CAISO Board advances new procedures for connecting large loads quickly and reliably

Board-approved proposal now goes to FERC for review

FOLSOM, Calif. – The California ISO (ISO) Board of Governors has advanced a proposal to establish new procedures for making sure large loads can be connected to the grid quickly and reliably. With the Board’s approval Wednesday, the ISO will file its proposal with the Federal Energy Regulatory Commission (FERC) by its November 16 deadline. 

FERC will then determine if the proposal satisfies its June “Show Cause” order on large loads. The order directed the California ISO and five other regional grid operators and their transmission owners to demonstrate that they have the necessary rules and processes to enable large loads such as data centers and manufacturing operations to connect to the grid quickly, without compromising reliability or shifting costs to other customers. 

“Our response to the FERC order to show cause will improve planning and operational awareness of new large loads on the system, prevent cost-shifting, encourage flexibility and expedite large load energization,” said Elliot Mainzer, the ISO’s president and CEO.

Timely interconnection of large loads such as data centers has become a prominent national issue as more are being built around the country.

The ISO, in close coordination with transmission owners, state energy agencies, and local regulatory authorities, has been integrating significant amounts of new resources onto the grid over the past several years to keep pace with growing demand. The proposal approved by the Board builds on that success.

A key element of the Board-approved proposal, referred to as a “flexible interim load interconnection,” would enable large loads to interconnect quickly to the transmission system with enforceable flexibility determined by grid conditions and constraints until associated network upgrades are complete.

The proposal describes four other key areas the ISO will address to enable innovation while protecting customers and ensuring safe and reliable service:

  • Procedures to improve coordination with utilities related to load interconnection applications, studies, technical standards, and operational requirements for accurate long-term planning and near-term reliability; 
  • A framework to prevent cost shifting;
  • Parallel information and application requirements for co-located load and generation arrangements to enable full visibility to the ISO, and;
  • Consideration of future policy development to study generating facilities for loads and generation that are located in separate but proximate locations.

Specifically, related to load interconnection applications and studies, the proposal creates a new monthly window for the ISO to review any transmission additions or upgrades associated with large loads that fall outside the usual transmission planning cycle to accommodate FERC’s 60-90 day requirement for participating transmission owners’ load interconnection studies.

In addition, the ISO proposes the following technical requirements and will continue to work with the North American Electric Reliability Corporation (NERC) in the establishment of reliability standards for computational loads:

  • Require hourly forecasts, telemetry, and other operational data necessary to provide the ISO with sufficient operational visibility;
  • Utilize communication protocols for the ISO to coordinate with the participating transmission owner to remotely disconnect large loads when necessary to maintain transmission system reliability, and;
  • Establish requirements for maintaining communication channels between the ISO and transmission customers serving large loads.

“We look forward to our ongoing collaboration with our participating transmission owners, state energy agencies and industry stakeholders to make sure we stay ahead of the curve on interconnecting large loads without compromising reliability or placing an undue burden on consumers,” Mainzer added.

# # #

About the California ISO 
250 Outcropping Way, Folsom, CA 95630 | www.caiso.com

The California Independent System Operator (ISO) is a nonprofit public-benefit corporation dedicated with its partners to continuous improvement and secure operation of a reliable grid operated for the benefit of electricity consumers. The ISO provides comprehensive grid planning, open and nondiscriminatory access to one of the largest networks of high-voltage transmission power lines in the world and operates a competitive electricity market that in 2024 included $16.1 billion in transactions. In helping to carry out California’s energy policy objectives, the ISO is at the forefront of integrating renewable power and advanced technologies that will help provide a reliable and sustainable energy future efficiently and cleanly.

About the Western Energy Markets 
The Western Energy Imbalance Market (WEIM) is a real-time wholesale energy trading market that enables participants throughout the West to buy and sell energy when needed. Since its inception in 2014, it has resulted in more than $8.6 billion in financial benefits to market participants and their customers and has enhanced reliability across the region by sharing diverse resources and optimizing inter-connected transmission. The Western Energy Markets Governing Body, designed by regional stakeholders, has primary decision-making authority regarding rules specific to participation in the WEIM and Extended Day-Ahead Market.

Back to top