Day-Ahead System Summary | |||||||
Hour | DA Forecast |
DA Net Load Forecast1 |
DA Forecast plus Reserves2 |
RUC Forecast Adjustment3 |
RUC Shortfall with Forecast Adjust4 |
RUC Shortfall5 | RUC Self-Sched (PTK) Export Reduction6 |
---|---|---|---|---|---|---|---|
1 | 25,559 | 21,277 | 27,131 | 0 | 0 | 0 | 0 |
2 | 24,360 | 20,154 | 25,849 | 0 | 0 | 0 | 0 |
3 | 23,361 | 19,285 | 24,784 | 0 | 0 | 0 | 0 |
4 | 22,792 | 18,887 | 24,179 | 0 | 0 | 0 | 0 |
5 | 22,968 | 19,223 | 24,360 | 0 | 0 | 0 | 0 |
6 | 23,806 | 20,350 | 25,229 | 0 | 0 | 0 | 0 |
7 | 24,826 | 18,797 | 26,313 | 1,787 | 0 | 0 | 0 |
8 | 25,571 | 12,127 | 27,150 | 2,761 | 0 | 0 | 0 |
9 | 25,450 | 6,531 | 27,089 | 1,076 | 0 | 0 | 0 |
10 | 24,487 | 4,059 | 26,186 | 733 | 0 | 0 | 0 |
11 | 23,335 | 2,391 | 25,101 | 177 | 0 | 0 | 0 |
12 | 22,594 | 1,219 | 24,395 | 169 | 0 | 0 | 0 |
13 | 22,490 | 839 | 24,300 | 349 | 0 | 0 | 0 |
14 | 23,095 | 1,175 | 24,903 | 513 | 0 | 0 | 0 |
15 | 24,320 | 2,321 | 26,113 | 843 | 0 | 0 | 0 |
16 | 25,934 | 4,089 | 27,684 | 1,100 | 0 | 0 | 0 |
17 | 27,519 | 6,184 | 29,237 | 1,362 | 0 | 0 | 0 |
18 | 29,414 | 10,291 | 31,239 | 1,750 | 0 | 0 | 0 |
19 | 31,099 | 18,315 | 33,037 | 3,171 | 0 | 0 | 0 |
20 | 31,412 | 25,558 | 33,341 | 1,692 | 0 | 0 | 0 |
21 | 31,434 | 27,604 | 33,365 | 120 | 0 | 0 | 0 |
22 | 30,714 | 26,776 | 32,601 | 283 | 0 | 0 | 0 |
23 | 28,973 | 24,933 | 30,743 | 0 | 0 | 0 | 0 |
24 | 26,912 | 22,953 | 28,551 | 0 | 0 | 0 | 0 |
1 Day-Ahead CAISO Demand forecast minus solar and wind forecast | |||||||
2 Day-Ahead CAISO Demand forecast plus hourly operating reserve requirements | |||||||
3 Adjustment applied to the Day-Ahead load forecast | |||||||
4 RUC Shortfall that includes any operator adjustment to RUC forecast | |||||||
5 The RUC Under-supply infeasibility discounting the adjustment to Day-Ahead forecast | |||||||
6 Difference between RUC schedule and IFM schedules for export schedules supported by non-RA resources |
For any questions related to this report, please reach Market Validation and Quality Analysis at MarketValidationandQualityAnalysis@caiso.com