​2017 Expedited GIDAP Enhancements

The ISO has identified two interconnection issues that need expedited resolutions: 1) how long an interconnection customer may “park” for purposes of receiving a Transmission Plan Deliverability allocation; and 2) how long interconnection customers have to submit, correct, and re-submit new interconnection requests within the ISO validation timeframe.  Through this initiative the ISO proposes to change the current parking and interconnection request window and validation processes in the Generator Interconnection and Deliverability Allocation Procedures (GIDAP).

 

Outcome

The Federal Energy Regulatory Commission approved on March 9, 2018, the enhancements proposed in the Generator Interconnection and Deliverability Allocation Procedures including extending the parking provisions and revising the interconnection request window and validation timeframe. The purpose of these changes was to provide relief to generation interconnection customers impacted by the current timelines related to these items.

FERC approval: March 9, 2018
Tariff amendment filing: January 9, 2018
Board of Governors approval: December 14, 2017

Notice of decisional classification

This notice provides the ISO Board of Governors Chair and the EIM Governing Body Chair with Management's proposed decisional classification for a policy initiative, e.g., whether the initiative falls within the primary authority of the EIM Governing Body or its advisory role. This notice requirement is described in the Guidance for Handling Policy Initiatives- EIM Governing Body.

FERC filings and orders

Tariff development

Policy development