Day-Ahead System Summary | |||||||
Hour | DA Forecast |
DA Net Load Forecast1 |
DA Forecast plus Reserves2 |
RUC Forecast Adjustment3 |
RUC Shortfall with Forecast Adjust4 |
RUC Shortfall5 | RUC Self-Sched (PTK) Export Reduction6 |
---|---|---|---|---|---|---|---|
1 | 25,629 | 21,970 | 27,208 | 0 | 0 | 0 | 0 |
2 | 24,341 | 20,794 | 25,833 | 0 | 0 | 0 | 0 |
3 | 23,298 | 19,947 | 24,724 | 0 | 0 | 0 | 0 |
4 | 22,724 | 19,545 | 24,112 | 0 | 0 | 0 | 0 |
5 | 22,855 | 19,924 | 24,248 | 0 | 0 | 0 | 0 |
6 | 23,772 | 21,169 | 25,194 | 0 | 0 | 0 | 0 |
7 | 24,719 | 19,477 | 26,200 | 1,777 | 0 | 0 | 0 |
8 | 25,271 | 12,499 | 26,834 | 2,744 | 0 | 0 | 0 |
9 | 25,144 | 6,732 | 26,762 | 992 | 0 | 0 | 0 |
10 | 24,054 | 4,032 | 25,754 | 690 | 0 | 0 | 0 |
11 | 23,028 | 2,339 | 24,796 | 207 | 0 | 0 | 0 |
12 | 22,476 | 1,335 | 24,280 | 105 | 0 | 0 | 0 |
13 | 22,480 | 1,084 | 24,293 | 307 | 0 | 0 | 0 |
14 | 23,062 | 1,396 | 24,874 | 509 | 0 | 0 | 0 |
15 | 24,298 | 2,587 | 26,094 | 712 | 0 | 0 | 0 |
16 | 25,960 | 4,495 | 27,710 | 1,021 | 0 | 0 | 0 |
17 | 27,791 | 6,950 | 29,530 | 1,346 | 0 | 0 | 0 |
18 | 29,771 | 11,225 | 31,616 | 1,722 | 0 | 0 | 0 |
19 | 31,219 | 18,992 | 33,133 | 3,187 | 0 | 0 | 0 |
20 | 31,631 | 26,185 | 33,572 | 1,677 | 0 | 0 | 0 |
21 | 31,375 | 27,930 | 33,300 | 121 | 0 | 0 | 0 |
22 | 30,543 | 27,071 | 32,417 | 283 | 0 | 0 | 0 |
23 | 28,851 | 25,279 | 30,615 | 0 | 0 | 0 | 0 |
24 | 26,873 | 23,301 | 28,510 | 0 | 0 | 0 | 0 |
1 Day-Ahead CAISO Demand forecast minus solar and wind forecast | |||||||
2 Day-Ahead CAISO Demand forecast plus hourly operating reserve requirements | |||||||
3 Adjustment applied to the Day-Ahead load forecast | |||||||
4 RUC Shortfall that includes any operator adjustment to RUC forecast | |||||||
5 The RUC Under-supply infeasibility discounting the adjustment to Day-Ahead forecast | |||||||
6 Difference between RUC schedule and IFM schedules for export schedules supported by non-RA resources |
For any questions related to this report, please reach Market Validation and Quality Analysis at MarketValidationandQualityAnalysis@caiso.com