    The 2008 Generation Interconnection Process Reform (GIPR) for large generation interconnection projects which are projects greater than 20 MW was implemented in July 2008. The major elements of this reform included moving from a serial study approach (one project at a time) to a cluster study approach and also included new cost allocation methodologies for network upgrades to provide cost and schedule certainty to interconnection customers. — Implemented: Jul 28, 2008; FERC Order: Sep 26, 2008 (ER08-1317); Board of Governors approval: Jul 01, 2008