Day-Ahead System Summary | |||||||
Hour | DA Forecast |
DA Net Load Forecast1 |
DA Forecast plus Reserves2 |
RUC Forecast Adjustment3 |
RUC Shortfall with Forecast Adjust4 |
RUC Shortfall5 | RUC Self-Sched (PTK) Export Reduction6 |
---|---|---|---|---|---|---|---|
1 | 23,689 | 21,977 | 25,332 | 0 | 0 | 0 | 0 |
2 | 22,646 | 21,137 | 24,249 | 0 | 0 | 0 | 0 |
3 | 21,588 | 20,248 | 23,070 | 0 | 0 | 0 | 0 |
4 | 20,948 | 19,722 | 22,375 | 0 | 0 | 0 | 0 |
5 | 20,773 | 19,639 | 22,152 | 0 | 0 | 0 | 0 |
6 | 20,837 | 19,824 | 22,356 | 0 | 0 | 0 | 0 |
7 | 21,072 | 20,104 | 22,349 | 310 | 0 | 0 | 0 |
8 | 20,901 | 16,434 | 22,186 | 2,520 | 0 | 0 | 0 |
9 | 20,761 | 9,288 | 22,077 | 2,305 | 0 | 0 | 0 |
10 | 20,154 | 4,500 | 21,575 | 1,633 | 0 | 0 | 0 |
11 | 19,541 | 2,650 | 21,070 | 556 | 0 | 0 | 0 |
12 | 19,082 | 1,719 | 20,652 | 113 | 0 | 0 | 0 |
13 | 19,088 | 1,688 | 20,655 | 338 | 0 | 0 | 0 |
14 | 19,811 | 2,533 | 21,356 | 441 | 0 | 0 | 0 |
15 | 21,380 | 4,343 | 22,884 | 917 | 0 | 0 | 0 |
16 | 23,507 | 7,058 | 25,028 | 1,579 | 0 | 0 | 0 |
17 | 25,484 | 11,659 | 27,073 | 2,192 | 0 | 0 | 0 |
18 | 27,495 | 19,999 | 29,192 | 2,665 | 0 | 0 | 0 |
19 | 28,445 | 25,951 | 30,202 | 633 | 0 | 0 | 0 |
20 | 28,529 | 26,811 | 30,293 | 199 | 0 | 0 | 0 |
21 | 27,809 | 26,144 | 29,526 | 336 | 0 | 0 | 0 |
22 | 26,954 | 25,468 | 28,617 | 293 | 0 | 0 | 0 |
23 | 25,482 | 24,232 | 27,054 | 0 | 0 | 0 | 0 |
24 | 23,959 | 22,925 | 25,432 | 0 | 0 | 0 | 0 |
1 Day-Ahead CAISO Demand forecast minus solar and wind forecast | |||||||
2 Day-Ahead CAISO Demand forecast plus hourly operating reserve requirements | |||||||
3 Adjustment applied to the Day-Ahead load forecast | |||||||
4 RUC Shortfall that includes any operator adjustment to RUC forecast | |||||||
5 The RUC Under-supply infeasibility discounting the adjustment to Day-Ahead forecast | |||||||
6 Difference between RUC schedule and IFM schedules for export schedules supported by non-RA resources |
For any questions related to this report, please reach Market Validation and Quality Analysis at MarketValidationandQualityAnalysis@caiso.com