Notice
Aug. 29, 2023
REQUESTED ACTION
Request for Comment
CATEGORIES
Legal & Regulatory
BPM change management: Proposed revision requests and updated BPMs posted as of 8/29/2023
MESSAGE

The California ISO has posted new Proposed Revision Requests (PRRs) reflecting edits to Business Practice Manuals (BPMs). Revised BPMs that have completed the BPM change management process are posted in the BPM Library. All PRRs and related activity are publicly available through the BPM change management site.

 

BPM PRR updates are part of the ISO Daily Briefing in addition to being listed in the “Announcement” sections of the BPM change management tool. These updates include PRRs that have become available for review, upcoming BPM meetings, and comment due dates. All registered BPM users should continue to reference the BPM change management tool to see current PRR status. Subscribe to the Daily Briefing to stay up to date.

 

The PRRs listed below have an open 10-business day comment or appeal period from Aug. 29, 2023 through Sept.13, 2023.

 

New PRRs

PRR 1525 Energy Imbalance Market BPM, Emergency PRR, Emergency assistance energy transfer opt-in process

PRR 1526 Market Operations BPM, Addition of a withdrawal limit for scheduling coordinators of battery resources

PRR 1527 Market Operations BPM, Changes to automated dispatch system partial accept and T-minus 20 auto approval

PRR 1528 Settlements and Billing BPM, Created and updated multiple BPM configuration guides to accommodate energy storage enhancements phase 1 track 2 initiative

PRR 1529 Settlements and Billing BPM, Update configuration guide for intertie deviation settlement to resolve rounding issue

PRR 1530 Market Operations BPM, Changes to ancillary awards constraints and bidding requirements implemented in energy storage enhancements track 1

PRR 1531 Market Operations BPM, Two new customer market results interface reports that display market priority types

PRR 1532 Energy Imbalance Market BPM, Addition of exemption to failed-to-start rule for hydro resources

PRR 1533 Market Operations BPM, Removal of day ahead economic market priority type

PRR 1534 Market Instruments BPM, Western energy imbalance market Washington greenhouse gas enhancements

PRR 1535 Energy Imbalance Market BPM, Western energy imbalance market Washington greenhouse gas enhancements

PRR 1536 Market Operations BPM, New payment for exceptional dispatches holding state-of-charge

PRR 1537 Market Instruments BPM, New customer market results interface report that displays Hold state-of-charge exceptional dispatch data

 

ISO recommendations

PRR 1519 Managing Full Network Model BPM, Emergency PRR, Utilize North to South and South to North nomograms in all real-time markets to manage physical and market flows with all lines in service and/or outage conditions

PRR 1520 Congestion Revenue Rights BPM, Emergency PRR, Process for handling disconnected PNodes for congestion revenue rights purposes

PRR 1521 Market Operations BPM, Emergency PRR, New process to automatically adjust day ahead electronic tags to the match the energy profile to the residual unit commitment final schedule

PRR 1522 Settlements and Billing BPM, Documentation only updates to the real time energy quantity pre-calculation and metered energy adjustment factor pre-calculation for the BAResBaseScheduleEnergy variable. 

PRR 1523 Reliability Requirements BPM, Maximum import capability enhancements policy changes

PRR 1524 Market Instruments BPM, Maximum import capability enhancements

 

ISO final decisions

PRR 1515 Scheduling Coordinator Certification and Termination BPM, Adding additional clarifying information for the 24/7 grid test

PRR 1516 Market Instruments BPM, Emergency PRR, Bidding limitations for non-generating resources and default energy bid changes associated with Energy Storage Enhancements Track 1

PRR 1517 Market Instruments BPM, Transition cost bid adjustments, reference level change request clarifications, hydro default energy bid update; wholesale electricity price calculation update

PRR 1518 Metering BPM, Meter data retention

 

BPM library updates

The PRR tracking log on the ISO website lists the updated BPMs in the library.

 

The ISO may unilaterally make and implement revisions to the BPMs in emergency circumstances, as set forth in Sections 22.4.3 and 22.11 of the ISO tariff and in Section 2.6 of the BPM for BPM change management. An emergency PRR will continue through the BPM change management stakeholder process to obtain stakeholder input on the revisions and make other recommendations, as necessary.

 

Please note that affected parties must register in order to submit a PRR or written comments.

 

More information on the BPM change management process is available on the BPM webpage of the ISO website.

 

CONTACT INFORMATION

Please contact Nicole Hines at 916-597-8108 or BPM_CM@caiso.com with any questions.