Day-Ahead System Summary | |||||||
Hour | DA Forecast |
DA Net Load Forecast1 |
DA Forecast plus Reserves2 |
RUC Forecast Adjustment3 |
RUC Shortfall with Forecast Adjust4 |
RUC Shortfall5 | RUC Self-Sched (PTK) Export Reduction6 |
---|---|---|---|---|---|---|---|
1 | 27,134 | 25,344 | 28,802 | 0 | 0 | 0 | 0 |
2 | 25,709 | 24,111 | 27,286 | 0 | 0 | 0 | 0 |
3 | 24,312 | 22,836 | 25,846 | 0 | 0 | 0 | 0 |
4 | 23,433 | 22,033 | 24,934 | 0 | 0 | 0 | 0 |
5 | 22,986 | 21,649 | 24,416 | 0 | 0 | 0 | 0 |
6 | 23,092 | 21,802 | 24,507 | 0 | 0 | 0 | 0 |
7 | 23,370 | 21,364 | 24,779 | 584 | 0 | 0 | 0 |
8 | 23,486 | 15,891 | 24,924 | 2,865 | 0 | 0 | 0 |
9 | 23,575 | 8,557 | 25,133 | 1,855 | 0 | 0 | 0 |
10 | 23,074 | 4,807 | 24,681 | 836 | 0 | 0 | 0 |
11 | 22,717 | 3,560 | 24,381 | 270 | 0 | 0 | 0 |
12 | 22,704 | 3,212 | 24,396 | 207 | 0 | 0 | 0 |
13 | 23,548 | 3,995 | 25,257 | 182 | 0 | 0 | 0 |
14 | 24,982 | 5,435 | 26,702 | 475 | 0 | 0 | 0 |
15 | 27,055 | 7,659 | 28,845 | 867 | 0 | 0 | 0 |
16 | 29,379 | 10,397 | 31,218 | 1,103 | 0 | 0 | 0 |
17 | 31,394 | 13,719 | 33,337 | 1,412 | 0 | 0 | 0 |
18 | 33,378 | 20,599 | 35,448 | 2,636 | 0 | 0 | 0 |
19 | 34,172 | 28,675 | 36,259 | 1,911 | 0 | 0 | 0 |
20 | 33,800 | 31,365 | 35,862 | 50 | 0 | 0 | 0 |
21 | 32,755 | 30,265 | 34,752 | 132 | 0 | 0 | 0 |
22 | 31,501 | 29,007 | 33,419 | 146 | 0 | 0 | 0 |
23 | 29,685 | 27,272 | 31,489 | 0 | 0 | 0 | 0 |
24 | 27,705 | 25,425 | 29,384 | 0 | 0 | 0 | 0 |
1 Day-Ahead CAISO Demand forecast minus solar and wind forecast | |||||||
2 Day-Ahead CAISO Demand forecast plus hourly operating reserve requirements | |||||||
3 Adjustment applied to the Day-Ahead load forecast | |||||||
4 RUC Shortfall that includes any operator adjustment to RUC forecast | |||||||
5 The RUC Under-supply infeasibility discounting the adjustment to Day-Ahead forecast | |||||||
6 Difference between RUC schedule and IFM schedules for export schedules supported by non-RA resources |
For any questions related to this report, please reach Market Validation and Quality Analysis at MarketValidationandQualityAnalysis@caiso.com