREGATE | Planned | 236.80 | 0.00 | SCE Gen | 
      
        | EASTWD_7_UNIT | EASTWOOD PUMP-GEN | Planned | 200.00 | 0.00 | SCE Gen | 
      
        | ELCAJN_7_GT1 | EL CAJON | Forced | 16.36 | 16.36 | SDGE Gen | 
      
        | ELDORO_7_UNIT 1 | El Dorado Unit 1 | Planned | 11.00 | 11.00 | PGAE North | 
      
        | ELDORO_7_UNIT 2 | El Dorado Unit 2 | Planned | 11.00 | 11.00 | PGAE North | 
      
        | ELECTR_7_PL1X3 | ELECTRA PH UNIT 1 & 2 AGGREGATE | Planned | 101.50 | 0.00 | PGAE North | 
      
        | ENCINA_7_EA1 | ENCINA UNIT 1 | Forced | 106.00 | 0.00 | SDGE Gen | 
      
        | ENCINA_7_EA2 | ENCINA UNIT 2 | Forced | 104.00 | 0.00 | SDGE Gen | 
      
        | ENCINA_7_EA3 | ENCINA UNIT 3 | Forced | 110.00 | 0.00 | SDGE Gen | 
      
        | ENCINA_7_EA4 | ENCINA UNIT 4 | Forced | 300.00 | 0.00 | SDGE Gen | 
      
        | ENCINA_7_EA5 | ENCINA UNIT 5 | Forced | 330.00 | 0.00 | SDGE Gen | 
      
        | ENWIND_2_WIND2 | Ridgetop I | Planned | 65.00 | 46.30 | SCE Gen | 
      
        | ESCNDO_6_UNITB1 | CalPeak Power Enterprise Unit 1 | Planned | 48.04 | 0.00 | SDGE Gen | 
      
        | ETIWND_2_FONTNA | FONTANALYTLE CREEK POWERHOUSE P | Planned | 2.56 | 2.06 | SCE Gen | 
      
        | ETIWND_6_MWDETI | ETIWANDA RECOVERY HYDRO | Planned | 24.00 | 24.00 | SCE Gen | 
      
        | ETIWND_7_MIDVLY | MN Mid Valley Genco  LLC | Planned | 2.10 | 1.00 | SCE Gen | 
      
        | ETIWND_7_UNIT 4 | ETIWANDA GEN STA. UNIT 4 | Forced | 320.00 | 70.00 | SCE Gen | 
      
        | GARNET_1_UNITS | GARNET GREEN POWER PROJECT AGGREGATE | Forced | 16.50 | 1.50 | SCE Gen | 
      
        | GARNET_1_WINDS | Garnet Winds Aggregation | Forced | 22.50 | 1.50 | SCE Gen | 
      
        | GARNET_2_WIND2 | Karen Avenue Wind Farm | Planned | 11.70 | 3.45 | SCE Gen | 
      
        | GLNARM_7_UNIT 2 | GLEN ARM UNIT 2 | Forced | 22.30 | 22.30 | SCE Gen | 
      
        | GRNLF1_1_UNITS | GREENLEAF #1 COGEN AGGREGATE | Forced | 49.50 | 0.30 | PGAE North | 
      
        | GRNLF2_1_UNIT | GREENLEAF II COGEN | Planned | 63.75 | 63.75 | PGAE North | 
      
        | HAASPH_7_PL1X2 | HAAS PH UNIT 1 & 2 AGGREGATE | Forced | 144.00 | 0.00 | PGAE North | 
      
        | HARBGN_7_UNITS | HARBOR COGEN COMBINED CYCLE | Forced | 109.01 | 9.01 | SCE Gen | 
      
        | HIDSRT_2_UNITS | HIGH DESERT POWER PROJECT AGGREGATE | Forced | 830.00 | 60.00 | SCE Gen | 
      
        | HUMBPP_1_UNITS3 | Humboldt Bay Generating Station 3 | Forced | 65.08 | 16.27 | PGAE North | 
      
        | INDIGO_1_UNIT 1 | INDIGO PEAKER UNIT 1 | Planned/Forced | 44.00 | 1.00 | SCE Gen | 
      
        | INDIGO_1_UNIT 2 | INDIGO PEAKER UNIT 2 | Planned/Forced | 44.53 | 1.53 | SCE Gen | 
      
        | INDIGO_1_UNIT 3 | INDIGO PEAKER UNIT 3 | Planned | 43.69 | 0.00 | SCE Gen | 
      
        | IVWEST_2_SOLAR1 | Imperial Valley West ( Q # 608) | Planned/Forced | 150.00 | 4.00 | SDGE Gen | 
      
        | JAWBNE_2_NSRWND | North Sky River Wind Project | Forced | 160.00 | 8.00 | SCE Gen | 
      
        | KEARNY_7_KY2 | KEARNY GT2 AGGREGATE | Forced | 59.00 | 59.00 | SDGE Gen | 
      
        | KEARNY_7_KY3 | KEARNY GT3 AGGREGATE | Forced | 61.00 | 61.00 | SDGE Gen | 
      
        | KELYRG_6_UNIT | KELLY RIDGE HYDRO | Forced | 11.00 | 11.00 | PGAE North | 
      
        | KERKH2_7_UNIT 1 | KERKHOFF PH 2 UNIT #1 | Planned | 153.90 | 153.90 | PGAE North | 
      
        | KERRGN_1_UNIT 1 | KERN RIVER HYDRO UNITS 1-4 AGGREGATE | Planned/Forced | 25.60 | 0.00 | SCE Gen | 
      
        | LAKHDG_6_UNIT 1 | Lake Hodges Pumped Storage-Unit1 | Forced | 20.00 | 20.00 | SDGE Gen | 
      
        | LARKSP_6_UNIT 1 | LARKSPUR PEAKER UNIT 1 | Forced | 46.10 | 2.10 | SDGE Gen | 
      
        | LARKSP_6_UNIT 2 | LARKSPUR PEAKER UNIT 2 | Forced | 47.98 | 3.98 | SDGE Gen | 
      
        | LAROA1_2_UNITA1 | LR1 | Forced | 180.00 | 15.00 | SDGE Gen | 
      
        | LAROA2_2_UNITA1 | LR2 | Forced | 322.00 | 17.00 | SDGE Gen | 
      
        | MANZNA_2_WIND | Manzana Wind | Forced | 189.00 | 0.00 | SCE Gen | 
      
        | MDFKRL_2_PROJCT | MIDDLE FORK AND RALSTON PSP | Planned | 218.39 | 69.00 | PGAE North | 
      
        | MONLTH_6_BOREL | BOREL HYDRO UNITS 1-3 AGGREGATE | Planned/Forced | 11.00 | 11.00 | SCE Gen | 
      
        | MOORPK_7_UNITA1 | WEME- Simi Valley Landfill | Planned | 2.49 | 0.39 | SCE Gen | 
      
        | MRCHNT_2_PL1X3 | Desert Star Energy Center | Forced | 494.58 | 4.58 | SCE Gen | 
      
        | MRGT_6_MMAREF | Miramar Energy Facility | Planned | 48.00 | 48.00 | SDGE Gen | 
      
        | MRGT_7_UNITS | MIRAMAR COMBUSTION TURBINE AGGREGATE | Forced | 36.00 | 36.00 | SDGE Gen | 
      
        | MTWIND_1_UNIT 1 | Mountain View Power Project I | Planned/Forced | 44.40 | 0.00 | SCE Gen | 
      
        | MTWIND_1_UNIT 2 | Mountain View Power Project II | Planned/Forced | 22.20 | 9.60 | SCE Gen | 
      
        | MTWIND_1_UNIT 3 | Mountain View Power Project III | Forced | 22.44 | 0.66 | SCE Gen | 
      
        | NAROW2_2_UNIT | NARROWS PH 2 UNIT | Forced | 55.00 | 55.00 | PGAE North | 
      
        | OGROVE_6_PL1X2 | Orange Grove Energy Center | Forced | 96.00 | 0.00 | SDGE Gen | 
      
        | OMAR_2_UNIT 1 | KERN RIVER COGENERATION CO. UNIT 1 | Forced | 78.00 | 1.60 | SCE Gen | 
      
        | OMAR_2_UNIT 2 | KERN RIVER COGENERATION CO. UNIT 2 | Forced | 78.11 | 0.11 | SCE Gen | 
      
        | OMAR_2_UNIT 3 | KERN RIVER COGENERATION CO. UNIT 3 | Forced | 81.41 | 1.61 | SCE Gen | 
      
        | OTAY_6_LNDFL5 | Otay 5 | Planned | 1.50 | 0.00 | SDGE Gen | 
      
        | OTMESA_2_PL1X3 | OTAY MESA ENERGY CENTER | Forced | 603.68 | 3.68 | SDGE Gen | 
      
        | PACLUM_6_UNIT | PACIFIC LUMBER (HUMBOLDT) | Forced | 28.80 | 21.80 | PGAE North | 
      
        | PADUA_2_ONTARO | ONTARIO/SIERRA HYDRO PSP | Planned | 1.92 | 1.42 | SCE Gen | 
      
        | PANDOL_6_UNIT | Covanta Delano, Inc. | Forced | 49.00 | 4.00 | SCE Gen | 
      
        | PANSEA_1_PANARO | Mesa Wind Project | Forced | 30.00 | 21.61 | SCE Gen | 
      
        | PIT1_7_UNIT 1 | PIT PH 1 UNIT 1 | Planned | 32.00 | 0.00 | PGAE North | 
      
        | PIT3_7_PL1X3 | PIT PH 3 UNITS 1, 2 & 3 AGGREGATE | Planned | 70.60 | 0.00 | PGAE North | 
      
        | PIT4_7_PL1X2 | PIT PH 4 UNITS 1 & 2 AGGREGATE | Planned/Forced | 95.00 | 0.00 | PGAE North | 
      
        | PIT5_7_PL3X4 | PIT PH 5 UNITS 3 & 4 AGGREGATE | Planned | 82.00 | 82.00 | PGAE North | 
      
        | PIT6_7_UNIT 1 | PIT PH 6 UNIT 1 | Forced | 39.00 | 0.00 | PGAE North | 
      
        | PIT6_7_UNIT 2 | PIT PH 6 UNIT 2 | Forced | 40.00 | 0.00 | PGAE North | 
      
        | PIT7_7_UNIT 1 | PIT PH 7 UNIT 1 | Forced | 55.70 | 1.70 | PGAE North | 
      
        | PIT7_7_UNIT 2 | PIT PH 7 UNIT 2 | Forced | 54.60 | 0.00 | PGAE North | 
      
        | PLAINV_6_BSOLAR | Western Antelope Blue Sky Ranch A | Forced | 20.00 | 1.00 | SCE Gen | 
      
        | POEPH_7_UNIT 1 | POE HYDRO UNIT 1 | Planned | 69.00 | 69.00 | PGAE North | 
      
        | POEPH_7_UNIT 2 | POE HYDRO UNIT 2 | Planned | 68.50 | 68.50 | PGAE North | 
      
        | POTTER_6_UNITS | Potter Valley | Planned/Forced | 10.10 | 10.10 | PGAE North | 
      
        | PWEST_1_UNIT | PACIFIC WEST 1 WIND GENERATION | Forced | 2.10 | 2.10 | SCE Gen | 
      
        | RCKCRK_7_UNIT 2 | ROCK CREEK HYDRO UNIT 2 | Planned | 56.90 | 56.90 | PGAE North | 
      
        | RECTOR_2_KAWEAH | KAWEAH PH 2 & 3 PSP AGGREGATE | Planned | 6.55 | 0.00 | SCE Gen | 
      
        | RECTOR_2_QF | RECTOR QFS | Forced | 19.50 | 0.00 | SCE Gen | 
      
        | RENWD_1_QF | Renwind re-powering project | Forced | 10.00 | 0.00 | SCE Gen | 
      
        | ROSMDW_2_WIND1 | Pacific Wind - Phase 1 | Forced | 140.00 | 10.00 | SDGE Gen | 
      
        | SAMPSN_6_KELCO1 | KELCO QUALIFYING FACILITY | Planned | 25.00 | 7.40 | SDGE Gen | 
      
        | SANTGO_6_COYOTE | GAS RECOVERY SYS. (COYOTE CANYON) | Forced | 9.99 | 7.98 | SCE Gen | 
      
        | SANWD_1_QF | San Gorgonio Farms Wind Farm | Planned | 31.00 | 2.48 | SCE Gen | 
      
        | SAUGUS_7_LOPEZ | MM Lopez Energy | Planned | 6.10 | 0.90 | SCE Gen | 
      
        | SBERDO_2_SNTANA | SANTA ANA PSP | Planned | 6.95 | 5.95 | SCE Gen | 
      
        | SBERDO_6_MILLCK | MILL CREEK PSP | Planned | 3.93 | 3.23 | SCE Gen | 
      
        | SLYCRK_1_UNIT 1 | SLY CREEK HYDRO | Forced | 13.00 | 13.00 | PGAE North | 
      
        | SNDBAR_7_UNIT 1 | SAND BAR HYDRO | Planned/Forced | 18.60 | 18.60 | PGAE North | 
      
        | SPRGVL_2_TULESC | TULE RIVER HYDRO PLANT (SCE) | Forced | 2.50 | 1.20 | SCE Gen | 
      
        | SYCAMR_2_UNIT 1 | Sycamore Cogeneration Unit 1 | Forced | 85.00 | 4.72 | SCE Gen | 
      
        | SYCAMR_2_UNIT 2 | Sycamore Cogeneration Unit 2 | Forced | 85.00 | 3.70 | SCE Gen | 
      
        | SYCAMR_2_UNIT 3 | Sycamore Cogeneration Unit 3 | Forced | 85.00 | 1.33 | SCE Gen | 
      
        | SYCAMR_2_UNIT 4 | Sycamore Cogeneration Unit 4 | Forced | 85.00 | 3.07 | SCE Gen | 
      
        | TERMEX_2_PL1X3 | TDM | Forced | 625.00 | 2.00 | SDGE Gen | 
      
        | TIFFNY_1_DILLON | TIFFNY_1_DILLON | Forced | 45.00 | 2.00 | SCE Gen | 
      
        | VALLEY_7_BADLND | VALLEY_7_BADLND | Forced | 1.30 | 1.30 | SCE Gen | 
      
        | VALLEY_7_UNITA1 | WM Energy, El Sobrante Landfill | Forced | 3.74 | 2.14 | SCE Gen | 
      
        | VESTAL_2_KERN | KERN RIVER PH 3 UNITS 1 & 2 AGGREGATE | Forced | 36.80 | 16.30 | SCE Gen | 
      
        | VINCNT_2_WESTWD | Oasis Power Plant | Planned | 60.00 | 5.00 | SCE Gen | 
      
        | WALCRK_2_CTG1 | Walnut Creek Energy Park Unit 1 | Planned | 96.43 | 0.00 | SCE Gen | 
      
        | WALCRK_2_CTG2 | Walnut Creek Energy Park Unit 2 | Planned | 96.91 | 0.00 | SCE Gen | 
      
        | WALCRK_2_CTG3 | Walnut Creek Energy Park Unit 3 | Planned | 96.65 | 0.00 | SCE Gen | 
      
        | WALCRK_2_CTG4 | Walnut Creek Energy Park Unit 4 | Planned | 96.49 | 0.00 | SCE Gen | 
      
        | WALCRK_2_CTG5 | Walnut Creek Energy Park Unit 5 | Planned | 96.65 | 0.00 | SCE Gen | 
      
        | WALNUT_7_WCOVCT | WALNUT_7_WCOVCT | Forced | 4.50 | 4.50 | SCE Gen | 
      
        | WHTWTR_1_WINDA1 | Whitewater Hill Wind Project | Forced | 61.50 | 16.50 | SCE Gen | 
      
        | WNDSTR_2_WIND | Windstar | Planned | 120.00 | 0.00 | SCE Gen | 
      
        | YUBACT_1_SUNSWT | YUBA CITY COGEN | Planned | 49.97 | 49.97 | PGAE North | 
      
        | ADERA_1_SOLAR1 | Adera Solar | Planned | 20.00 | 7.00 |  | 
      
        | ADLIN_1_UNITS | GEYSERS AIDLIN AGGREGATE | Planned | 22.00 | 6.00 |  | 
      
        | ALLGNY_6_HYDRO1 | Salmon Creek Hydroelectric Project | Forced | 0.52 | 0.52 |  | 
      
        | ANZA_6_SOLAR1 | Seville Solar One | Planned | 20.00 | 9.00 |  | 
      
        | BALCHS_7_UNIT 3 | BALCH 2 PH UNIT 3 | Planned | 54.60 | 0.00 |  | 
      
        | BCTSYS_5_PWXDYN | BCTSYS_5_PWXDYN | Forced | 428.00 | 128.00 |  | 
      
        | BDGRCK_1_UNITS | BADGER CREEK LIMITED | Forced | 47.49 | 2.99 |  | 
      
        | BEARDS_7_UNIT 1 | Beardsley Hydro | Planned | 11.50 | 0.00 |  | 
      
        | BEARMT_1_UNIT | Bear Mountain Limited | Forced | 47.49 | 1.09 |  | 
      
        | BELDEN_7_UNIT 1 | BELDEN HYDRO | Planned/Forced | 119.00 | 119.00 |  | 
      
        | BLCKBT_2_STONEY | BLACK BUTTE HYDRO | Forced | 6.20 | 0.00 |  | 
      
        | BLULKE_6_BLUELK | Blue Lake Power | Forced |  |  |  | 
      
        | BNNIEN_7_ALTAPH | ALTA POWER HOUSE | Planned | 1.00 | 0.00 |  | 
      
        | BRDSLD_2_HIWIND | High Winds Energy Center | Forced | 162.00 | 7.20 |  | 
      
        | BRDSLD_2_MTZUM2 | NextEra Energy Montezuma Wind II | Planned | 78.20 | 0.00 |  | 
      
        | BRDSLD_2_SHILO1 | Shiloh I Wind Project | Forced | 150.00 | 3.00 |  | 
      
        | BRDSLD_2_SHILO2 | SHILOH WIND PROJECT 2 | Planned | 150.00 | 8.00 |  | 
      
        | BRDSLD_2_SHLO3A | Shiloh III Wind Project, LLC | Forced | 102.50 | 8.50 |  | 
      
        | BRDSLD_2_SHLO3B | Shiloh IV Wind Project | Forced | 100.00 | 1.60 |  | 
      
        | BUCKCK_7_PL1X2 | BUCKS CREEK AGGREGATE | Planned | 59.00 | 34.00 |  | 
      
        | CAPWD_1_QF | Edom Hills Wind Farm | Forced | 19.55 | 2.05 |  | 
      
        | CHALK_1_UNIT | CHALK CLIFF LIMITED | Forced | 47.49 | 1.89 |  | 
      
        | CHWCHL_1_BIOMAS | Chow II Biomass to Energy | Planned | 10.80 | 1.30 |  | 
      
        | CLRKRD_6_LIMESD | Lime Saddle Hydro | Forced | 2.00 | 1.00 |  | 
      
        | CNTRVL_6_UNIT | Centerville | Forced | 6.40 | 6.40 |  | 
      
        | COCOPP_2_CTG1 | Marsh Landing 1 | Forced | 204.20 | 3.63 |  | 
      
        | COCOPP_2_CTG2 | Marsh Landing 2 | Forced | 202.70 | 2.98 |  | 
      
        | COCOPP_2_CTG3 | Marsh Landing 3 | Forced | 208.96 | 9.67 |  | 
      
        | COCOPP_2_CTG4 | Marsh Landing 4 | Forced | 204.29 | 3.13 |  | 
      
        | CONTAN_1_UNIT | Graphic Packaging Cogen | Forced | 27.70 | 27.70 |  | 
      
        | COTTLE_2_FRNKNH | Frankenheimer Power Plant | Forced | 5.30 | 0.00 |  | 
      
        | CSTRVL_7_PL1X2 | Marina Land Fill Gas | Planned | 4.53 | 2.53 |  | 
      
        | DALYCT_1_FCELL | PGE San Francisco State Fuel Cell | Forced | 1.60 | 1.60 |  | 
      
        | DEADCK_1_UNIT | DEADCK_1_UNIT | Forced | 2.00 | 2.00 |  | 
      
        | DELTA_2_PL1X4 | DELTA ENERGY CENTER AGGREGATE | Forced | 880.00 | 29.00 |  | 
      
        | DINUBA_6_UNIT | DINUBA GENERATION PROJECT | Forced | 12.00 | 0.00 |  | 
      
        | DOUBLC_1_UNITS | DOUBLE "C" LIMITED | Forced | 52.23 | 0.53 |  | 
      
        | DSRTSL_2_SOLAR1 | Desert Stateline | Forced | 299.99 | 276.99 |  | 
      
        | ELKCRK_6_STONYG | STONEY GORGE HYDRO AGGREGATE | Forced | 4.90 | 0.00 |  | 
      
        | ELKHIL_2_PL1X3 | ELK HILLS COMBINED CYCLE (AGGREGATE) | Forced | 551.70 | 50.70 |  | 
      
        | ELNIDP_6_BIOMAS | El Nido Biomass to Energy | Planned/Forced | 10.50 | 10.50 |  | 
      
        | ENWIND_2_WIND1 | Cameron Ridge | Planned | 47.10 | 20.40 |  | 
      
        | EXCHEC_7_UNIT 1 | EXCHEQUER HYDRO | Planned | 94.50 | 94.50 |  | 
      
        | FLOWD2_2_FPLWND | DIABLO WINDS | Forced | 18.60 | 0.00 |  | 
      
        | FORKBU_6_UNIT | HYPOWER, INC. (FORKS OF BUTTE) | Forced | 14.30 | 14.30 |  | 
      
        | FROGTN_7_UTICA | FROGTN_7_UTICA | Forced | 6.20 | 6.20 |  | 
      
        | GATWAY_2_PL1X3 | GATEWAY GENERATING STATION | Forced | 562.50 | 0.00 |  | 
      
        | GEYS11_7_UNIT11 | GEYSERS UNIT 11 (HEALDSBURG) | Forced | 74.40 | 7.40 |  | 
      
        | GEYS12_7_UNIT12 | GEYSERS UNIT 12 (HEALDSBURG) | Forced | 57.00 | 4.00 |  | 
      
        | GEYS13_7_UNIT13 | GEYSERS UNIT 13 (HEALDSBURG) | Planned/Forced | 95.00 | 10.00 |  | 
      
        | GEYS14_7_UNIT14 | GEYSERS UNIT 14 (HEALDSBURG) | Forced | 70.00 | 10.00 |  | 
      
        | GEYS16_7_UNIT16 | GEYSERS UNIT 16 (HEALDSBURG) | Forced | 85.00 | 85.00 |  | 
      
        | GEYS17_7_UNIT17 | GEYSERS UNIT 17 (HEALDSBURG) | Planned | 60.00 | 0.00 |  | 
      
        | GEYS18_7_UNIT18 | GEYSERS UNIT 18 (HEALDSBURG) | Forced | 72.00 | 72.00 |  | 
      
        | GEYS20_7_UNIT20 | GEYSERS UNIT 20 (HEALDSBURG) | Forced | 62.00 | 62.00 |  | 
      
        | GILRPP_1_PL1X2 | GILROY ENERGY CENTER UNITS 1&2 AGGREGATE | Planned | 95.40 | 0.00 |  | 
      
        | GILRPP_1_PL3X4 | GILROY ENERGY CENTER, UNIT #3 | Planned | 46.20 | 0.00 |  | 
      
        | GRIFFI_2_LSPDYN | Griffith Energy | Forced | 570.00 | 370.00 |  | 
      
        | GRNVLY_7_SCLAND | SANTA CRUZ LANDFILL GENERATING PLANT | Planned | 3.04 | 0.00 |  | 
      
        | GWFPWR_1_UNITS | HANFORD PEAKER PLANT | Forced | 98.46 | 0.47 |  | 
      
        | GYS5X6_7_UNITS | GEYSERS UNITS 5 & 6 AGGREGATE | Forced | 85.00 | 0.00 |  | 
      
        | GYS7X8_7_UNITS | GEYSERS UNITS 7 & 8 AGGREGATE | Forced | 82.00 | 4.00 |  | 
      
        | GYSRVL_7_WSPRNG | Sonoma CWA Warm Springs Hydro | Forced | 3.75 | 2.37 |  | 
      
        | HATRDG_2_WIND | Hatchet Ridge Wind Farm | Forced | 102.00 | 0.80 |  | 
      
        | HELMPG_7_UNIT 1 | HELMS PUMP-GEN UNIT 1 | Planned | 407.00 | 407.00 |  | 
      
        | HENRTA_6_UNITA1 | GWF HENRIETTA PEAKER PLANT UNIT 1 | Forced | 49.98 | 1.31 |  | 
      
        | HENRTA_6_UNITA2 | GWF HENRIETTA PEAKER PLANT UNIT 2 | Forced | 49.42 | 0.86 |  | 
      
        | HMLTBR_6_UNITS | HAMILTON BRANCH PH (AGGREGATE) | Planned/Forced | 4.90 | 4.90 |  | 
      
        | HYTTHM_2_UNITS | HYATT-THERMALITO PUMP-GEN (AGGREGATE) | Planned/Forced | 933.10 | 630.10 |  | 
      
        | INTKEP_2_UNITS | CCSF Hetch_Hetchy Hydro Aggregate | Forced | 405.00 | 110.00 |  | 
      
        | INTMNT_3_RIVERSIDE | IPPDYN | Forced | 137.00 | 1.00 |  | 
      
        | JAKVAL_6_UNITG1 | BUENA VISTA | Forced | 17.84 | 17.84 |  | 
      
        | KELSO_2_UNITS | Mariposa Energy | Forced | 196.00 | 0.00 |  | 
      
        | KERNFT_1_UNITS | KERN FRONT LIMITED | Forced | 52.40 | 0.50 |  | 
      
        | KIRKER_7_KELCYN | KELLER CANYON LANDFILL GEN FACILICITY | Forced | 3.56 | 1.91 |  | 
      
        | KRNCNY_6_UNIT | KERN CANYON | Planned | 11.50 | 1.00 |  | 
      
        | LAMONT_1_SOLAR3 | Woodmere Solar Farm | Planned/Forced | 14.99 | 0.00 |  | 
      
        | LAMONT_1_SOLAR4 | Hayworth Solar Farm | Planned | 26.66 | 0.00 |  | 
      
        | LAMONT_1_SOLAR5 | Redcrest Solar Farm | Forced | 16.66 | 0.00 |  | 
      
        | LAPAC_6_UNIT | LOUISIANA PACIFIC SAMOA | Forced | 20.00 | 20.00 |  | 
      
        | LAPLMA_2_UNIT 1 | La Paloma Generating Plant Unit #1 | Forced | 259.80 | 4.80 |  | 
      
        | LAPLMA_2_UNIT 2 | La Paloma Generating Plant Unit #2 | Forced | 260.20 | 4.20 |  | 
      
        | LAPLMA_2_UNIT 3 | La Paloma Generating Plant Unit #3 | Forced | 256.15 | 56.15 |  | 
      
        | LAPLMA_2_UNIT 4 | LA PALOMA GENERATING PLANT, UNIT #4 | Forced | 259.54 | 3.54 |  | 
      
        | LASSEN_6_AGV1 | AGV 1 | Planned | 1.80 | 1.80 |  | 
      
        | LECEF_1_UNITS | LOS ESTEROS ENERGY FACILITY AGGREGATE | Forced | 294.00 | 2.30 |  | 
      
        | LITLRK_6_SOLAR2 | Palmdale 18 | Planned | 2.00 | 0.00 |  | 
      
        | LIVOAK_1_UNIT 1 | LIVE OAK LIMITED | Forced | 47.49 | 47.49 |  | 
      
        | LMEC_1_PL1X3 | Los Medanos Energy Center AGGREGATE | Forced | 561.29 | 561.29 |  | 
      
        | LODIEC_2_PL1X2 | Lodi Energy Center | Forced | 302.58 | 10.58 |  | 
      
        | MALAGA_1_PL1X2 | Malaga Power Aggregate | Planned | 96.00 | 0.00 |  | 
      
        | MARCPW_6_SOLAR1 | Maricopa West Solar PV | Planned | 20.00 | 5.00 |  | 
      
        | MCSWAN_6_UNITS | MC SWAIN HYDRO | Planned | 10.00 | 10.00 |  | 
      
        | MENBIO_6_RENEW1 | CalRENEW - 1(A) | Forced | 5.00 | 0.50 |  | 
      
        | MERCFL_6_UNIT | MERCED FALLS | Forced | 3.50 | 3.50 |  | 
      
        | METEC_2_PL1X3 | Metcalf Energy Center | Forced | 593.16 | 8.16 |  | 
      
        | MIDWD_2_WIND1 | Windland Refresh 2 | Forced | 7.81 | 7.81 |  | 
      
        | MKTRCK_1_UNIT 1 | MCKITTRICK LIMITED | Forced | 47.49 | 1.59 |  | 
      
        | MNDOTA_1_SOLAR2 | Citizen Solar B | Planned | 5.00 | 1.00 |  | 
      
        | MOSSLD_7_UNIT 7 | MOSS LANDING UNIT 7 | Forced | 755.00 | 15.00 |  | 
      
        | MTNPOS_1_UNIT | MT.POSO COGENERATION CO. | Forced | 46.64 | 4.64 |  | 
      
        | NCPA_7_GP2UN3 | NCPA GEO PLANT 2 UNIT 3 | Planned | 42.42 | 42.42 |  | 
      
        | OAK C_7_UNIT 1 | OAKLAND STATION C GT UNIT 1 | Forced | 55.00 | 0.00 |  | 
      
        | OAK C_7_UNIT 3 | OAKLAND STATION C GT UNIT 3 | Forced | 55.00 | 0.00 |  | 
      
        | OILFLD_7_QFUNTS | Nacimiento Hydroelectric Plant | Forced | 3.80 | 3.80 |  | 
      
        | OLDRIV_6_BIOGAS | Bidart Old River 1 | Forced | 2.00 | 1.00 |  | 
      
        | OXMTN_6_LNDFIL | Ox Mountain Landfill Generating Plant | Forced | 10.62 | 1.02 |  | 
      
        | PARDEB_6_UNITS | Pardee Power House | Planned | 30.00 | 10.00 |  | 
      
        | PINFLT_7_UNITS | PINE FLAT HYDRO AGGREGATE | Planned/Forced | 210.00 | 210.00 |  | 
      
        | PITTSP_7_UNIT 6 | PITTSBURG UNIT 6 | Planned | 317.00 | 317.00 |  | 
      
        | PITTSP_7_UNIT 7 | PITTSBURG UNIT 7 | Planned | 530.00 | 130.00 |  | 
      
        | PLACVL_1_CHILIB | Chili Bar Hydro | Planned | 8.40 | 0.00 |  | 
      
        | PLAINV_6_SOLAR3 | Sierra Solar Greenworks LLC | Forced | 20.00 | 5.00 |  | 
      
        | PNCHPP_1_PL1X2 | Midway Peaking Aggregate | Forced | 119.91 | 0.00 |  | 
      
        | PNOCHE_1_UNITA1 | CalPeak Power Panoche Unit 1 | Planned | 52.01 | 4.01 |  | 
      
        | PRIMM_2_SOLAR1 | Silver State South | Planned/Forced | 250.00 | 195.00 |  | 
      
        | RAMON_2_SCEDYN | RAMON_2_SCEDYN | Planned | 471.60 | 93.60 |  | 
      
        | RICHMN_7_BAYENV | BAY ENVIRONMENTAL (NOVE POWER) | Forced | 2.50 | 2.50 |  | 
      
        | RIOBRV_6_UNIT 1 | KERN HYDRO (OLCESE) | Forced | 18.40 | 0.00 |  | 
      
        | RUSCTY_2_UNITS | Russell City Energy Center | Forced | 620.00 | 0.00 |  | 
      
        | SANTFG_7_UNITS | GEYSERS CALISTOGA AGGREGATE | Forced | 92.10 | 34.10 |  | 
      
        | SCEHOV_2_HOOVER | SCEHOV_2_HOOVER | Planned | 525.00 | 211.00 |  | 
      
        | SCHLTE_1_PL1X3 | Tracy Combined Cycle Power Plant | Forced | 332.28 | 0.68 |  | 
      
        | SIERRA_1_UNITS | HIGH SIERRA LIMITED | Forced | 52.43 | 0.73 |  | 
      
        | SKERN_6_SOLAR1 | South Kern Solar PV Plant | Forced | 20.00 | 6.00 |  | 
      
        | SLST13_2_SOLAR1 | Quinto Solar PV Project | Planned | 107.60 | 44.80 |  | 
      
        | SLUISP_2_UNITS | SAN LUIS (GIANELLI) PUMP-GEN (AGGREGATE) | Planned/Forced | 374.43 | 246.43 |  | 
      
        | SMUDGO_7_UNIT 1 | SONOMA POWER PLANT | Forced | 53.00 | 24.00 |  | 
      
        | SNMALF_6_UNITS | Sonoma County Landfill | Planned | 7.50 | 4.10 |  | 
      
        | STOILS_1_UNITS | Chevron Richmond Refinery | Forced | 113.90 | 0.00 |  | 
      
        | SUNRIS_2_PL1X3 | Sunrise Power Project AGGREGATE II | Forced | 586.02 | 6.02 |  | 
      
        | SUNSET_2_UNITS | MIDWAY SUNSET COGENERATION PLANT | Forced | 248.00 | 11.00 |  | 
      
        | SUNSHN_2_LNDFL | Sunshine Gas Producers | Forced | 20.00 | 2.00 |  | 
      
        | SWIFT_1_NAS | YERBA BUENA BATTERY | Forced | 4.80 | 4.80 |  | 
      
        | THMENG_1_UNIT 1 | Tracy Biomass | Forced | 18.50 | 18.50 |  | 
      
        | TUPMAN_1_BIOGAS | ABEC Bidart-Stockale #1 | Forced | 0.60 | 0.60 |  | 
      
        | USWND1_2_UNITS | US WIND POWER#1(WALKER) | Forced | 38.90 | 38.90 |  | 
      
        | USWND2_1_UNITS | US WIND POWER#2(PATTERSON) | Forced | 138.50 | 138.50 |  | 
      
        | USWNDR_2_SMUD | SOLANO WIND FARM | Forced | 102.18 | 3.00 |  | 
      
        | USWNDR_2_SMUD2 | Solano Wind Project Phase 3 | Forced | 127.80 | 0.00 |  | 
      
        | USWPFK_6_FRICK | GREEN RIDGE POWER LLC (FRICK) | Forced | 10.90 | 10.90 |  | 
      
        | VACADX_1_UNITA1 | CalPeak Power Vaca Dixon Unit 1 | Planned | 50.61 | 2.61 |  | 
      
        | VLYHOM_7_SSJID | Woodward Power Plant | Forced | 3.00 | 0.00 |  | 
      
        | WDFRDF_2_UNITS | WEST FORD FLAT AGGREGATE | Forced | 32.60 | 32.60 |  | 
      
        | WHEATL_6_LNDFIL | G2 ENERGY, OSTROM ROAD LLC | Forced | 3.00 | 1.50 |  | 
      
        | WISE_1_UNIT 1 | Wise Hydro Unit 1 | Planned | 14.50 | 14.50 |  | 
      
        | WNDMAS_2_UNIT 1 | BUENA VISTA ENERGY, LLC | Forced | 38.00 | 0.00 |  | 
      
        | ZOND_6_UNIT | ZOND WINDSYSTEMS INC. | Forced | 17.10 | 17.10 |  |