The California ISO has posted new proposed revision requests (PRRs) reflecting edits to Business Practice Manuals (BPM). Revised BPMs that have completed the BPM change management process are posted in the BPM Library.
BPM PRR updates are part of the ISO Daily Briefing in addition to being listed in the “Announcement” sections of the BPM change management tool. These updates include PRRs that have become available for review, upcoming BPM meetings, and comment due dates. All registered BPM users should continue to reference the BPM Change Management tool to see current PRR status. Click here to sign up for the Daily Briefing.
The PRRs listed below have an open 10-business day comment or appeal period from August 3, 2021 through August 17, 2021.
New PRRs
There are no new PRRs submitted at this time.
ISO Recommendations
PRR 1361 Reliability Requirements BPM, Emergency PRR, Resource adequacy enhancement project phase 1 transition process
PRR 1362 Market Operations BPM, Emergency PRR, FERC Order 831 Phase 2 threshold logic
PRR 1363 Market Operations BPM, Trajectory between real-time dispatch intervals
PRR 1364 Reliability Requirements BPM, Correct bidding requirements for non-generating resource (non-regulation energy management)
ISO Final Decisions
PRR 1345 Market Operations BPM, Emergency PRR, Summer Readiness 2021 as it relates to Market Operations BPM and penalty prices
PRR 1348 Market Operations BPM, Emergency PRR, Description of losses impact on Point of Receive (POR) energy locational marginal prices (LMPs)
PRR 1353 Market Instruments BPM, Emergency PRR, Clarification of Dispatch Operating Target (DOT) breakdown for Eligible Intermittent Resources (EIR)
PRR 1355 Candidate CRR Holder Registration BPM, CRR holder minor revision to correct typographical errors
PRR 1356 Reliability Requirements BPM, 2022 availability assessment hours
PRR 1357 Market Instruments BPM, Emergency PRR, Market instrument changes related to FERC Order 831 Phase 2
PRR 1358 EIM BPM, Emergency PRR, Summer Readiness 2021 as it relates to EIM BPM Effective June Auto-Mirror changes
PRR 1359 Market Operations BPM, Emergency PRR, Summer Readiness 2021 as it relates to Market Operations BPM effective July penalty prices update
PRR 1360 Market Operations BPM, Emergency PRR, Summer Readiness 2021 as it relates to Market Operations BPM for effective July scheduling priorities for exports and load
BPM Library updates
The reference document on the ISO website lists the updated BPMs in the library.
The ISO may unilaterally make and implement revisions to the BPMs in emergency circumstances, as set forth in Sections 22.4.3 and 22.11 of the ISO Tariff and in Section 2.6 of the Business Practice Manual for BPM Change Management. An emergency PRR will continue through the BPM change management stakeholder process to obtain stakeholder input on the revisions and make other recommendations, as necessary.
Please note that affected parties must register in order to submit a PRR or written comments.
More information on the BPM change management process is available on the BPM webpage of the ISO website.