The California ISO has revised the operating procedure referenced below.
RC0630 Outage Coordination Process, version 1.3, effective Jan. 18, 2024.
Section 5: Removed option #3, as it is no longer applicable.
RC0690 PRC-012 Remedial Action Schemes, version 1.1, effective Jan. 18, 2024.
RC0690A PRC-012 Remedial Action Schemes - RAS Review Checklist, version 1.1, effective Jan. 18, 2024.
RC0690B PRC-012 Process - RAS Design Preview, version 1.1, effective Jan. 18, 2024.
RC0690C PRC-012 Remedial Action Schemes - Corrective Action Plan (CAP) and Results, version 1.1, effective Jan. 18, 2024.
Periodic Review: No content changes, only minor formatting.
The California ISO and RC West operating procedures are available on the Operating Procedures webpage.