REQUESTED ACTION
Information onlyCATEGORIES
PlanningC15 Estimated Interconnection Facilities Study Costs and Timeframe
The California ISO, pursuant to Section 8.1.1 of the CAISO Tariff Appendix KK, has posted the non-binding updated good faith estimate of the cost of the cluster 15 interconnection facilities study in the market participant portal. This is the Instructions to gain access.
The non-binding updated good faith estimated timeframe to complete the cluster study is 120 calendar days, commencing July 3, 2026, and concluding Oct. 30, 2026.
Please review the Resource Interconnection Standards Interconnection Study Timeline for more details.
Contact information
Please contact IRInfo@caiso.com with any questions or submit a comment within the Grid Resource Interconnection Portal.