The California ISO has revised the operating procedures referenced below.
1510 Pre-schedule and Checkout Validation, version 6.3, effective April 9, 2024.
Section 3.1, Task 2: Updated 17:30 Auto Adjustment timing to daily and removed all language about arranging a specific 17:30 auto adjustment run.
2210 Real-Time Market Activities, version 11.5, effective April 9, 2024.
Section 3.1.2, Real-Time Pre-Dispatch (RTPD) Description: Added second bullet for 5-minute Ancillary Service Requirement Setter (ASRS) calculation.
2210Z Effectiveness Factors - All, version 28.9, effective April 9, 2024.
- Added new 7760, Table 1D: Devers Area Generation Effectiveness - version 1.0, effective 4/04/24
- Updated version and date only for the following:
- 6110: version 13.0, effective 4/01/24
- 6140: version 7.1, effective 2/22/24
- 6140A: version 2.2, effective 2/22/24
- 6310: version 25.0, effective 4/09/24
- 7230: version 15.4, effective 4/09/24
- 7240: version 14.1, effective 4/01/24
- 7320 : version 24.6, effective 2/29/24
- 7410: version 9.4, effective 1/11/24
- 7430: version 26.1, effective 4/01/24
- 7440: version 3.1, effective 4/01/24
- 7450: version 2.8, effective 4/01/24
- 7540: version 2.1, effective 10/12/23
- 7550: version 9.2, effective 1/04/24
- 7680: version 3.2, effective 1/04/24
- 7690: version 4.1, effective 3/29/24
- 7820: version 19.0, effective 2/29/24
4420 System Emergency, version 15.6, effective April 9, 2024.
Added more detail in the Long Start Strategic Reliability Reserve Resources (LS-SRR) start-up and verification of output process.
5510 Procedure Development, Maintenance and Distribution, version 6.2, effective April 9, 2024.
Periodic Review: Minor edits based on current process changes.
The California ISO’s operating procedures are available on the Operating Procedures webpage. |