Skip to main content
Notice

05/04/2026

REQUESTED ACTION

Information only

CATEGORIES

Legal and regulatory
Planning

Annual Commercial Viability Criteria demonstration due 6/5/26

Generator interconnection customers that demonstrated Commercial Viability Criteria (CVC) to extend their Project’s Commercial Operation date beyond the 7/10 year allowable time-in-queue. Those customers are required to provide an annual demonstration of continued CVC. 

The annual CVC demonstration is normally due during the annual Transmission Plan (TP) Deliverability allocation/retention cycle. However, because there is no TP Deliverability allocation cycle in 2026, the annual CVC demonstration for 2026 will be due on June 5, 2026, which falls equidistant between the 2025 and 2027 TP Deliverability allocation cycles. 

For annual CVC demonstration requirements, refer to Section 6.1.5.1 of the BPM for Generator Management and the ISO Tariff Appendix DD section 6.7.4.

Contact information

Please contact QueueManagement@caiso.com with any questions.

Back to top